A002.pdf
PDF 2 MB Posted
- Solicitation number
- 6982AF23B000022
About this file
This federal contract solicitation seeks proposals for emergency road repairs on Generals Highway and Mineral King Road within Sequoia and King's Canyon National Park. The scope of work includes reinforced shotcrete facing for eight mechanically stabilized earth walls, curb repairs, and various guardrail repairs. Principal work items are 2,210 square yards of reinforced shotcrete, 45 cubic yards of concrete, five type MGS tangent terminal sections, and lump sum temporary traffic control. The estimated total cost range is $700,000 to $2,000,000. This opportunity is a total small business set-aside being issued by the Department of Transportation Federal Highway Administration. Proposals are due by July 20, 2023.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
NOTICE TO BIDDERS
A-ii
Notice of SAM Registration – you must be registered in the System for Award Management (SAM) prior to submission of a bid in response to this solicitation. Failure to register prior to submission of a bid may require award to the next successful registered offeror. See FAR Subpart
4.1102. Register online at www.sam.gov.
Representations and Certifications – This solicitation is issued under NAICS 237310 – Highway, Street & Bridge Construction with a small business size standard of $45 million. If your average annual gross receipts for the past 5 years are above $45 million, you are a large business for this solicitation. If they are below $45 million you are a small business. Before submitting bids, you must ensure you have completed your annual representations and certifications electronically at the SAM website at www.sam.gov. Include NAICS 237310 in your SAM profile.
Vets-4212 Reporting: - The Contractor must complete the report if required. See reporting requirements at: https://www.dol.gov/agencies/vets/contractor/instructions-for-electronic-submission-vets-4212-reports.
• My firm had a qualifying Federal Contract in 2022 and has complied with the reporting requirements.
• My firm did not have a qualifying Federal Contract in 2022 and is therefore exempt from the reporting requirements
Bid Guarantee – Follow the requirements of FAR Clause 52.228-1 Bid Guarantee and Subpart
102.03 of the FP-14. Bid bonds must be originals and have original signatures and corporate seals.
Photocopied and faxed copies of bonds will be rejected and cause your bid to be non-responsive.
Accuracy and Completeness of Bid- The Contractor is fully responsible to verify that all data is correct when an offer is submitted. Failure to properly update your data may cause the offer to be rejected.
Request for Technical Information – Questions relative to the plans and SCRs for this solicitation will only be accepted in writing (see Item 9 on Page A-3).
TECHNICAL QUESTIONS REGARDING THIS SOLICITATION WILL NOT BE
ACCEPTED AFTER 4 P.M. ON JULY 14, 2023
Questions can be submitted to CFLContracts@dot.gov. Questions and answers will be posted at https://sam.gov
Modifications to Bids - Bids may be modified or withdrawn by regular mail, electronic commerce (email) or facsimile, if such notice is received prior to the time specified for receipt of bids. The Government will not be responsible for ANY failure attributable to the transmission or receipt of electronic commerce (email) or facsimile data.
For all modifications, we STRONGLY ENCOURAGE you to resubmit the entire bid schedule
Amendment A001 http://www.sam.gov/ http://www.sam.gov/ mailto:CFLContracts@dot.gov https://sam.gov/
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration or Repair)
1. SOLICITATION NO.
6982AF23B000022
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
06/8/2023
PAGE OF
PAGES
IMPORTANT - THE "OFFER SECTION ON THE REVERSE MUST BE FULLY COMPLETED BY OFFEROR.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
HFLCEO230313PR
6. PROJECT NO.
CA ERFO NP SEKI 2021-1(1)
7. ISSUED BY:
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS DIVISION
12300 WEST DAKOTA AVENUE, SUITE 167
LAKEWOOD, COLORADO 80228
CODE: 69050001 8. ADDRESS OFFER TO:
Ryan Phillips, Contract Specialist Federal Highway Administration Central Federal Lands Division Office 12300 W. Dakota Avenue Lakewood, CO 80228
9. FOR INFORMATION CALL
SEE PAGE A-3
A. NAME:
SEE PAGE A-3
B. TELEPHONE NO. (Include area code)
SEE PAGE A-3
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:
ROADWAY CONSTRUCTION PROJECT IN STRICT ACCORDANCE WITH:
1. FEDERAL ACQUISITION AND TRANSPORATION ACQUISITION REGULATIONS (FAR & TAR)
2. DEPARTMENT OF LABOR, CONSTRUCTION WAGE RATE REQUIREMENT RATES
3. SPECIAL CONTRACT REQUIREMENTS
4. PLANS
5. BID SCHEDULE
6. STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY
PROJECTS, FP-14, U.S. CUSTOMARY UNITS
See Subsection 104.04 of the FP-14 for governing order of precedence
11. The Contractor shall begin performance within 10 calendar days and complete it within * calendar days after receiving award notice to proceed. The performance period is mandatory negotiable. *Refer to Subsection 108.01 as amended in the Special Contract Requirements.
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.) YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8. by 2:00 p.m. (hour) local time on 7/20/23 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is is not required.
C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA
FAR (48 CFR) 53.236-1(d)
X
X
X
X
X
A-1 Amendment A001
"General Decision Number: CA20230021 04/21/2023
Superseded General Decision Number: CA20220021
State: California
Construction Types: Heavy (Heavy and Dredging) and Highway
County: Tulare County in California.
