This bid tabulation report details bids received for the CA ERFO SIERRA NF 05S07(1) Norris Creek Bridge project. Major work items included in the single schedule (Schedule A) are the removal of the existing bridge structures and obstructions, excavation and embankment construction totaling 8,500 cubic yards, 250 cubic yards of riprap, 300 tons of roadway aggregate, a 70-foot by 25-foot prefabricated steel bridge totaling 200 tons, 150 linear feet of guardrail including terminals, and 80 hours of equipment and 40 hours of labor. Six bids were received ranging from $1,464,728.76 to $3,003,650.00 with Taylor Jane Construction, LP submitting the low bid of $1,464,728.76. The engineer's estimate was $1,875,000.00. No award date or other award details were provided.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 01/04/23
1 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF22B000037
Division: Central Federal Lands
State: CA County: Madera
Federal Land: Sierra NF Opened at: Lakewood, CO
Opened by: Sheri Walsh
Date: 11/08/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Taylor Jane Construction, LP $1,464,728.76 151 W. Dana St, Suite 101 Nipomo, CA 93444
K.W. Emerson, Inc. $1,572,868.95 P.O. Box 549 San Andreas, CA 95249
AGEE CONSTRUCTION CORPORATION $1,763,712.40
1039 Hoblitt Avenue Clovis, CA 93612
VIKING CONSTRUCTION COMPANY, INC $2,329,575.00
11315 Sunrise Gold Circle, Suite A Rancho Cordova, CA 95742
Genesis Design and Development, LLC $2,664,303.00 7033 Kalgan Rd NE Rio Rancho, NM 87144
WEST COAST CONTRACTORS, INC $3,003,650.00
61050 Highway 101 Coos Bay, OR 97420
Engineer's Estimate $1,875,000.00
2 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
Taylor Jane Construction, LP Lump Sum $145,000.00 K.W. Emerson, Inc. Lump Sum $193,803.00 AGEE CONSTRUCTION CORPORATION Lump Sum $160,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $232,800.00 Genesis Design and Development, LLC Lump Sum $485,600.00 WEST COAST CONTRACTORS, INC Lump Sum $300,000.00 Engineer's Estimate ALL LPSM Lump Sum $262,901.00
A0040 15214-1000 SURVEY AND STAKING, BRIDGE
Taylor Jane Construction, LP Lump Sum $10,000.00 K.W. Emerson, Inc. Lump Sum $2,981.00 AGEE CONSTRUCTION CORPORATION Lump Sum $12,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $11,200.00 Genesis Design and Development, LLC Lump Sum $77,000.00 WEST COAST CONTRACTORS, INC Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $12,000.00
A0060 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
Taylor Jane Construction, LP $248,100.00 $10,172.10 K.W. Emerson, Inc. $138,390.00 $5,673.99
AGEE CONSTRUCTION CORPORATION $135,000.00 $5,535.00
VIKING CONSTRUCTION COMPANY, INC $136,585.37 $5,600.00
Genesis Design and Development, LLC $940,000.00 $38,540.00
WEST COAST CONTRACTORS, INC $500,000.00 $20,500.00
Engineer's Estimate 0.041 MILE $50,000.00 $2,050.00
A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING
Taylor Jane Construction, LP $116,752.00 $9,573.66 K.W. Emerson, Inc. $49,341.46 $4,046.00
AGEE CONSTRUCTION CORPORATION $130,700.00 $10,717.40
VIKING CONSTRUCTION COMPANY, INC $68,292.68 $5,600.00
Genesis Design and Development, LLC $470,000.00 $38,540.00
WEST COAST CONTRACTORS, INC $350,000.00 $28,700.00
Engineer's Estimate 0.082 MILE $40,000.00 $3,280.00
A0100 15301-0000 CONTRACTOR QUALITY CONTROL
