Post Award Schedule - 6TX0905 (Apr. 2026) (1).docx

DOCX document 12 KB Posted

Attached to
Lease of Office Space within Houston, TX. Request for Lease Proposals (RLP) #26NAT01
Solicitation number
6TX0905
Issued by

About this file

This is a Post Award Schedule document for a General Services Administration (GSA) lease solicitation for office space in Houston, Texas. The file serves as an attachment to Request for Lease Proposals (RLP) #26NAT01 and replaces the standard R100 attachment referenced in the RLP, specifically for use when reviewing section 4.01 of the Lease (L100) form.

The solicitation seeks competitive lease proposals for office space within a delineated area of Houston bounded by Highway 6, Interstate 10, N Kirkwood Road, S Kirkwood Road, and Briar Forest Drive. The required space must be between 4,941 and 5,682 ABOA (Adjusted Building Occupancy Area) square feet with 16 reserved parking spaces. The lease term is 15 years with 13 years being firm, and the amortization term is 8 years for both Tenant Improvements and Building Specific Amortized Capital. The Government is providing a Tenant Improvement Allowance of $52.48 per ABOA SF with zero Building Specific Amortized Capital. Award will be made to the lowest-priced, technically acceptable offer without negotiations. Interested parties must submit proposals through the GSA Leasing Portal at https://leasing.gsa.gov, and offerors are encouraged to submit rates for all available terms under the AAAP RLP for consideration in future requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity
Working Days
Lessor-Provided Design Intent Drawings
20

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents
20
Government Review of Construction Drawings
10
Lessor Preparation and Submission of the TI and BSAC Price Proposal
20
Government Reviews and Approves Pricing
20
Government Issues Notice to Proceed with Construction
5
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
60
Government Inspects and Accepts Finished Space
10
Total Work Days from Lease Award to Government Acceptance
195