DREDGING (excluding self-propelled hopper dredge work), HEAVY (excluding water well drilling), AND HIGHWAY CONSTRUCTION
PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $16.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2023. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.15 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2023. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
D-1 Amendment A002
0 01/06/2023 1 01/13/2023 2 03/03/2023 3 03/17/2023 4 03/31/2023 5 04/21/2023
ASBE0016-006 01/01/2021
Rates Fringes
Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not)....$ 30.45 10.60
ASBE0016-010 02/01/2023
Rates Fringes
Asbestos Workers/Insulator (Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems).....$ 62.26 23.82
BOIL0549-004 01/01/2021
Rates Fringes
BOILERMAKER......................$ 45.60 38.99
BRCA0003-001 08/01/2022
Rates Fringes
MARBLE FINISHER..................$ 39.20 18.31
BRCA0003-016 04/01/2022
Rates Fringes
TILE FINISHER....................$ 29.89 16.80
TILE LAYER.......................$ 45.78 19.92
BRCA0003-017 07/01/2022
Rates Fringes
TERRAZZO FINISHER................$ 41.93 18.98
TERRAZZO WORKER/SETTER...........$ 56.84 27.53
* BRCA0004-005 05/01/2020
Rates Fringes
BRICKLAYER; MARBLE SETTER........$ 41.52 18.47
D-2 Amendment A002
*The wage scale for prevailing wage projects performed in Blythe, China lake, Death Valley, Fort Irwin, Twenty-Nine Palms, Needles and 1-15 corridor (Barstow to the Nevada State Line) will be Three Dollars ($3.00) above the standard San Bernardino/Riverside County hourly wage rate
CARP0034-002 07/01/2021
Rates Fringes
Diver Assistant Tender, ROV Tender/Technician...........$ 54.10 34.69 Diver standby...............$ 60.51 34.69 Diver Tender................$ 59.51 34.69 Diver wet...................$ 103.62 34.69 Manifold Operator (mixed gas)........................$ 64.51 34.69 Manifold Operator (Standby).$ 59.51 34.69
DEPTH PAY (Surface Diving):
050 to 100 ft $2.00 per foot 101 to 150 ft $3.00 per foot 151 to 220 ft $4.00 per foot 221 ft.-deeper $5.00 per foot
SATURATION DIVING:
The standby rate shall apply until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. The diver rate shall be paid for all saturation hours.
DIVING IN ENCLOSURES:
Where it is necessary for Divers to enter pipes or tunnels, or other enclosures where there is no vertical ascent, the following premium shall be paid: Distance traveled from entrance 26 feet to 300 feet: $1.00 per foot. When it is necessary for a diver to enter any pipe, tunnel or other enclosure less than 48"" in height, the premium will be $1.00 per foot.
WORK IN COMBINATION OF CLASSIFICATIONS:
Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.
CARP0034-003 07/01/2021
Rates Fringes
Piledriver.......................$ 54.10 34.69
CARP1109-002 07/01/2020
Rates Fringes
Carpenters Bridge Builder/Highway Carpenter...................$ 52.65 30.82 Hardwood Floorlayer, Shingler, Power Saw
D-3 Amendment A002
Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 45.57 30.82 Journeyman Carpenter........$ 45.42 30.82 Millwright..................$ 47.92 32.41
ELEC0100-001 03/01/2023
Rates Fringes
ELECTRICIAN......................$ 43.50 27.655
ELEC1245-001 06/01/2022
Rates Fringes
LINE CONSTRUCTION
(1) Lineman; Cable splicer..$ 64.40 22.58
(2) Equipment specialist (operates crawler tractors, commercial motor vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment).............$ 50.00 21.30
(3) Groundman...............$ 38.23 20.89
(4) Powderman...............$ 51.87 18.79
HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day
ENGI0003-006 06/29/2020
Rates Fringes
OPERATOR: Power Equipment
(AREA 1:)
GROUP 1.....................$ 51.42 31.15
GROUP 2.....................$ 49.89 31.15
GROUP 3.....................$ 48.41 31.15
GROUP 4.....................$ 47.03 31.15
GROUP 5.....................$ 45.76 31.15
GROUP 6.....................$ 44.44 31.15
GROUP 7.....................$ 43.30 31.15
GROUP 8.....................$ 42.16 31.15
GROUP 8-A...................$ 39.95 31.15
OPERATOR: Power Equipment (Cranes and Attachments -
AREA 1:)
GROUP 1
Cranes.....................$ 52.30 31.15 Oiler......................$ 43.79 31.15 Truck crane oiler..........$ 46.08 31.15
GROUP 2
Cranes.....................$ 50.54 31.15 Oiler......................$ 42.83 31.15 Truck crane oiler..........$ 45.07 31.15
GROUP 3
Cranes.....................$ 48.80 31.15 Hydraulic..................$ 44.44 31.15 Oiler......................$ 42.55 31.15 Truck crane oiler..........$ 44.83 31.15
D-4 Amendment A002
GROUP 4
Cranes.....................$ 44.83 31.15 OPERATOR: Power Equipment (Piledriving - AREA 1:)
GROUP 1
Lifting devices............$ 52.64 31.15 Oiler......................$ 43.38 31.15 Truck crane oiler..........$ 45.66 31.15
GROUP 2
Lifting devices............$ 50.82 31.15 Oiler......................$ 43.11 31.15 Truck crane oiler..........$ 45.41 31.15
GROUP 3
Lifting devices............$ 49.14 31.15 Oiler......................$ 42.89 31.15 Truck crane oiler..........$ 45.12 31.15
