Please provide answers to the following questions:

1. Can you please get the total cooling tower tonnage for Northeastern Blvd We have three 500 ton cooling towers. Normal usage has one tower in operation at any

1. CT Tonnage for Murphy Drive. 11 Murphy Dr. does not have cooling towers.

1. Circulating pump Gallons per minute (GPM) for Northeastern Blvd and Murphy Drive CT pumps. Northeastern Blvd has three 1500 GPM CT pumps.

1. GPM for Murphy Drive Chiller plant Pumps.

Primary CHW Pumps (265 GPM) Loop-1 (180GPM) Loop-2 ( 280 GPM) Loop-3 (90 GPM)

Other files

File Type Posted
SIR 697DCK-19-R-00058.pdf PDF
Wage Determination.docx DOCX document
SIR 697DCK-19-R-00058.pdf PDF
Wage Determination.docx DOCX document
Wage Determination.docx DOCX document
SIR 697DCK-19-R-00058.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it.