Taylor Jane Construction, LP Lump Sum $42,800.00 K.W. Emerson, Inc. Lump Sum $66,447.00 AGEE CONSTRUCTION CORPORATION Lump Sum $34,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $100,000.00 Genesis Design and Development, LLC Lump Sum $178,000.00 WEST COAST CONTRACTORS, INC Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $150,000.00
3 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0120 15401-0000 CONTRACTOR TESTING
Taylor Jane Construction, LP Lump Sum $48,000.00 K.W. Emerson, Inc. Lump Sum $15,669.00 AGEE CONSTRUCTION CORPORATION Lump Sum $5,700.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $75,000.00 Genesis Design and Development, LLC Lump Sum $154,000.00 WEST COAST CONTRACTORS, INC Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $125,000.00
A0140 15501-0000 CONSTRUCTION SCHEDULE
Taylor Jane Construction, LP Lump Sum $6,100.00 K.W. Emerson, Inc. Lump Sum $1,469.00 AGEE CONSTRUCTION CORPORATION Lump Sum $2,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $7,500.00 Genesis Design and Development, LLC Lump Sum $29,000.00 WEST COAST CONTRACTORS, INC Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0160 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Taylor Jane Construction, LP $5.30 $4,505.00 K.W. Emerson, Inc. $4.01 $3,408.50
AGEE CONSTRUCTION CORPORATION $7.00 $5,950.00
VIKING CONSTRUCTION COMPANY, INC $10.00 $8,500.00
Genesis Design and Development, LLC $8.00 $6,800.00
WEST COAST CONTRACTORS, INC $11.00 $9,350.00
Engineer's Estimate 850 LNFT $13.00 $11,050.00
A0180 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Taylor Jane Construction, LP $8.00 $3,200.00 K.W. Emerson, Inc. $5.71 $2,284.00
AGEE CONSTRUCTION CORPORATION $9.50 $3,800.00
VIKING CONSTRUCTION COMPANY, INC $10.00 $4,000.00
Genesis Design and Development, LLC $13.00 $5,200.00
WEST COAST CONTRACTORS, INC $6.00 $2,400.00
Engineer's Estimate 400 LNFT $14.00 $5,600.00
A0200 20101-0000 CLEARING AND GRUBBING
Taylor Jane Construction, LP $75,600.00 $26,460.00 K.W. Emerson, Inc. $15,311.43 $5,359.00
AGEE CONSTRUCTION CORPORATION $60,000.00 $21,000.00
VIKING CONSTRUCTION COMPANY, INC $357,000.00 $124,950.00
Genesis Design and Development, LLC $138,000.00 $48,300.00
WEST COAST CONTRACTORS, INC $90,000.00 $31,500.00
Engineer's Estimate 0.35 ACRE $35,000.00 $12,250.00
4 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 20220-1000 REMOVAL, INDIVIDUAL TREE (HAZARD)
Taylor Jane Construction, LP $1,900.00 $22,800.00 K.W. Emerson, Inc. $257.42 $3,089.04
AGEE CONSTRUCTION CORPORATION $1,700.00 $20,400.00
VIKING CONSTRUCTION COMPANY, INC $2,500.00 $30,000.00
Genesis Design and Development, LLC $1,600.00 $19,200.00
WEST COAST CONTRACTORS, INC $3,000.00 $36,000.00
Engineer's Estimate 12 EACH $1,200.00 $14,400.00
A0240 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Taylor Jane Construction, LP $51.00 $24,225.00 K.W. Emerson, Inc. $17.03 $8,089.25
AGEE CONSTRUCTION CORPORATION $15.00 $7,125.00
VIKING CONSTRUCTION COMPANY, INC $50.00 $23,750.00
Genesis Design and Development, LLC $66.00 $31,350.00
WEST COAST CONTRACTORS, INC $50.00 $23,750.00
Engineer's Estimate 475 SQYD $23.00 $10,925.00
A0260 20304-2000 REMOVAL OF BRIDGE
Taylor Jane Construction, LP Lump Sum $15,422.00 K.W. Emerson, Inc. Lump Sum $26,380.00 AGEE CONSTRUCTION CORPORATION Lump Sum $40,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $75,000.00 Genesis Design and Development, LLC Lump Sum $39,800.00 WEST COAST CONTRACTORS, INC Lump Sum $500,000.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00
