This document is an Amendment (A001) to a Request for Proposal (RFP) for an Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple-Award Task Order Contract (MATOC) for Expedited California Road & Bridge Construction, issued by the Federal Highway Administration's Central Federal Lands Highway Division. The solicitation (No. 6982AF25R000003) seeks multiple contractors to perform road and bridge construction projects in rural mountainous or environmentally sensitive areas, with individual task orders anticipated to range from $1,000,000 to $25,000,000. The contract will have a 1-year base period with two 2-year option periods, and a maximum shared capacity value of $250,000,000.
The amendment extends the proposal due date to 10/23/2025 and revises the evaluation criteria for Technical Evaluation Factor 1, which focuses on the prime contractor's recent and relevant experience. Contractors must demonstrate three public agency road construction contracts from the past six years, with at least one contract exceeding $10 million and two contracts exceeding $5 million. Each project must include a minimum of five construction elements (such as roadway reconstruction, bridge construction, and excavation) and two operational elements (like working in rural mountainous terrain or managing traffic control). The government will evaluate submissions to determine if contractors meet the specified requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment A003.pdf | ||
| Amendment A002.pdf | ||
| QnA 10 16 2025.pdf | ||
| QnA 10 3 2025.pdf | ||
| QnA 9 18 2025.pdf | ||
| 6982AF25R000003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
A001
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE, SUITE 360
LAKEWOOD, COLORADO 80228
9A. AMENDMENT OF SOLICITATION NUMBER
6982AF25R000003
5. PROJECT NUMBER (If applicable)
EXP CA ROAD&BRIDGE
09/18/2025
9B. DATED (SEE ITEM 11)
09/08/2025
0*
*See Item 14
Request for Proposal Remove and replace page A-1 and A-11 with the attached new pages. The evaluation criteria has been revised and the due date has been extended to 10/23/2025.
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. X
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration or Repair)
1. SOLICITATION NO.
6982AF25R000003
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
09/08/2025
PAGE OF
PAGES
IMPORTANT - THE "OFFER SECTION ON THE REVERSE MUST BE FULLY COMPLETED BY OFFEROR.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
EXPEDITED CALIFORNIA ROAD& BRIDGE
CONSTRUCTION
7. ISSUED BY:
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS DIVISION
12300 WEST DAKOTA AVENUE, SUITE 167
LAKEWOOD, COLORADO 80228
CODE: 69050001 8. ADDRESS OFFER TO:
Jorey Deml, Contract Specialist Federal Highway Administration Central Federal Lands Division Office 12300 W. Dakota Avenue Lakewood, CO 80228
9. FOR INFORMATION CALL
SEE PAGE A-3
A. NAME:
SEE PAGE A-3
B. TELEPHONE NO. (Include area code)
SEE PAGE A-3
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:
Indefinite Delivery/Indefinite Quantity Multiple-Award Task Order Contract (MATOC) for Expedited California Road & Bridge
Construction.
MATOC contracts will be for a 1-year base and two 2-year option periods. Individual projects will be issued as Task Orders. The
Government anticipates individual Task Orders ranging from $1,000,000 to $25,000,000. Each minimum guarantee will be for
$10,000.00 and the maximum value of the MATOC will not exceed $250,000,000.00 shared capacity.
11. The Contractor shall begin performance within 10 calendar days and complete it within * calendar days after receiving award notice to proceed. The performance period is mandatory negotiable. *Refer to Subsection 108.01 as amended in the Special Contract Requirements.
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.) YES NO
12B. CALENDAR DAYS
Required on a Task
Order basis
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8. by 2:00 p.m. (hour) local time on 10/09/25 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is is not required for MATOC base contract. (Required for Task Order awards)
C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA
FAR (48 CFR) 53.236-1(d)
X
X
X
X
X
A-1 Amendment A001 09/18/2025 jorey.deml Cross-Out jorey.deml Typewritten Text 10/23/25
A-11
TECHNICAL EVALUATION FACTOR 1 – PROPOSED PRIME CONTRACTOR RECENT AND
RELEVANT EXPERIENCE
Projects submitted for this factor must meet the requirements defined below and the contractor must have been the prime contractor for the project.
Requirements
A brief narrative of three Public Agency contracts as a prime contractor over the past six years that consist of road construction projects with the below Construction Elements in rural mountainous terrain or other environmentally and culturally historic sensitive areas similar to national parks or national forests. At least one contract must exceed $10 million (2025 dollars) and the remaining two contracts must exceed $5 million (2025 dollars). Each individual project must include a minimum of five construction elements and two operational elements. Identify the elements that were part of the project.
Construction Elements
(1) Roadway reconstruction, rehabilitation
(2) Bridge Construction
(3) Roadway excavation, rock embankment or embankment construction
(4) MSE Walls
(5) Reinforced Soil Slopes / Deep patches
(6) Culvert and drainage construction
(7) Asphalt Concrete Paving
(8) Roadway aggregate
(9) Trail Construction
(10) Clearing and grubbing
(11) Parking lot construction
Operational Elements
(1) Work in rural mountainous terrain or other environmentally and culturally historic sensitive areas similar to national parks or national forests
(2) Demonstrated ability to access project sites with unique mobilization challenges
(3) Performance within constricted work areas such as steep slopes or narrow roadway benches
(4) Performance that required traffic control management with delay restrictions
Evaluation Process
The Government will review the documents submitted to ensure the contractor meets the requirements listed above.
The Government may contact the contracting agency/private company to verify the submitted information. The Government will evaluate Factor 1 according to the following rating criteria.
Rating
Technically Acceptable. Based on the Government’s review, the contractor:
Amendment A001 09/18/2025