GROUP 4
Lifting devices............$ 47.47 31.15
GROUP 5
Lifting devices............$ 44.73 31.15
GROUP 6
Lifting devices............$ 42.50 31.15 OPERATOR: Power Equipment (Steel Erection - AREA 1:)
GROUP 1
Cranes.....................$ 53.27 31.15 Oiler......................$ 43.72 31.15 Truck Crane Oiler..........$ 45.95 31.15
GROUP 2
Cranes.....................$ 51.50 31.15 Oiler......................$ 43.45 31.15 Truck Crane Oiler..........$ 45.73 31.15
GROUP 3
Cranes.....................$ 50.02 31.15 Hydraulic..................$ 45.07 31.15 Oiler......................$ 43.23 31.15 Truck Crane Oiler..........$ 38.71 31.15
GROUP 4
Cranes.....................$ 48.00 31.15
GROUP 5
Cranes.....................$ 46.70 31.15 OPERATOR: Power Equipment (Tunnel and Underground Work
- AREA 1:)
SHAFTS, STOPES, RAISES:
GROUP 1....................$ 47.52 31.15
GROUP 1-A..................$ 49.99 31.15
GROUP 2....................$ 46.26 31.15
GROUP 3....................$ 44.93 31.15
GROUP 4....................$ 43.79 31.15
GROUP 5....................$ 42.65 31.15
UNDERGROUND:
GROUP 1....................$ 47.42 31.15
GROUP 1-A..................$ 49.89 31.15
GROUP 2....................$ 46.16 31.15
GROUP 3....................$ 44.83 31.15
GROUP 4....................$ 43.69 31.15
GROUP 5....................$ 42.55 31.15
FOOTNOTE: Work suspended by ropes or cables, or work on a Yo-Yo Cat: $.60 per hour additional.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
D-5 Amendment A002
GROUP 1: Operator of helicopter (when used in erection work);
Hydraulic excavator, 7 cu. yds. and over; Power shovels, over 7 cu. yds.
GROUP 2: Highline cableway; Hydraulic excavator, 3-1/2 cu.
yds. up to 7 cu. yds.; Licensed construction work boat operator, on site; Power blade operator (finish); Power shovels, over 1 cu. yd. up to and including 7 cu. yds.
m.r.c.
GROUP 3: Asphalt milling machine; Cable backhoe; Combination backhoe and loader over 3/4 cu. yds.; Continuous flight tie back machine assistant to engineer or mechanic; Crane mounted continuous flight tie back machine, tonnage to apply; Crane mounted drill attachment, tonnage to apply;
Dozer, slope brd; Gradall; Hydraulic excavator, up to 3 1/2
cu. yds.; Loader 4 cu. yds. and over; Long reach excavator;
Multiple engine scraper (when used as push pull); Power shovels, up to and including 1 cu. yd.; Pre-stress wire wrapping machine; Side boom cat, 572 or larger; Track loader 4 cu. yds. and over; Wheel excavator (up to and including 750 cu. yds. per hour)
GROUP 4: Asphalt plant engineer/box person; Chicago boom;
Combination backhoe and loader up to and including 3/4 cu.
yd.; Concrete batch plant (wet or dry); Dozer and/or push cat; Pull- type elevating loader; Gradesetter, grade checker (GPS, mechanical or otherwise); Grooving and grinding machine; Heading shield operator; Heavy-duty drilling equipment, Hughes, LDH, Watson 3000 or similar;
Heavy-duty repairperson and/or welder; Lime spreader;
Loader under 4 cu. yds.; Lubrication and service engineer (mobile and grease rack); Mechanical finishers or spreader machine (asphalt, Barber-Greene and similar); Miller Formless M-9000 slope paver or similar; Portable crushing and screening plants; Power blade support; Roller operator, asphalt; Rubber-tired scraper, self-loading (paddle-wheels, etc.); Rubber- tired earthmoving equipment (scrapers); Slip form paver (concrete); Small tractor with drag; Soil stabilizer (P & H or equal); Spider plow and spider puller;
Tubex pile rig; Unlicensed constuction work boat operator, on site; Timber skidder; Track loader up to 4 yds.;
Tractor-drawn scraper; Tractor, compressor drill combination; Welder; Woods-Mixer (and other similar Pugmill equipment)
GROUP 5: Cast-in-place pipe laying machine; Combination slusher and motor operator; Concrete conveyor or concrete pump, truck or equipment mounted; Concrete conveyor, building site; Concrete pump or pumpcrete gun; Drilling equipment, Watson 2000, Texoma 700 or similar; Drilling and boring machinery, horizontal (not to apply to waterliners, wagon drills or jackhammers); Concrete mixer/all; Person and/or material hoist; Mechanical finishers (concrete) (Clary, Johnson, Bidwell Bridge Deck or similar types);
Mechanical burm, curb and/or curb and gutter machine, concrete or asphalt); Mine or shaft hoist; Portable crusher; Power jumbo operator (setting slip-forms, etc., in tunnels); Screed (automatic or manual); Self-propelled compactor with dozer; Tractor with boom D6 or smaller;
Trenching machine, maximum digging capacity over 5 ft.
depth; Vermeer T-600B rock cutter or similar
GROUP 6: Armor-Coater (or similar); Ballast jack tamper;
Boom- type backfilling machine; Assistant plant engineer;
D-6 Amendment A002
Bridge and/or gantry crane; Chemical grouting machine, truck-mounted; Chip spreading machine operator; Concrete saw (self-propelled unit on streets, highways, airports and canals); Deck engineer; Drilling equipment Texoma 600, Hughes 200 Series or similar up to and including 30 ft.
