21 Amendment 0004 697DCK-27-R-00022A.pdf

PDF 506 KB Posted

Attached to
Design Renovation, System Support Center (SSC), 3551 Combine St., Paso Robles, CA
Solicitation number
697DCK-27-R-00022A
Issued by

About this file

This is Amendment 0004 to Solicitation 697DCK-27-R-00022A issued by the Federal Aviation Administration (FAA), Regional Acquisitions office in College Park, Georgia. The amendment changes the offer due date from November 30, 2026 to December 2, 2026 and provides responses to 36 vendor questions regarding design renovation services for a facility located at 3551 Combine Street, Paso Robles, California. The contracting officer is Linda M. Hennequant (Linda.hennequant@faa.gov).

Key scope clarifications include: design must comply with the 2025 California Building Code adopted by the City of Paso Robles; architectural, civil, and structural design services must be included in the proposal if required for permitting; the thermal envelope upgrade is not expected to be required; CAD/BIM background drawings will be provided by the FAA; no formal land survey is required, only on-site field verification; specific finishes will be selected by the FAA at the 90% review stage; a high-low electric water cooler with bottle filler is required; all exterior and locked interior doors must accept a Best Lock 7-pin core; and the selected consultant must serve as the Architect of Record and prepare architectural permit documents. The project completion period spans ten weeks from Notice to Proceed to final permit drawing submission, with FAA reviews occurring within this timeframe. Award is anticipated within 60 days after the offer due date, with a post-award meeting to establish the project start date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6)CODE

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. CONTRACT AUTHORITY

(Signature of Contracting Officer)

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Linda M. Hennequant

See continuation page

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

1701 COLUMBIA AVENUE

COLLEGE PARK GA 30337

AAQ510ATL-AFN

697DCK-27-R-00022

11/13/2026

10/07/2026

1 8

A

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A /0004

Design Renovation, SSC, 3551 Combine St., Paso

Robles, California 93446.

Contracting Officer: Linda.hennequant@faa.gov

PURPOSE:

The purpose of this amendment is to Change the

Offer Due Date, and answer Vendor Questions.

CHANGE:

Offer due date: 30-NOV-26 changed to 02-DEC-26

QUESTIONS & ANSWERS:

1 – Applicable Building Code

The current code enforced by the City of Paso

Robles is the 2025 California Building Code

(CBC). Please confirm we are to design to the

2025 version.

FAA ANSWER: Please design to the 2025

California Building Code (CBC). While the

Statement of Work (SOW) references the 2022 edition, it explicitly states that “the design must adhere to all Building Codes and Design

Standards adopted by the City of Paso Robles.”

Because the City has since adopted the 2025 version, it supersedes the 2022 edition.

2 – Architectural, Civil, and Structural Design

Services

The Statement of Work indicates scope for MEP, Life Safety, and Fire Protection. Will architectural services be required? Can we provide, as an option, the cost for

Architectural, Civil, and Structural design services?

FAA ANSWER: Drawings and SOW are provided to show intent and scope. If additional architectural drawings are required for permit/construction you will need to provide.

3 – Existing Thermal Envelope

Please confirm that this project will not require upgrading the existing thermal envelope

(wall insulation, roof insulation, window glazing U-factors, etc.).

FAA ANSWER: It is not expected to be needed as the FAA does not have a standard, any deficiencies will be identified on the on-site

Continued...

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A/0004

pre-bid visit.

4 – Missing Sheets A001, A002, and A003

Sheet A201, General Notes, Note G, refers to

Sheets A001, A002, and A003. These sheets were not provided in the DID set. Please provide them to assist in pricing.

FAA ANSWER: These reference sheets are considered ‘boilerplate’ standard accessibility sheets you will need to provide any current sheets for this locality needed for permit/construction.

5 – Topographic and Boundary Survey

The DIDs indicate a new fence and gates surrounding the majority of the existing parking. Should our proposal include a topographic and boundary survey?