A0280 20420-0000 EMBANKMENT CONSTRUCTION
Taylor Jane Construction, LP $77.00 $65,450.00 K.W. Emerson, Inc. $73.68 $62,628.00
AGEE CONSTRUCTION CORPORATION $125.00 $106,250.00
VIKING CONSTRUCTION COMPANY, INC $250.00 $212,500.00
Genesis Design and Development, LLC $254.00 $215,900.00
WEST COAST CONTRACTORS, INC $300.00 $255,000.00
Engineer's Estimate 850 CUYD $115.00 $97,750.00
A0300 20801-0000 STRUCTURE EXCAVATION
Taylor Jane Construction, LP $254.00 $27,940.00 K.W. Emerson, Inc. $572.05 $62,925.50
AGEE CONSTRUCTION CORPORATION $625.00 $68,750.00
VIKING CONSTRUCTION COMPANY, INC $150.00 $16,500.00
Genesis Design and Development, LLC $97.00 $10,670.00
WEST COAST CONTRACTORS, INC $200.00 $22,000.00
Engineer's Estimate 110 CUYD $350.00 $38,500.00
5 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0320 20803-0000 STRUCTURAL BACKFILL
Taylor Jane Construction, LP $375.00 $18,750.00 K.W. Emerson, Inc. $317.64 $15,882.00
AGEE CONSTRUCTION CORPORATION $750.00 $37,500.00
VIKING CONSTRUCTION COMPANY, INC $300.00 $15,000.00
Genesis Design and Development, LLC $204.00 $10,200.00
WEST COAST CONTRACTORS, INC $200.00 $10,000.00
Engineer's Estimate 50 CUYD $300.00 $15,000.00
A0340 20820-0000 DEWATERING
Taylor Jane Construction, LP Lump Sum $9,830.00 K.W. Emerson, Inc. Lump Sum $68,250.00 AGEE CONSTRUCTION CORPORATION Lump Sum $100,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $15,000.00 Genesis Design and Development, LLC Lump Sum $20,000.00 WEST COAST CONTRACTORS, INC Lump Sum $100,000.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00
A0360 25101-2200 PLACED RIPRAP, METHOD B, CLASS 2
Taylor Jane Construction, LP $248.00 $62,000.00 K.W. Emerson, Inc. $298.93 $74,732.50
AGEE CONSTRUCTION CORPORATION $265.00 $66,250.00
VIKING CONSTRUCTION COMPANY, INC $350.00 $87,500.00
Genesis Design and Development, LLC $474.00 $118,500.00
WEST COAST CONTRACTORS, INC $300.00 $75,000.00
Engineer's Estimate 250 CUYD $360.00 $90,000.00
A0380 30202-2000 ROADWAY AGGREGATE, METHOD 2
Taylor Jane Construction, LP $101.00 $30,300.00 K.W. Emerson, Inc. $171.87 $51,561.00
AGEE CONSTRUCTION CORPORATION $100.00 $30,000.00
VIKING CONSTRUCTION COMPANY, INC $250.00 $75,000.00
Genesis Design and Development, LLC $169.00 $50,700.00
WEST COAST CONTRACTORS, INC $375.00 $112,500.00
Engineer's Estimate 300 TON $110.00 $33,000.00
A0400 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
Taylor Jane Construction, LP $306.00 $42,840.00 K.W. Emerson, Inc. $306.96 $42,974.40
AGEE CONSTRUCTION CORPORATION $255.00 $35,700.00
VIKING CONSTRUCTION COMPANY, INC $400.00 $56,000.00
Genesis Design and Development, LLC $334.00 $46,760.00
WEST COAST CONTRACTORS, INC $800.00 $112,000.00
Engineer's Estimate 140 TON $350.00 $49,000.00
6 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
Taylor Jane Construction, LP $2,240.00 $69,440.00 K.W. Emerson, Inc. $1,279.42 $39,662.02
AGEE CONSTRUCTION CORPORATION $3,720.00 $115,320.00
VIKING CONSTRUCTION COMPANY, INC $4,000.00 $124,000.00
Genesis Design and Development, LLC $2,760.00 $85,560.00
WEST COAST CONTRACTORS, INC $3,000.00 $93,000.00
Engineer's Estimate 31 CUYD $3,500.00 $108,500.00
A0440 55401-1000 REINFORCING STEEL
