Post Award Schedule - 6TX0905 (Apr. 2026) (1).docx
DOCX document 12 KB Posted
- Solicitation number
- 6TX0905
About this file
This is a Post Award Schedule document for a General Services Administration (GSA) lease solicitation for office space in Houston, Texas. The file serves as an attachment to Request for Lease Proposals (RLP) #26NAT01 and replaces the standard R100 attachment referenced in the RLP, specifically for use when reviewing section 4.01 of the Lease (L100) form.
The solicitation seeks competitive lease proposals for office space within a delineated area of Houston bounded by Highway 6, Interstate 10, N Kirkwood Road, S Kirkwood Road, and Briar Forest Drive. The required space must be between 4,941 and 5,682 ABOA (Adjusted Building Occupancy Area) square feet with 16 reserved parking spaces. The lease term is 15 years with 13 years being firm, and the amortization term is 8 years for both Tenant Improvements and Building Specific Amortized Capital. The Government is providing a Tenant Improvement Allowance of $52.48 per ABOA SF with zero Building Specific Amortized Capital. Award will be made to the lowest-priced, technically acceptable offer without negotiations. Interested parties must submit proposals through the GSA Leasing Portal at https://leasing.gsa.gov, and offerors are encouraged to submit rates for all available terms under the AAAP RLP for consideration in future requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
| Activity |
| Working Days |
| Lessor-Provided Design Intent Drawings |
| 20 |
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings
| Lessor Preparation and Submission of Construction Documents |
| 20 |
| Government Review of Construction Drawings |
| 10 |
| Lessor Preparation and Submission of the TI and BSAC Price Proposal |
| 20 |
| Government Reviews and Approves Pricing |
| 20 |
| Government Issues Notice to Proceed with Construction |
| 5 |
| Lessor Completes Construction of TIs and Completion of Other Required Construction Work |
| 60 |
| Government Inspects and Accepts Finished Space |
| 10 |
| Total Work Days from Lease Award to Government Acceptance |
| 195 |
| AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 | PSA VERSION - REV (04/26) |
| AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 | PSA VERSION - REV (10/22) |
File details come from the government source that posted it. Updated .