7 Notice of Contractors Settlement (1).pdf

PDF 129 KB Posted

Attached to
AFB; 2019-097M21 Refurb Ash Conveyor System Heat Plant Ph1
Solicitation number
NCS1 IHHA 2027000029 1
Issued by
Pueblo County, Colorado

About this file

This is a Notice of Contractor's Settlement issued by the Colorado Department of Human Services through the State of Colorado Office of the State Architect, State Buildings Program. The document pertains to Project No. 2019-097M21, which involves refurbishing the Ash Conveyor System and Heat Plant at the Colorado Mental Health Institute at Pueblo, Phase 2 of 2. Final settlement with the contractor, DC Power Industrial Projects LLC, is scheduled for September 14, 2026, at 4112 S. Knox Ct, Denver, Colorado. The notice provides a deadline for filing any unpaid claims related to labor, materials, equipment rental, machinery, tools, or other supplies furnished by the contractor or its subcontractors during project performance.

The settlement notice requires all creditors with unpaid claims to file verified statements with the Colorado Department of Human Services, represented by Authorized Facility Manager Karie Westphal (contact: 303-868-7131 or Karie.Westphal@state.co.us), prior to the final settlement date. Any claims not filed before September 14, 2026, will relieve the State of Colorado of all liability. The notice was approved on August 31, 2026, and published between September 2 and September 11, 2026.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SBP-6.271

07/2025

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

NOTICE OF CONTRACTOR’S SETTLEMENT

Notice Number: 1 Institution or Agency: Colorado Department of Human Services Project No./Project Name: 2019-097M21/ Refurbish Ash Conveyor System, Heat Plant, Colorado Mental Health Institute at Pueblo, Ph 2 of 2

Notice is hereby given that on 9/14/2026 at 4112 S. Knox Ct, Denver Colorado, final settlement will be made by the STATE OF COLORADO with DC Power Industrial Projects LLC , hereinafter called the "CONTRACTOR", for and on account of the contract for the construction of a PROJECT as referenced above.

1. Any person, co-partnership, association or corporation who has an unpaid claim against the said project, for or on account of the furnishing of labor, materials, team hire, sustenance, provisions, provender, rental machinery, tools, or equipment and other supplies used or consumed by such Contractor or any of his subcontractors in or about the performance of said work, may at any time up to and including said time of such final settlement, file a verified statement of the amount due and unpaid on account of such claim

2. All such claims shall be filed with the Authority for College, Institution, Department or Agency.

3. Failure on the part of a creditor to file such statement prior to such final settlement will relieve the State of Colorado from any and all liability for such claim

Authorized Facility Manager or Authorized Individual

Name: Karie Westphal Approved Date: 8/31/2026 Agency: Colorado Department of Human Sevices Phone: 303 868-7131 Email: Karie.Westphal@state.co.us

PUBLICATION DATES:

First: 9/2/26 - 9/11/26

File details come from the government source that posted it. Updated .