6WA0547 - Post Award Schedule.pdf
PDF 93 KB Posted
- Solicitation number
- 6WA0547
About this file
This is an AAAP Project Specific Advertisement (PSA) Attachment detailing the post-award schedule for a GSA lease project. The schedule establishes a 140 total working day timeline commencing within 5 working days of lease award and concluding at government acceptance of the finished space. The schedule manages the design and construction process through nine sequential activities: (1) Lessor-Provided Design Intent Drawings (10 working days), (2) Government (GSA and Client) Review and Approval (15 working days), (3) Lessor Preparation and Submission of Construction Documents (10 working days), (4) Government Review of Construction Drawings (5 working days), (5) Lessor Preparation and Submission of TI and BSAC Price Proposal (10 working days), (6) Government Review and Approval of Pricing (15 working days), (7) Government Issuance of Notice to Proceed with Construction (5 working days), (8) Lessor Completion of TI Construction and Other Required Construction Work (60 working days), and (9) Government Inspection and Acceptance of Finished Space (10 working days).
This attachment replaces the schedule referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100). The schedule applies to the management of design and construction processes for tenant improvements (TI) and building standard alterations and contingencies (BSAC) associated with the lease award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6WA0547 - Space Breakdown.pdf | ||
| 6WA0547 - Delineated Area.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (04/26)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor-Provided Design Intent Drawings 10
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings
Lessor Preparation and Submission of Construction Documents 10
Government Review of Construction Drawings 5
Lessor Preparation and Submission of the TI and BSAC Price Proposal
Government Reviews and Approves Pricing 15
Government Issues Notice to Proceed with Construction 5
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
Government Inspects and Accepts Finished Space 10
AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)
Total Work Days from Lease Award to Government Acceptance 140