m.r.c.; Drill doctor; Helicopter radio operator;
Hydro-hammer or similar; Line master; Skidsteer loader, Bobcat larger than 743 series or similar (with attachments); Locomotive; Lull hi-lift or similar; Oiler, truck mounted equipment; Pavement breaker, truck-mounted, with compressor combination; Paving fabric installation and/or laying machine; Pipe bending machine (pipelines only); Pipe wrapping machine (tractor propelled and supported); Screed (except asphaltic concrete paving);
Self- propelled pipeline wrapping machine; Tractor;
Self-loading chipper; Concrete barrier moving machine
GROUP 7: Ballast regulator; Boom truck or dual-purpose A-frame truck, non-rotating - under 15 tons; Cary lift or similar; Combination slurry mixer and/or cleaner; Drilling equipment, 20 ft. and under m.r.c.; Firetender (hot plant);
Grouting machine operator; Highline cableway signalperson;
Stationary belt loader (Kolman or similar); Lift slab machine (Vagtborg and similar types); Maginnes internal full slab vibrator; Material hoist (1 drum); Mechanical trench shield; Pavement breaker with or without compressor combination); Pipe cleaning machine (tractor propelled and supported); Post driver; Roller (except asphalt); Chip Seal; Self-propelled automatically applied concrete curing mahcine (on streets, highways, airports and canals);
Self-propelled compactor (without dozer); Signalperson;
Slip-form pumps (lifting device for concrete forms); Tie spacer; Tower mobile; Trenching machine, maximum digging capacity up to and including 5 ft. depth; Truck- type loader
GROUP 8: Bit sharpener; Boiler tender; Box operator;
Brakeperson; Combination mixer and compressor (shotcrete/gunite); Compressor operator; Deckhand; Fire tender; Forklift (under 20 ft.); Generator;
Gunite/shotcrete equipment operator; Hydraulic monitor; Ken seal machine (or similar); Mixermobile; Oiler; Pump operator; Refrigeration plant; Reservoir-debris tug (self-propelled floating); Ross Carrier (construction site);
Rotomist operator; Self-propelled tape machine; Shuttlecar;
Self-propelled power sweeper operator (includes vacuum sweeper); Slusher operator; Surface heater; Switchperson;
Tar pot firetender; Tugger hoist, single drum; Vacuum cooling plant; Welding machine (powered other than by electricity)
GROUP 8-A: Elevator operator; Skidsteer loader-Bobcat 743 series or smaller, and similar (without attachments); Mini excavator under 25 H.P. (backhoe-trencher); Tub grinder wood chipper
ALL CRANES AND ATTACHMENTS
GROUP 1: Clamshell and dragline over 7 cu. yds.; Crane, over 100 tons; Derrick, over 100 tons; Derrick barge pedestal-mounted, over 100 tons; Self-propelled boom-type lifting device, over 100 tons
GROUP 2: Clamshell and dragline over 1 cu. yd. up to and
D-7 Amendment A002 including 7 cu. yds.; Crane, over 45 tons up to and including 100 tons; Derrick barge, 100 tons and under;
Self-propelled boom-type lifting device, over 45 tons;
Tower crane
GROUP 3: Clamshell and dragline up to and including 1 cu.
yd.; Cranes 45 tons and under; Self-propelled boom-type lifting device 45 tons and under;
GROUP 4: Boom Truck or dual purpose A-frame truck, non-rotating over 15 tons; Truck-mounted rotating telescopic boom type lifting device, Manitex or similar (boom truck) over 15 tons; Truck-mounted rotating telescopic boom type lifting device, Manitex or similar (boom truck) - under 15 tons;
PILEDRIVERS
GROUP 1: Derrick barge pedestal mounted over 100 tons;
Clamshell over 7 cu. yds.; Self-propelled boom-type lifting device over 100 tons; Truck crane or crawler, land or barge mounted over 100 tons
GROUP 2: Derrick barge pedestal mounted 45 tons to and including 100 tons; Clamshell up to and including 7 cu.
