Text version

Port Steering Gear Hydraulic Pump ‐ 2018

SR No 5189039 – Port Steering Hydraulic Pump

ABSTRACT

This item describes the repair to the Port Steering Gear Hydraulic Pump that has a leak and needs to be repaired by an OEM certified repair shop

REFERENCES

Port Steering Gear Hydraulic Pump Nameplate Data:

Mfgr: Denison – DO 2314

Model No: 023.03694

Serial No: 86E01-9383

ITEM LOCATION / DESCRIPTION

Location:

Steering Gear Room

Description:

Isolate electrically and hydraulically the Port Steering Gear Remove the hydraulic pump from service and blank off all lines Transport pump to shop for repairs Transport pump from shop to ship Reinstall pump and bleed system with CE Test run to satisfaction of CE

STATEMENT OF WORK

Contractor to Tag out and isolate the Port Steering Gear Hydraulic pump to all removal of same with the crew as overseen by the Chief Engineer.

Contractor to Supply all labor, material, rigging and transportation and rigging to remove the Port Steering Gear Hydraulic pump from service and transport same to the shop for repairs.

Upon completion of the repairs, Contractor to transport repaired pump to ship for reinstallation.

Contractor to supply all new gaskets and cleaned and lubricated fasteners to allow for reinstallation of the hydraulic pump. Alignment of the coupling to be tested and approved by Chief Engineer.

Port Steering Gear Hydraulic Pump ‐ 2018

After reinstallation, bleed the system to allow the repaired pump to be filled with hydraulic oil in preparation for testing

Once all the connections are made up, CE will test the pump for operation and leaks

DELIVERABLES:

Supply hard copy of shop notes and comments of pump repair to Chief Engineer and electronic copy to Chief Engineer and COTR

ADDITIONAL WORK AND SUPPLEMENTARY

Contractor to submit a written Condition Found report (CFR) to the COTR for any additional work outside the contract. Approval for additional work must be approved by either the COTR ($5000 or less) or the Contracting Officer (over $5000)

Contractor to provide cost breakdowns as they relate to labor, material, subcontractors and travel costs, if applicable. Supplementary costs must be approved by COTR by written CFR, RFQ, Quotation and Delivery Order process.

Supplementary Labor

15hrs @ $___/hr = $_________

Supplementary Material

$5,000