About this file

697DCK-19-R-00433amendment0001 (pdf)

View the file

Other files

File Type Posted
1402993 Roofing Project Full Spec.pdf PDF
Wagerate.pdf PDF
697DCK-19-R-00433RFO.pdf PDF
1402993 Roofing Project.pdf PDF
697DCK-19-R-00433RFO.pdf PDF
Wagerate.pdf PDF
1402993 Roofing Project.pdf PDF
1402993 Roofing Project Full Spec.pdf PDF
1402993 Roofing Project Full Spec.pdf PDF
1402993 Roofing Project.pdf PDF
Wagerate.pdf PDF
697DCK-19-R-00433RFO.pdf PDF
1402993 Roofing Project Full Spec.pdf PDF
1402993 Roofing Project.pdf PDF
697DCK-19-R-00433RFO.pdf PDF
Wagerate.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 3

3. EFFECTIVE DATE

07/2/2019

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

1200 DISTRICT AVENUE

BURLINGTON MA 01803

AAQ510BOS-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ x x

697DCK-19-R-00433

copies to the issuing office.

06/12/2019

(x)

Amendment 0001 is issued for the following clarification and questions / answers:

Clarification- The contractor will be allowed to locate their dumpsters in front of the facility adjacent to the main entrance. The contractor will be responsible to restore the site in this area. Repairs to the lawn irrigation system, sidewalks and curbs will be required if damaged. The contractor will repair all damage to the lawn areas, grade with new top soil and hydro-seed areas to restore the area. Protect shrubs adjacent to the facility, replace damaged bushes are required.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Susan J. Newcomb

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

697DCK-19-R-000433

Question- There are no taper slope indication (roof deck or insulation) on the roof drawings-

Answer- Ponding (standing water) will not be allowed on any completed roof. Install crickets and tampered insulation to insure no standing water is present on completed roofs. The contractor shall field verify the existing slope of each roof and determine the need for tapered insulation during the pre-bid walk through. It is intent of the design for the contractor to provide a roof cricket adjacent to all existing drains to insure no ponding is present after the roof is completed.

At the access doors for Roof B and Roof E there has been ponding adjacent to the access doors to these roofs. For these two areas we are requesting large crickets to be installed for 20’ out from the existing door x 25’ - to shed water away from these areas.

Question- There are no indication of electrical installation needed for lightning protection etc. Please advise.

Answer- Remove and re-install the perimeter lightning protection system cables on each roof. The contractor will need to mark the existing cables to reinstall them correctly. If the contractor misplaces or damages the existing lightning protection cable, he will need to replace the cable with cable by Thompson Lightning Protection Company (Type A28 28 x 14 gauge). Provide new cable attachments and lightning rod supports- new A730 Cable Holders for Aluminum cable installed 5’ on center and A66 Bases for Air Terminals (Thompson Lightning Protection) and 2’ air terminals (Thompson A571BT). The contractor shall confirm part numbers and quantities for a complete lightning protection system. Save all cables connectors and other hardware to be reinstalled. Replace missing or damaged parts in kind.

Question- Please provide spec/information about wall panel system to be installed:

- type of wall panels

- thickness or gage

- type of metal

- type of sub-grid and size

- gage of sub-grid

Answer- Provide metal siding to cover the existing brick along the inside of the parapet walls where called for in the contract documents. Install this siding on 1” galvanized steel hat channels that are expansion bolted to the existing brick. The new coping along the top of the parapet walls shall be fabricated to accommodate the siding installation. The corrugated siding panel shall be galvanized steel, bronze in color, and 20 gauge. Provide stainless steel screws with matching bronze covers. S &J Sheet Metal Supply (L.I. Tinsmith Supply) meets this specification.

Does this job required a bid bond? No - only payment and performance bonds are required