yds.; Self-propelled boom-type lifting device over 45 tons;
Truck crane or crawler, land or barge mounted, over 45 tons up to and including 100 tons; Fundex F-12 hydraulic pile rig
GROUP 3: Derrick barge pedestal mounted under 45 tons; Self-propelled boom-type lifting device 45 tons and under;
Skid/scow piledriver, any tonnage; Truck crane or crawler, land or barge mounted 45 tons and under
GROUP 4: Assistant operator in lieu of assistant to engineer;
Forklift, 10 tons and over; Heavy-duty repairperson/welder
GROUP 5: Deck engineer
GROUP 6: Deckhand; Fire tender
STEEL ERECTORS
GROUP 1: Crane over 100 tons; Derrick over 100 tons; Self-propelled boom-type lifting device over 100 tons
GROUP 2: Crane over 45 tons to 100 tons; Derrick under 100 tons; Self-propelled boom-type lifting device over 45 tons to 100 tons; Tower crane
GROUP 3: Crane, 45 tons and under; Self-propelled boom-type lifting device, 45 tons and under
GROUP 4: Chicago boom; Forklift, 10 tons and over; Heavy-duty repair person/welder
GROUP 5: Boom cat
D-8 Amendment A002
TUNNEL AND UNDERGROUND WORK
GROUP 1-A: Tunnel bore machine operator, 20' diameter or more
GROUP 1: Heading shield operator; Heavy-duty repairperson;
Mucking machine (rubber tired, rail or track type); Raised bore operator (tunnels); Tunnel mole bore operator
GROUP 2: Combination slusher and motor operator; Concrete pump or pumpcrete gun; Power jumbo operator
GROUP 3: Drill doctor; Mine or shaft hoist
GROUP 4: Combination slurry mixer cleaner; Grouting Machine operator; Motorman
GROUP 5: Bit Sharpener; Brakeman; Combination mixer and compressor (gunite); Compressor operator; Oiler; Pump operator; Slusher operator
ENGI0003-008 08/01/2022
Rates Fringes
Dredging: (DREDGING:
CLAMSHELL & DIPPER DREDGING;
HYDRAULIC SUCTION DREDGING:)
AREA 1:
(1) Leverman...............$ 55.15 35.46
(2) Dredge Dozer; Heavy duty repairman.............$ 50.19 35.46
(3) Booster Pump Operator; Deck Engineer; Deck mate;
Dredge Tender; Winch Operator...................$ 49.07 35.46
(4) Bargeman; Deckhand;
Fireman; Leveehand; Oiler..$ 45.77 35.46
AREA 2:
(1) Leverman...............$ 57.15 35.46
(2) Dredge Dozer; Heavy duty repairman.............$ 52.19 35.46
(3) Booster Pump Operator; Deck Engineer; Deck mate;
Dredge Tender; Winch Operator...................$ 51.07 35.46
(4) Bargeman; Deckhand;
Fireman; Leveehand; Oiler..$ 47.77 35.46
AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,
NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,
SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,
SUTTER, YOLO, AND YUBA COUNTIES
AREA 2: MODOC COUNTY
THE REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2
AS NOTED BELOW:
ALPINE COUNTY:
D-9 Amendment A002
Area 1: Northernmost part Area 2: Remainder
CALAVERAS COUNTY:
Area 1: Remainder Area 2: Eastern part
COLUSA COUNTY:
Area 1: Eastern part Area 2: Remainder
ELDORADO COUNTY:
Area 1: North Central part Area 2: Remainder
FRESNO COUNTY:
Area 1: Remainder Area 2: Eastern part
GLENN COUNTY:
Area 1: Eastern part Area 2: Remainder
LASSEN COUNTY:
Area 1: Western part along the Southern portion of border with Shasta County Area 2: Remainder
MADERA COUNTY:
Area 1: Except Eastern part Area 2: Eastern part
MARIPOSA COUNTY
Area 1: Except Eastern part Area 2: Eastern part
MONTERREY COUNTY
Area 1: Except Southwestern part Area 2: Southwestern part
NEVADA COUNTY:
Area 1: All but the Northern portion along the border of Sierra County Area 2: Remainder
PLACER COUNTY:
Area 1: Al but the Central portion Area 2: Remainder
PLUMAS COUNTY:
Area 1: Western portion Area 2: Remainder
SHASTA COUNTY:
Area 1: All but the Northeastern corner Area 2: Remainder
SIERRA COUNTY:
Area 1: Western part Area 2: Remainder
SISKIYOU COUNTY:
Area 1: Central part
D-10 Amendment A002
SONOMA COUNTY:
Area 1: All but the Northwestern corner Area 2: Remainder
TEHAMA COUNTY:
Area 1: All but the Western border with Mendocino & Trinity Counties Area 2: Remainder
TRINITY COUNTY:
Area 1: East Central part and the Northeastern border with Shasta County Area 2: Remainder
TUOLUMNE COUNTY:
Area 1: Except Eastern part Area 2: Eastern part
ENGI0003-019 06/29/2020
SEE AREA DESCRIPTIONS BELOW
Rates Fringes
OPERATOR: Power Equipment
(LANDSCAPE WORK ONLY)
GROUP 1
AREA 1.....................$ 39.95 30.28
AREA 2.....................$ 41.95 30.28
GROUP 2
AREA 1.....................$ 36.35 30.28
AREA 2.....................$ 38.35 30.28
GROUP 3
AREA 1.....................$ 31.74 30.28
AREA 2.....................$ 33.74 30.28
GROUP DESCRIPTIONS:
GROUP 1: Landscape Finish Grade Operator: All finish grade work regardless of equipment used, and all equipment with a rating more than 65 HP.
GROUP 2: Landscape Operator up to 65 HP: All equipment with a manufacturer's rating of 65 HP or less except equipment covered by Group 1 or Group 3. The following equipment shall be included except when used for finish work as long as manufacturer's rating is 65 HP or less: A-Frame and Winch Truck, Backhoe, Forklift, Hydragraphic Seeder Machine, Roller, Rubber-Tired and Track Earthmoving Equipment, Skiploader, Straw Blowers, and Trencher 31 HP up to 65 HP.
GROUP 3: Landscae Utility Operator: Small Rubber-Tired Tractor, Trencher Under 31 HP.