Taylor Jane Construction, LP $6.50 $20,150.00 K.W. Emerson, Inc. $14.99 $46,469.00
AGEE CONSTRUCTION CORPORATION $6.00 $18,600.00
VIKING CONSTRUCTION COMPANY, INC $10.00 $31,000.00
Genesis Design and Development, LLC $6.00 $18,600.00
WEST COAST CONTRACTORS, INC $5.00 $15,500.00
Engineer's Estimate 3,100 LB $6.00 $18,600.00
A0460 55504-0000 PRE-FABRICATED STEEL BRIDGE (24'x68')
Taylor Jane Construction, LP Lump Sum $387,674.00 K.W. Emerson, Inc. Lump Sum $338,793.00 AGEE CONSTRUCTION CORPORATION Lump Sum $487,000.00 VIKING CONSTRUCTION COMPANY, INC Lump Sum $550,000.00 Genesis Design and Development, LLC Lump Sum $741,000.00 WEST COAST CONTRACTORS, INC Lump Sum $600,000.00 Engineer's Estimate ALL LPSM Lump Sum $475,000.00
A0480 56501-0200 DRILLED SHAFT, 24-INCH DIAMETER
Taylor Jane Construction, LP $4,485.00 $291,525.00 K.W. Emerson, Inc. $5,108.52 $332,053.80
AGEE CONSTRUCTION CORPORATION $4,100.00 $266,500.00
VIKING CONSTRUCTION COMPANY, INC $5,225.00 $339,625.00
Genesis Design and Development, LLC $711.00 $46,215.00
WEST COAST CONTRACTORS, INC $2,000.00 $130,000.00
Engineer's Estimate 65 LNFT $1,550.00 $100,750.00
A0500 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
Taylor Jane Construction, LP $181.00 $9,050.00 K.W. Emerson, Inc. $228.94 $11,447.00
AGEE CONSTRUCTION CORPORATION $182.00 $9,100.00
VIKING CONSTRUCTION COMPANY, INC $450.00 $22,500.00
Genesis Design and Development, LLC $770.00 $38,500.00
WEST COAST CONTRACTORS, INC $100.00 $5,000.00
Engineer's Estimate 50 LNFT $120.00 $6,000.00
7 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Taylor Jane Construction, LP $4,193.00 $16,772.00 K.W. Emerson, Inc. $8,772.75 $35,091.00
AGEE CONSTRUCTION CORPORATION $7,900.00 $31,600.00
VIKING CONSTRUCTION COMPANY, INC $5,500.00 $22,000.00
Genesis Design and Development, LLC $7,700.00 $30,800.00
WEST COAST CONTRACTORS, INC $7,000.00 $28,000.00
Engineer's Estimate 4 EACH $8,000.00 $32,000.00
A0540 61707-0000 STRUCTURE TRANSITION RAILING
Taylor Jane Construction, LP $185.00 $9,250.00 K.W. Emerson, Inc. $303.42 $15,171.00
AGEE CONSTRUCTION CORPORATION $260.00 $13,000.00
VIKING CONSTRUCTION COMPANY, INC $200.00 $10,000.00
Genesis Design and Development, LLC $770.00 $38,500.00
WEST COAST CONTRACTORS, INC $7,000.00 $350,000.00
Engineer's Estimate 50 LNFT $200.00 $10,000.00
A0560 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
Taylor Jane Construction, LP $197.00 $3,940.00 K.W. Emerson, Inc. $165.00 $3,300.00
AGEE CONSTRUCTION CORPORATION $420.00 $8,400.00
VIKING CONSTRUCTION COMPANY, INC $175.00 $3,500.00
Genesis Design and Development, LLC $150.00 $3,000.00
WEST COAST CONTRACTORS, INC $150.00 $3,000.00
Engineer's Estimate 20 HOUR $175.00 $3,500.00
A0580 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Taylor Jane Construction, LP $177.00 $3,540.00 K.W. Emerson, Inc. $185.00 $3,700.00
AGEE CONSTRUCTION CORPORATION $290.00 $5,800.00
VIKING CONSTRUCTION COMPANY, INC $250.00 $5,000.00
Genesis Design and Development, LLC $180.00 $3,600.00
WEST COAST CONTRACTORS, INC $200.00 $4,000.00
Engineer's Estimate 20 HOUR $180.00 $3,600.00
A0600 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Taylor Jane Construction, LP $237.00 $4,740.00 K.W. Emerson, Inc. $250.00 $5,000.00
AGEE CONSTRUCTION CORPORATION $290.00 $5,800.00
VIKING CONSTRUCTION COMPANY, INC $275.00 $5,500.00
