This document provides questions and answers regarding Invitation for Bid number 6982AF20B000016 for the AZ FTFS 275(1) Stone Creek AOP Improvements project issued by the Department of Transportation Federal Highway Administration. The contract completion date is January 29, 2021, with work restricted to the period between October 1 and March 1 to accommodate environmental considerations. Clarification was provided that the completion date of January 29, 2021 is correct, notwithstanding earlier language indicating a work window between October 1 and March 1. No other details were included regarding required products or services, pricing terms, responses dates, or awards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers During Advertisement for AZ FTFS 275(1) Stone Creek AOP Improvements

Thursday, August 6, 2020

Question Answer

We would like clarification on Contract time. Section 108.01a states perform all work between October 1 and March 1 and later in the 108 section it states that completion date is January 29, 2021.

The contract completion date of January 29, 2021 is correct. The October 1 to March 1 window for work is noted to represent an environmental restriction on ground disturbing activities.