22R00242 Amendment 1_with RFI responses.pdf

PDF 432 KB Posted

Attached to
RFO/Solicitation; OWD ATCT Fire Alarm System (FAS) Replacement project in Norwood, MA
Solicitation number
697DCK-22-R-00242
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

OWD ATCT FAS Upgrade project in Norwood, MA N/A 1 5

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0001 4/4/22 ES-22-00538

6. ISSUED BY 7. ADMINISTRATED BY (If other than Item 6)

Federal Aviation Administration

ATTN: AAQ-550

1200 District Ave Burlington, MA 01803

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

Offeror: Please fill name and address here:

9A. AMENDMENT OF SOLICITATION NO.

697DCK-22-R-00242

9B. DATED (SEE ITEM 11)

3/11/22

10A. MODIFICATION OF CONTRACT/ORDER NO.

*TO BE COMPLETED BY VENDOR IF NOT COMPLETE 10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is: extended is not extended.

(a) By completing Item 8 and 15, and returning 2 copies of the amendment; (b) acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hours and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO.

AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

.See Block #14 E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.

14. Amendment #1 issued to incorporate the following:

1. See the attached consolidated RFI responses, which are incorporated into the Solicitation requirements.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Robert K. Higgins.

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign)

BY

(Signature of Contracting Officer) 4/4/22

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

(a) Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

(b) Item 3 (Effective date).

(1) For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

(2) For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

(3) For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

(4) For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

(5) For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(c) Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

(d) Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original con- tract or order, unless changed by this or a previous modification.

(e) Items 9, (Amendment of Solicitation No.- Dated), and

10, (Modification of Contract/Order No.- Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

(f) Item 12 (Accounting and Appropriation Data). When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(1) Accounting classification Net increase $

(2) Accounting classification Net decrease $

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet."

(g) Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document.

(h) Item 14 (Description of Amendment/Modification).

(1) Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section (if UCF used) headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

(2) Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

(3) State reason for modification.

(4) When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(5) When Template 11 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to -

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(6) Include subject matter or short title of solicitation/ contract where feasible.

(i) Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

OWD FAS project in Norwood, MA RFI Responses 4/4/22

1. Please confirm if taxes should be carried in proposals?

Yes, while the FAA is tax exempt, the awarded offerer will be expected to be responsible for any/all taxes.

2. Please confirm if any state, local, and/or Federal permits will be required on this project?

The FAA owns this facility, therefore, no permits are legally required. We are our own AHJ but we still coordinate with the local fire department, for courtesy purposes. They have already reviewed our plans and specs. The local FD did ask us to let them know who the contractor is, so after award, they may be reaching out.

3. Please confirm if there are any known hazardous materials?

Here is the information about the areas we know to stay away from:

Control Cab Asbestos Material Countertop Mastic Roof Drain Mastic On Roof Ladder

4th floor & Catwalk Suspect Material Countertop Mastic Mudded Roof Drain Electrical Putty Window Caulks Carpet Mastic Insulation Wrap Ceiling Tile Sealant Roof Mastic

Stair to Cab Asbestos Containing Material Floor Tile and Mastic

4. Please confirm if the tower and the administration building fire alarm are networked together?

Yes. The tower, link and base building all share one FACP, which is located in the tower, first floor.

5. Please confirm surface mounted conduits will be allowed ATCT building?

Surface mounted conduits will be allowed in areas that are unfinished (no sheetrock, tape, paint). In finished areas, we would like to re-use existing conduits to the fullest extent and conceal all new conduits behind the walls.

6. Please confirm this project is to have a full time Superintendent on site while work is going on at all times? Yes. A general contractor-representative is required to be onsite to coordinate and supervise activities with their own people and all subs. Any contractor who is onsite, will be under FAA escort at all times.

7. There was a question at the walk through about a pull station in the base building being located an inch or two too low. The pull station should be already at 44” to the pull handle, per NFPA 72. The height of the manual fire alarm boxes are allowed be a minimum of 42 inches.

8. The solicitation requirements, the following companies were listed:

Edwards (Carrier) Notifier/Honeywell Siemens Simplex/Johnson Controls

Approximately 5 years ago Johnson Controls opened a second identical Fire Alarm product line under the “Autocall” brand which is sold through independent distributors as opposed to direct factory sales of their Simplex Fire Alarm products. Will either Simplex or Autocall be acceptable?

AutoCall could be accepted under the Simplex brand. It would constitute a substitution/equivalent request, so your proposal would have to call out this request and provide documentation to show that it will meet all the salient features as required by the Specs and/or Drawings.

22R00242 Amendment 1
Amendment 1_consolidated RFI responses
2022-04-04T07:45:49-0400
ROBERT K HIGGINS