Genesis Design and Development, LLC $180.00 $3,600.00
WEST COAST CONTRACTORS, INC $200.00 $4,000.00
Engineer's Estimate 20 HOUR $215.00 $4,300.00
8 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0620 62201-2750 MOTOR GRADER
Taylor Jane Construction, LP $244.00 $4,880.00 K.W. Emerson, Inc. $265.00 $5,300.00
AGEE CONSTRUCTION CORPORATION $315.00 $6,300.00
VIKING CONSTRUCTION COMPANY, INC $325.00 $6,500.00
Genesis Design and Development, LLC $210.00 $4,200.00
WEST COAST CONTRACTORS, INC $250.00 $5,000.00
Engineer's Estimate 20 HOUR $195.00 $3,900.00
A0640 62301-0000 GENERAL LABOR
Taylor Jane Construction, LP $81.00 $1,620.00 K.W. Emerson, Inc. $99.00 $1,980.00
AGEE CONSTRUCTION CORPORATION $98.00 $1,960.00
VIKING CONSTRUCTION COMPANY, INC $125.00 $2,500.00
Genesis Design and Development, LLC $120.00 $2,400.00
WEST COAST CONTRACTORS, INC $120.00 $2,400.00
Engineer's Estimate 20 HOUR $100.00 $2,000.00
A0660 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Taylor Jane Construction, LP $197.00 $3,940.00 K.W. Emerson, Inc. $200.00 $4,000.00
AGEE CONSTRUCTION CORPORATION $170.00 $3,400.00
VIKING CONSTRUCTION COMPANY, INC $200.00 $4,000.00
Genesis Design and Development, LLC $150.00 $3,000.00
WEST COAST CONTRACTORS, INC $500.00 $10,000.00
Engineer's Estimate 20 HOUR $185.00 $3,700.00
A0680 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Taylor Jane Construction, LP $256.00 $5,120.00 K.W. Emerson, Inc. $225.00 $4,500.00
AGEE CONSTRUCTION CORPORATION $700.00 $14,000.00
VIKING CONSTRUCTION COMPANY, INC $500.00 $10,000.00
Genesis Design and Development, LLC $180.00 $3,600.00
WEST COAST CONTRACTORS, INC $500.00 $10,000.00
Engineer's Estimate 20 HOUR $280.00 $5,600.00
A0700 62515-1000 MULCHING, DRY METHOD
Taylor Jane Construction, LP $37,000.00 $5,920.00 K.W. Emerson, Inc. $11,631.25 $1,861.00
AGEE CONSTRUCTION CORPORATION $15,000.00 $2,400.00
VIKING CONSTRUCTION COMPANY, INC $60,000.00 $9,600.00
Genesis Design and Development, LLC $45,800.00 $7,328.00
WEST COAST CONTRACTORS, INC $12,500.00 $2,000.00
Engineer's Estimate 0.16 ACRE $3,400.00 $544.00
9 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO SIERRA NF 05S07(1)
Project Name: Norris Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0720 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Taylor Jane Construction, LP $225.00 $900.00 K.W. Emerson, Inc. $1,338.50 $5,354.00
AGEE CONSTRUCTION CORPORATION $70.00 $280.00
VIKING CONSTRUCTION COMPANY, INC $500.00 $2,000.00
Genesis Design and Development, LLC $740.00 $2,960.00
WEST COAST CONTRACTORS, INC $200.00 $800.00
Engineer's Estimate 4 EACH $400.00 $1,600.00
A0740 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Taylor Jane Construction, LP $20.00 $900.00 K.W. Emerson, Inc. $34.11 $1,534.95
AGEE CONSTRUCTION CORPORATION $35.00 $1,575.00
VIKING CONSTRUCTION COMPANY, INC $10.00 $450.00
Genesis Design and Development, LLC $164.00 $7,380.00
WEST COAST CONTRACTORS, INC $50.00 $2,250.00
Engineer's Estimate 45 SQFT $60.00 $2,700.00
Total Schedule - All Items
Taylor Jane Construction, LP $1,464,728.76 K.W. Emerson, Inc. $1,572,868.95
AGEE CONSTRUCTION CORPORATION $1,763,712.40
VIKING CONSTRUCTION COMPANY, INC $2,329,575.00
Genesis Design and Development, LLC $2,664,303.00
WEST COAST CONTRACTORS, INC $3,003,650.00
Engineer's Estimate $1,875,000.00
| 2023-01-04T11:53:13-0700 | |