About this file

This is a Post-Award Schedule attachment for an AAAP (Acquire America Act Project) federal lease solicitation that outlines the timeline for design and construction activities following lease award.

The schedule establishes a 140 working-day timeline commencing within 5 working days of lease award, governing the design and construction process through government acceptance of the space. Key milestones include: Lessor-Provided Design Intent Drawings (10 days), Government (GSA and Client) Review and Approval (15 days), Lessor Preparation and Submission of Construction Documents (10 days), Government Review of Construction Drawings (5 days), Lessor Preparation and Submission of TI and BSAC Price Proposal (10 days), Government Reviews, Negotiates, and Approves Pricing (15 days), Government Issues Notice to Proceed (5 days), Lessor Obtains Construction Permit (30 days), Lessor Completes Construction of TIs and Other Required Work (30 days), Government Inspection of Finished Space (5 days), and Lessor Completion of Punchlist with Government Acceptance (5 days). This attachment replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100).

View the file

Other files

File Type Posted
6MO0265 - Space Breakdown.pdf PDF
6MO0265_Delineated Area.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 10

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 15

Lessor Preparation and Submission of Construction Documents 10

Government Review of Construction Drawings 5

Lessor Preparation and Submission of the TI and BSAC Price Proposal 10

Government Reviews, Negotiates, and Approves Pricing 15

Government Issues Notice to Proceed with Construction 5

Lessor Obtains Construction Permit 30

Lessor Completes Construction of TIs and Completion of Other Required Construction Work 30

Government Inspects Finished Space 5

Lessor Completes Punchlist and Government Accepts Finished Space 5

Total Work Days from Lease Award to Government Acceptance 140

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)