6KS0113 - Post Award Schedule .pdf
PDF 59 KB Posted
- Attached to
- Lease of Office Space in Multiple Cities, Kansas - Request for Lease Proposals (RLP) #26NAT01 - Office Space
- Solicitation number
- 6KS0113
About this file
This is a Project Specific Advertisement (PSA) attachment detailing the post-award schedule for a General Services Administration (GSA) lease project. The schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100). The post-award schedule commences within 5 working days of lease award and governs the design and construction process through acceptance of the space.
The schedule comprises 12 sequential activities spanning a total of 140 working days from lease award to government acceptance. Key activities and their durations include: Lessor-Provided Design Intent Drawings (10 days), Government review and approval of design intent drawings (15 days), Lessor preparation and submission of construction documents (10 days), Government review of construction drawings (5 days), Lessor preparation and submission of Tenant Improvement (TI) and Building Standard Allowance (BSAC) price proposal (10 days), Government review, negotiation, and approval of pricing (15 days), Government issuance of Notice to Proceed (5 days), Lessor obtainment of construction permit (30 days), Lessor completion of TI construction and other required construction work (30 days), Government inspection of finished space (5 days), and Lessor completion of punchlist with Government acceptance (5 days). This schedule establishes firm expectations for all parties involved in the lease procurement and buildout process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6KS0113 - Space Breakdown.pdf | ||
| 6KS0113 - Kansas City_ KS Delineated area.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor-Provided Design Intent Drawings 10
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 15
Lessor Preparation and Submission of Construction Documents 10
Government Review of Construction Drawings 5
Lessor Preparation and Submission of the TI and BSAC Price Proposal 10
Government Reviews, Negotiates, and Approves Pricing 15
Government Issues Notice to Proceed with Construction 5
Lessor Obtains Construction Permit 30
Lessor Completes Construction of TIs and Completion of Other Required Construction Work 30
Government Inspects Finished Space 5
Lessor Completes Punchlist and Government Accepts Finished Space 5
Total Work Days from Lease Award to Government Acceptance 140
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)
File details come from the government source that posted it. Updated .