AREA DESCRIPTIONS:
AREA 1: ALAMEDA, BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,
NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,
SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,
SUTTER, YOLO, AND YUBA COUNTIES
AREA 2 - MODOC COUNTY
D-11 Amendment A002
THE REMAINING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS
NOTED BELOW:
ALPINE COUNTY:
Area 1: Northernmost part Area 2: Remainder
CALAVERAS COUNTY:
Area 1: Except Eastern part Area 2: Eastern part
COLUSA COUNTY:
Area 1: Eastern part Area 2: Remainder
DEL NORTE COUNTY:
Area 1: Extreme Southwestern corner Area 2: Remainder
ELDORADO COUNTY:
Area 1: North Central part Area 2: Remainder
FRESNO COUNTY
Area 1: Except Eastern part Area 2: Eastern part
GLENN COUNTY:
Area 1: Eastern part Area 2: Remainder
HUMBOLDT COUNTY:
Area 1: Except Eastern and Southwestern parts Area 2: Remainder
LAKE COUNTY:
Area 1: Southern part Area 2: Remainder
LASSEN COUNTY:
Area 1: Western part along the Southern portion of border with Shasta County Area 2: Remainder
MADERA COUNTY
Area 1: Remainder Area 2: Eastern part
MARIPOSA COUNTY
Area 1: Remainder Area 2: Eastern part
MENDOCINO COUNTY:
Area 1: Central and Southeastern parts Area 2: Remainder
MONTEREY COUNTY
Area 1: Remainder Area 2: Southwestern part
NEVADA COUNTY:
Area 1: All but the Northern portion along the border of Sierra County
D-12 Amendment A002
PLACER COUNTY:
Area 1: All but the Central portion Area 2: Remainder
PLUMAS COUNTY:
Area 1: Western portion Area 2: Remainder
SHASTA COUNTY:
Area 1: All but the Northeastern corner Area 2: Remainder
SIERRA COUNTY:
Area 1: Western part Area 2: Remainder
SISKIYOU COUNTY:
Area 1: Central part Area 2: Remainder
SONOMA COUNTY:
Area 1: All but the Northwestern corner Area 2: Reaminder
TEHAMA COUNTY:
Area 1: All but the Western border with mendocino & Trinity Counties Area 2: Remainder
TRINITY COUNTY:
Area 1: East Central part and the Northeaster border with Shasta County Area 2: Remainder
TULARE COUNTY;
Area 1: Remainder Area 2: Eastern part
TUOLUMNE COUNTY:
Area 1: Remainder Area 2: Eastern Part
IRON0433-006 01/01/2023
Rates Fringes
IRONWORKER
Fence Erector...............$ 41.28 25.66 Ornamental, Reinforcing and Structural..............$ 46.20 34.30
PREMIUM PAY:
$6.00 additional per hour at the following locations:
China Lake Naval Test Station, Chocolate Mountains Naval Reserve-Niland, Edwards AFB, Fort Irwin Military Station, Fort Irwin Training Center-Goldstone, San Clemente Island, San Nicholas Island, Susanville Federal Prison, 29 Palms - Marine Corps, U.S. Marine Base - Barstow, U.S. Naval Air Facility - Sealey, Vandenberg AFB
$4.00 additional per hour at the following locations:
D-13 Amendment A002
Army Defense Language Institute - Monterey, Fallon Air Base, Naval Post Graduate School - Monterey, Yermo Marine Corps Logistics Center
$2.00 additional per hour at the following locations:
Port Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock
LABO0294-003 06/28/2021
Rates Fringes
LABORER (TRAFFIC CONTROL/LANE
CLOSURE)
Escort Driver, Flag Person..$ 33.48 26.21 Traffic Control Person I....$ 33.78 26.21 Traffic Control Person II...$ 31.28 26.21
TRAFFIC CONTROL PERSON I: Layout of traffic control, crash cushions, construction area and roadside signage.
TRAFFIC CONTROL PERSON II: Installation and removal of temporary/permanent signs, markers, delineators and crash cushions.
LABO0294-004 06/25/2018
Rates Fringes
Laborers: (CONSTRUCTION CRAFT
LABORERS)
Construction Specialist Group.......................$ 30.49 23.20
GROUP 1.....................$ 29.79 23.20
GROUP 1-a...................$ 30.01 23.20 GROUP 1-c...................$ 29.84 23.20 GROUP 1-e...................$ 30.34 23.20 GROUP 1-f...................$ 29.37 23.20
GROUP 2.....................$ 29.64 23.20
GROUP 3.....................$ 29.54 23.20
GROUP 4.....................$ 23.23 23.20
See groups 1-b and 1-d under laborer classifications Laborers: (GUNITE)
GROUP 1.....................$ 28.35 18.66
GROUP 2.....................$ 27.85 18.66
GROUP 3.....................$ 27.26 18.66
GROUP 4.....................$ 27.14 18.66
Laborers: (WRECKING)
GROUP 1.....................$ 29.79 23.20
GROUP 2.....................$ 29.64 23.20
Landscape Laborer (Gardeners, Horticultural & Landscape Laborers) Establishment Warranty Period......................$ 23.23 23.20 New Construction............$ 29.54 23.20
FOOTNOTES:
Laborers working off or with or from bos'n chairs, swinging scaffolds, belts (not applicable to workers entitled to receive the wage rate set forth in Group 1-a): $0.25 per hour additional.