FAA ANSWER: That is not needed, the FAA will be doing it’s own Metes and Bounds survey for the exact boundary locators.

6 – As-Built Documents and CAD/BIM Files

Please provide available as-built documents and the CAD/BIM files of the provided DIDs. Please also provide fire sprinkler as-built drawings and calculations.

FAA ANSWER: We will provide the CAD files for the DIDs. We do not have the original CAD files or as-builts for the building or the fire sprinkler. The building owner/leasing company would have those.

7 – Laminated Glass for Force Protection

Please confirm whether existing doors and windows require laminated glass as a force protection measure.

FAA ANSWER: This is not required.

8 – Window and Door Coverings

Please confirm whether window or door coverings

(privacy film, shades, blinds) are required on any or all glazing and fenestrations.

FAA ANSWER: Shades or Blinds should be included on windows and doors.

9 – Door Security Hardware

Please confirm which doors, if any, require

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A/0004

specific security hardware, such as card access, cipher hardware, a wireless access system, a biometric system, or alarmed systems.

FAA ANSWER: None, only door hardware requirement as they must accept a Best Lock

7-pin core on all exterior and locked interior doors.

10 – Intrusion Detection System

Please confirm whether an intrusion detection system (IDS) is required, including cameras or alarms for monitoring traffic and security breaches.

FAA ANSWER: No, not part of this scope.

11 – Finish Specifications

Please provide specifications for the new finishes: luxury vinyl tile, carpet, porcelain/ceramic tile, and acoustical ceiling system.

FAA ANSWER: Specific finishes will be selected by FAA by 90% review.

12 – Locker Specification

Please provide the specification for the eight

(8) new lockers in Room 118, Back of House

(BOH).

FAA ANSWER: Vented metal lockers for PPE equipment, 18”W x 36”D x 72 “H.

13 – Electric Water Cooler

Please confirm whether the indicated electric water cooler is a single unit or a high-low

(bi-level) unit. Will a bottle filler be required in either case?

FAA ANSWER: This should be a high-low unit with a bottle filler.

14 – Salvaged Plumbing Fixtures

Sheet A200, Demo Note 4, indicates fixtures are to be salvaged. Please confirm that the existing fixtures meet current plumbing code water-saving standards.

FAA ANSWER: This should be noted on your design that the contractor is to determine what is salvageable and meeting the permitting guidelines. There may not be any salvageable

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A/0004

fixtures.

15 – Existing Flooring

Please indicate the existing flooring type and extent.

FAA ANSWER: Existing flooring includes ceramic/porcelain tile (general area) and polished concrete (back of house area). Will confirm on site visit.

16 – Existing Ceilings

Please establish the existing ceiling type and extent.

FAA ANSWER: Hard qypsum board ceiling (general areas) and exposed ceiling (back of house area). Will confirm on site visit.

17 – HVAC at ELEC/TELCO Room 105

Does ELEC/TELCO Room 105 require 24/7 HVAC?

FAA ANSWER: Yes, this area requires a separate mini-split unit for conditioning.

18 – Air Conditioning at BOH Room 118

Please confirm whether BOH Room 118 requires air conditioning.

FAA ANSWER: Yes, this is conditioned space.

19 – Partition Stud Type

On Sheet A501, Partition Types General Notes, Keynote 3, and Partition Type Detail 1, please confirm whether all studs are to be wood or metal.

FAA ANSWER: Specific partition types calls out

3 5/8” metal studs.

20 – Door Inset Grilles

Sheet A501, Notes by Number, Note 6, refers to inset grilles, but Note 6 is not listed on the

Schedule. Please verify whether inset grilles are required on doors.

FAA ANSWER: General notes are not all used on design, reference design schedule.

21 – Emergency Backup Power

Please confirm whether emergency backup power and a generator are required.

FAA ANSWER: No back-up power is required.

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A/0004

22 – Back-of-House Functions Please describe the functions and activities that will occur in the Back-of-House area.

FAA ANSWER: This area is used for project material delivery and storage along with storage of parts for FAA navigational and communications equipment. There will also be a HAZMAT locker for pesticides and paint storage.

Minimal shop tools and workbenches. It is not intended to house vehicles and we do not do any maintenance on FAA vehicles.

23 – Rooftop HVAC Unit Please confirm that the rooftop HVAC unit will be new and is part of the project scope. Is demolition of the existing HVAC system in the scope?

FAA ANSWER: It is not part of the scope to replace the HVAC system that is on the roof.

This system is provided by that lessor. The age of the system does not appear to need changing at this time.

24 – Roof-Mounted Antennas Will antennas be mounted on the roof? If so, please indicate weight, dimensions, and any special mounting requirements.

FAA ANSWER: We will not be installing any roof top antennas.

25 – Does the ten-week completion period include both FAA review and final City of Paso Robles approval, or is it the deadline for submitting completed permit-ready drawings?

FAA ANSWER: The ten-week completion period is from the NTP to the final permit drawing submittal to the City for approval. You cannot be responsible for City review timelines.

26 – The SOW requires the 90% design submission within three weeks of the “review submission.”

What event starts that three-week period?

FAA ANSWER: FAA’s return of approval/comments to the 90% design.

27 -Does the Texas architect have someone licensed in CA? If not, we would need to be the Architect of Record.

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A/0004

FAA ANSWER: Correct, you would need to be the Architect of Record

28 - Will we receive the CAD background drawings from the Texas architect or will we need to create our own drawings? This is important in terms of cost.

FAA ANSWER: Yes, we will provide the CAD for the Design Intent Drawings

29 - What is the requirement for site survey?

Do they need a boundary survey from a licensed surveyor? Or just a site visit to the existing building to verify the information in the design drawings from the Texas architect?

FAA ANSWER: Just a site visit to the existing building not a land boundary survey.

30 - When is the project expected to be awarded? When are our services expected to start?

FAA ANSWER: Award is expected within 60 days after the offer due date. A Post-award meeting will be held shortly after award to determine the start date.

31 - In addition to the required documents identified in Section L02, may offerors include supplemental qualifications such as key personnel resumes, relevant project sheets, or a brief overview of the team's experience working together?

FAA ANSWER: There are no objections to this.

However, the determination for award will be based on pricing.

32 - Does the Fire Protection Engineer need specific FAA experience? Will any specialty equipment require a specific Fire Protection system?

FAA ANSWER: No, there are no FAA requirements for the fire suppression, only what is required by the city/state.

33 - What is the anticipated award date?

FAA ANSWER: Within 60 days after Offer due date

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

ITEM NO.

(A)

QUANTITY

(C)

697DCK-27-R-00022A/0004

34 - Leidos provided the architectural Design Intent Drawings; however, architectural construction documents will still be required for submission to the local jurisdiction for permitting. Should we assume the awarded team will be responsible for completing these drawings and serving as the Architect of Record?

FAA ANSWER: Yes

35 - The SOW requires a site survey within seven days of Notice to Proceed. Can you confirm whether this refers to a formal land survey performed by a licensed land surveyor or on-site field verification of existing conditions by the A&E team?

FAA ANSWER: Does not refer to a land survey, just an on-site field verification.

36 - Who will be responsible for preparing the architectural portion of the permit set and for addressing any architectural questions, revisions, or plan-check comments related to the Leidos Design Intent Drawings during development of the permit set and City review?

Will Leidos remain available for architectural coordination and preparation of the architectural permit documents, or is the selected consultant expected to include architectural services as part of its team?

FAA ANSWER: The intent is to include this with your offer and the selected consultant expected to include architectural services as part of its team. The Leidos Architect will be available for architectural coordination but not for the preparation of the architectural permit documents. That must be included in the offer.

END OF AMENDMENT

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed