6CA1168 - Post-Award Schedule.pdf
PDF 93 KB Posted
- Solicitation number
- 6CA1168
About this file
This document is an AAAP (Alternative Approach to Awarding Property) Project Specific Advertisement attachment that establishes the post-award schedule for a GSA lease project involving tenant improvement (TI) construction and building standard alterations and construction (BSAC).
The schedule commences within 5 working days of lease award and outlines a sequential 140 working-day process from lease award to government acceptance of the finished space. Key activities and their durations include: Lessor-Provided Design Intent Drawings (10 days), Government review and approval of design drawings (15 days), Lessor preparation and submission of construction documents (10 days), Government review of construction drawings (5 days), Lessor preparation and submission of TI and BSAC price proposal (10 days), Government review and approval of pricing (15 days), Government issuance of Notice to Proceed (5 days), Lessor completion of construction work (60 days), and Government inspection and acceptance of finished space (10 days). This attachment replaces the attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (04/26)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor-Provided Design Intent Drawings 10
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings
Lessor Preparation and Submission of Construction Documents 10
Government Review of Construction Drawings 5
Lessor Preparation and Submission of the TI and BSAC Price Proposal
Government Reviews and Approves Pricing 15
Government Issues Notice to Proceed with Construction 5
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
Government Inspects and Accepts Finished Space 10
AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)
Total Work Days from Lease Award to Government Acceptance 140