D-14 Amendment A002
LABORER CLASSIFICATIONS
CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;
Chainsaw; Laser beam in connection with laborers' work;
Masonry and plasterer tender; Cast-in-place manhole form setter; Pressure pipelayer; Davis trencher - 300 or similar type (and all small trenchers); Blaster; Diamond driller;
Multiple unit drill; Hydraulic drill
GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker and similar type tampers; Buggymobile; Caulker, bander, pipewrapper, conduit layer, plastic pipelayer; Certified hazardous waste worker; Compactors of all types; Concrete and magnesite mixer, 1/2 yd. and under; Concrete pan work;
Concrete sander; Concrete saw; Cribber and/or shoring; Cut granite curb setter; Dri-pak-it machine; Faller, logloader and bucker; Form raiser, slip forms; Green cutter;
Headerboard, Hubsetter, aligner, by any method; High pressure blow pipe (1-1/2"" or over, 100 lbs.
pressure/over); Hydro seeder and similar ype; Jackhammer operator; Jacking of pipe over 12 inches; Jackson and similar type compactor; Kettle tender, pot and worker applying asphalt, lay-kold, creosote, lime, caustic and similar type materials (applying means applying, dipping or handling of such materials); Lagging, sheeting, whaling, bracing, trenchjacking, lagging hammer; Magnesite, epoxyresin, fiberglass, mastic worker (wet or dry); No joint pipe and stripping of same, including repair of voids; Pavement breaker and spader, including tool grinder;
Perma curb; Pipelayer (including grade checking in connection with pipelaying); Precast-manhole setter;
Pressure pipe tester; Post hole digger, air, gas and electric; Power broom sweeper; Power tampers of all types (except as shown in Group 2); Ram set gun and stud gun;
Riprap stonepaver and rock-slinger, including placing of sacked concrete and/or sand (wet or dry) and gabions and similar type; Rotary scarifier or multiple head concrete chipping scarifier; Roto and Ditch Witch; Rototiller;
Sandblaster, pot, gun, nozzle operators; Signalling and rigging; Tank cleaner; Tree climber; Turbo blaster;
Vibrascreed, bull float in connection with laborers' work;
Vibrator
GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143 and similar type drills; Track driller; Jack leg driller;
Wagon driller; Mechanical drillers, all types regardless of type or method of power; Mechanical pipe layers, all types regardless of type or method of power; Blaster and powder;
All work of loading, placing and blasting of all powder and explosives of whatever type regardless of method used for such loading and placing; High scalers (including drilling of same); Tree topper; Bit grinder
GROUP 1-b: Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes, shall receive $5.00 per day above Group 1 wage rates.
GROUP 1-c: Burning and welding in connection with laborers' work; Synthetic thermoplastics and similar type welding
D-15 Amendment A002
GROUP 1-d: Maintenance and repair track and road beds (underground structures). All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed.
GROUP 1-e: Work on and/or in bell hole footings and shafts thereof, and work on and in deep footings. (A deep footing is a hole 15 feet or more in depth.) In the event the depth of the footing is unknown at the commencement of excavation, and the final depth exceeds 15 feet, the deep footing wage rate would apply to all employees for each and every day worked on or in the excavation of the footing from the date of inception.
GROUP 1-f: Wire winding machine in connection with guniting or shot crete
GROUP 2: Asphalt shoveler; Cement dumper and handling dry cement or gypsum; Choke-setter and rigger (clearing work);
Concrete bucket dumper and chute; Concrete chipping and grinding; Concrete laborer (wet or dry); Driller tender, chuck tender, nipper; Guinea chaser (stake), grout crew;
High pressure nozzle, adductor; Hydraulic monitor (over 100 lbs. pressure); Loading and unloading, carrying and hauling of all rods and materials for use in reinforcing concrete construction; Pittsburgh chipper and similar type brush shredders; Sloper; Single foot, hand-held, pneumatic tamper; All pneumatic, air, gas and electric tools not listed in Groups 1 through 1-f; Jacking of pipe - under 12 inches
GROUP 3: Construction laborers, including bridge and general laborer; Dump, load spotter; Flag person; Fire watcher;
Fence erector; Guardrail erector; Gardener, horticultural and landscape laborer; Jetting; Limber, brush loader and piler; Pavement marker (button setter); Maintenance, repair track and road beds; Streetcar and railroad construction track laborer; Temporary air and water lines, Victaulic or similar; Tool room attendant (jobsite only)
GROUP 4: All clean-up work of debris, grounds and building including but not limited to: street cleaner; cleaning and washing windows; brick cleaner (jobsite only); material cleaner (jobsite only). The classification ""material cleaner"" is to be utilized under the following conditions:
A: at demolition site for the salvage of the material.
B: at the conclusion of a job where the material is to be salvaged and stocked to be reused on another job.
C: for the cleaning of salvage material at the jobsite or temporary jobsite yard.
The material cleaner classification should not be used in the performance of ""form stripping, cleaning and oiling and moving to the next point of erection"".
GUNITE LABORER CLASSIFICATIONS
GROUP 1: Structural Nozzleman
GROUP 2: Nozzleman, Gunman, Potman, Groundman
D-16 Amendment A002
GROUP 3: Reboundman
GROUP 4: Gunite laborer
WRECKING WORK LABORER CLASSIFICATIONS
GROUP 1: Skilled wrecker (removing and salvaging of sash, windows and materials)
GROUP 2: Semi-skilled wrecker (salvaging of other building materials)
LABO0294-006 07/01/2021
TULARE COUNTY
Rates Fringes
Tunnel and Shaft Laborers:
GROUP 1.....................$ 42.00 25.71
GROUP 2.....................$ 41.77 25.71
GROUP 3.....................$ 41.52 25.71
GROUP 4.....................$ 41.07 25.71
GROUP 5.....................$ 40.53 25.71
Shotcrete Specialist........$ 42.52 25.71
TUNNEL AND SHAFT CLASSIFICATIONS
GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete nozzlemen
GROUP 2: Rodmen; Shaft work & raise (below actual or excavated ground level)
GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;
Cherry pickermen - where car is lifted; Concrete finisher in tunnel; Concrete screedman; Grout pumpman and potman;
Gunite & shotcrete gunman & potman; Headermen; High pressure nozzleman; Miner - tunnel, including top and bottom man on shaft and raise work; Nipper; Nozzleman on slick line; Sandblaster - potman, Robotic Shotcrete Placer, Segment Erector, Tunnel Muck Hauler, Steel Form raiser and setter; Timberman, retimberman (wood or steel or substitute materials therefore); Tugger (for tunnel laborer work);
Cable tender; Chuck tender; Powderman - primer house
GROUP 4: Vibrator operator, pavement breaker; Bull gang -muckers, trackmen; Concrete crew - includes rodding and spreading, Dumpmen (any method)
GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman
* LABO0294-009 07/01/2022
Rates Fringes
Plasterer tender.................$ 38.02 28.25
Work on a swing stage scaffold: $1.00 per hour additional.
