ad attachment - RLP and lease change.pdf
PDF 80 KB Posted
- Attached to
- Lease of Office Space within Philadelphia, PA. Request for Lease Proposals (RLP) #26NAT02
- Solicitation number
- 6PA0364
About this file
This is a Request for Lease Proposals (RLP) amendment for office space in Philadelphia, PA, issued by GSA under solicitation #26NAT02 and document number 6PA0364. The amendment modifies Paragraph 1.05 of the RLP (R100_AAAP) and Paragraph 4.01 of the Lease (L100_AAAP) to establish a detailed construction schedule replacing the previous "AAAP Construction Schedule." All timeframes are specified in working days and include design, approval, construction document preparation, bidding, and construction phases.
The revised schedule establishes a sequential process beginning with a design kick-off meeting 10 days after lease award, followed by lessor-provided design intent drawings (20 days) and government review and approval (15 days). The schedule continues through multiple construction document submission phases at 65%, 95%, and 100% completion levels, with government review periods of 15 days for each phase. The lessor must prepare and submit tenant improvement (TI) and Building Standard and Common Area (BSAC) price proposals within 30 days, with a 15-day government review period and opportunity for revised bids. Construction commencement begins 10 days after the construction kick-off meeting, with the lessor allocated 130 days for completion of tenant improvements and other required construction work. The final acceptance phase includes a 5-day inspection and punchlist generation period followed by 15 days for punchlist completion. The amendment also establishes that in any conflict between standard Lease Section 5 language and tenant special requirements, the more stringent tenant requirements will prevail.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lease of Office Space in Philadelphia, PA - Request for Lease Proposals (RLP)
#26NAT02
6PA0364 RLP & Lease Changes:
Paragraph 1.05 of the RLP (R100_AAAP) and Paragraph 4.01 of the Lease (L100_AAAP) is hereby modified to remove the “AAAP Construction Schedule” and replace it as follows. Note that “Days” are defined as “Working Days”.
· Design Kick Off Meeting with Lessor, GSA & Agency (after lease Award): 10 DAYS
· Lessor-Provided Design Intent Drawings (DIDs): 20 DAYS
· Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings: 15 DAYS
· Lessor Corrects/Finalizes DIDs: 10 DAYS
· Lessor Prepares and Submits 65% CDs: 20 DAYS
· Government Reviews 65% CDs: 15 DAYS
· Lessor Prepares and Submits 95% CDs: 20 DAYS
· Government Review of 95% CDs: 15 DAYS
· Lessor Prepares and Submits Updated CDs 100%: 10 DAYS
· Final Review by GSA/Agency: 10 DAYS
· Lessor Preparation and Submission of the TI and BSAC Price Proposal: 30 DAYS
· Government reviews TI/BSAC Bids and Provides Comments: 15 DAYS
· Lessor Submits Revised TI Bids: 10 DAYS
· Government Reviews Revised TI Bids and Provides Additional Comments (if needed): 10
DAYS
· Construction Kick Off Meeting: 10 DAYS
· Lessor Completes Construction of TIs and Completion of Other Required Construction Work: 130 DAYS
· Acceptance Inspection/Generate Punchlist: 5 DAYS
· Punchlist Completed: 15 DAYS
In the event of a conflict between the Lease (L100) Section 5 general language and the tenant’s special requirements, the more stringent tenant requirements will be adhered to.