Bid Opening Summary Sched A TX FW LAAT 10(4) Ocelot Crossing.pdf
PDF 115 KB Posted
- Attached to
- TX FW LAAT 10(4) OCELOT CROSSINGS
- Solicitation number
- 6982AF25B000002
About this file
This is a bid opening summary document for the Ocelot Crossing project (TX FW LAAT 10(4)) that was opened on December 19, 2024, at 2:00 p.m. MST in Lakewood, CO. The document records two submitted bids: Construction Solutions Group, LLC from St. Louis, MO bid $2,395,430.00, and C-A Native Constructors from Muskogee, OK bid $1,928,394.00. The Engineer's Estimate for the project was $1,965,000.00.
The project relates to a Federal Highway Administration contract for installing GRS-IBS bridges at Laguna Atascosa National Wildlife Refuge in Cameron County, Texas. C-A Native Constructors submitted the lowest bid, coming in approximately $37,000 below the Engineer's Estimate, while Construction Solutions Group's bid was approximately $430,000 above the estimate. The document notes that all bids are subject to verification, and there were no amendments to the original solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Opening Summary
Project Name: Ocelot Crossing Project Number: TX FW LAAT 10(4) Bid Opening Date: 12/19/2024 Time: 2:00 p.m. MST Bid Opening Location: Lakewood, CO Bid Opening Officer: Kelly Palmer
Amendments: N/A
Bidder Name Schedule A BID TOTAL Construction Solutions Group, LLC.
425 Highlands Ave.
St. Louis MO
$2,395,430.00 $2,395,430.00
C-A Native Constructors 4000 E. Harris Rd.
Muskogee OK
$1,928,394.00 $1,928,394.00
Engineer’s Estimate
$1,965,000.00 $1,965,000.00
*All bids are subject to verification.