PAIN0294-003 01/01/2023
Rates Fringes
D-17 Amendment A002
PAINTER..........................$ 32.99 21.30
FOOTNOTE:
Sandblast/Spray Painting: $1.00 per hour additional.
Work over 30 feet (does not include work from a lift): $1.00 per hour additional.
PAIN1176-001 07/01/2022
HIGHWAY IMPR0VEMENT
Rates Fringes
Parking Lot Striping/Highway Marking:
GROUP 1.....................$ 40.83 17.62
GROUP 2.....................$ 34.71 17.62
GROUP 3.....................$ 35.11 17.62
CLASSIFICATIONS
GROUP 1: Striper: Layout and application of painted traffic stripes and marking; hot thermo plastic; tape, traffic stripes and markings
GROUP 2: Gamecourt & Playground Installer
GROUP 3: Protective Coating, Pavement Sealing
PLAS0300-005 07/01/2016
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 32.15 23.27
PLUM0246-002 01/01/2023
Rates Fringes
PLUMBER & STEAMFITTER............$ 46.95 38.59
PLUM0355-003 07/01/2022
Rates Fringes
Underground Utility Worker /Landscape Fitter...........$ 32.22 17.55
TEAM0094-001 07/01/2022
Rates Fringes
Truck drivers:
GROUP 1.....................$ 36.95 31.14
GROUP 2.....................$ 37.25 31.14
GROUP 3.....................$ 37.55 31.14
GROUP 4.....................$ 37.90 31.14
GROUP 5.....................$ 38.25 31.14
FOOTNOTES:
Articulated dump truck; Bulk cement spreader (with or without auger); Dumpcrete truck; Skid truck (debris box); Dry
D-18 Amendment A002 pre-batch concrete mix trucks; Dumpster or similar type;
Slurry truck: Use dump truck yardage rate.
Heater planer; Asphalt burner; Scarifier burner; Industrial lift truck (mechanical tailgate); Utility and clean-up truck: Use appropriate rate for the power unit or the equipment utilized.
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Dump trucks, under 6 yds.; Single unit flat rack (2-axle unit); Nipper truck (when flat rack truck is used appropriate flat rack shall apply); Concrete pump truck (when flat rack truck is used appropriate flat rack shall apply); Concrete pump machine; Fork lift and lift jitneys;
Fuel and/or grease truck driver or fuel person; Snow buggy;
Steam cleaning; Bus or personhaul driver; Escort or pilot car driver; Pickup truck; Teamster oiler/greaser and/or serviceperson; Hook tender (including loading and unloading); Team driver; Tool room attendant (refineries)
GROUP 2: Dump trucks, 6 yds. and under 8 yds.; Transit mixers, through 10 yds.; Water trucks, under 7,000 gals.;
Jetting trucks, under 7,000 gals.; Single-unit flat rack (3-axle unit); Highbed heavy duty transport; Scissor truck;
Rubber-tired muck car (not self-loaded); Rubber-tired truck jumbo; Winch truck and ""A"" frame drivers; Combination winch truck with hoist; Road oil truck or bootperson;
Buggymobile; Ross, Hyster and similar straddle carriers;
Small rubber-tired tractor
GROUP 3: Dump trucks, 8 yds. and including 24 yds.; Transit mixers, over 10 yds.; Water trucks, 7,000 gals. and over;
Jetting trucks, 7,000 gals. and over; Vacuum trucks under 7500 gals. Trucks towing tilt bed or flat bed pull trailers; Lowbed heavy duty transport; Heavy duty transport tiller person; Self- propelled street sweeper with self-contained refuse bin; Boom truck - hydro-lift or Swedish type extension or retracting crane; P.B. or similar type self-loading truck; Tire repairperson; Combination bootperson and road oiler; Dry distribution truck (A bootperson when employed on such equipment, shall receive the rate specified for the classification of road oil trucks or bootperson); Ammonia nitrate distributor, driver and mixer; Snow Go and/or plow
GROUP 4: Dump trucks, over 25 yds. and under 65 yds.; Water pulls - DW 10's, 20's, 21's and other similar equipment when pulling Aqua/pak or water tank trailers; Helicopter pilots (when transporting men and materials); Lowbedk Heavy Duty Transport up to including 7 axles; DW10's, 20's, 21's and other similar Cat type, Terra Cobra, LeTourneau Pulls, Tournorocker, Euclid and similar type equipment when pulling fuel and/or grease tank trailers or other miscellaneous trailers; Vacuum Trucks 7500 gals and over and truck repairman
GROUP 5: Dump trucks, 65 yds. and over; Holland hauler; Low bed Heavy Duty Transport over 7 axles
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
D-19 Amendment A002
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that
D-20 Amendment A002 classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .