View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0003 02/28/2020

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

2200 S. 216TH STREET

DES MOINES WA 98198-6547

AAQ530ANM-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

697DCK-20-R-00108

1 copies to the issuing office.

01/10/2020

(x)

AMENDMENT 0003 IS TO POST ADDITIONAL QUESTIONS AND THEIR APPLICABLE ANSWERS. DEADLINE DATE

FOR OFFERS REMAINS THE SAME - THURSDAY MARCH 5TH, 2020, BY 5PM MOUNTAIN TIME.

NO OTHER CHAGNES.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Cynthia A. Tjelde

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

The keynotes provided on CCF interior finishes – FY19 (Plumbing Floor Plan) are not completely clear as to which fixture is to be installed in which location. Please clarify the questions below.

KEYNOTE 1) PROVIDE CHILD SIZED TOILETS WHERE INDICATED. SEE PLUMBING SCHEDULE FOR SPECIFICATIONS. – Assumed WC‐1

ANSWER: Yes, WC‐1, which is indicated on the details sheets and described in the plumbing fixture schedule drawing.

KEYNOTE 2) PROVIDE ST ANDARD SIZED TOILETS WHERE INDICATED. SEE PLUMBING

SCHEDULE FOR SPECIFICATIONS. – Assumed WC‐2

ANSWER: Yes, WC‐2. Model number in the plumbing fixture schedule drawing indicates a wall hung replacement toile. Must be4 wall hung, but may be approved equal brand/model.

KEYNOTE 3) REINSTALL SALVAGED SINKS INTO CASEWORK. PROVIDE NEW PLUMBING FIX TURES / FAUCETS /PIPING REQUIRED FOR CONNECTION. – Utilize existing sink reinstall in same location.

ANSWER: Yes, REINSTALL in same location in NEW cabinets.

KEYNOTE 5) PROVIDE NEW ADULT HEIGHT SINK /PLUMBING FIXTURES/FAUCETS IN CASEWORK. PROVIDE NEW PIPING AS REQUIRED FOR CONNECTION. – Neither S‐3 or S‐4 seem to fit this application.

ANSWER: Description is in error. Wall hung sink and therefore should be S‐4.

KEYNOTE 6) PROVIDE ADULT HEIGHT SINGLE STAINLESS STEEL SINK ASSEMBLY. PROVIDE NEW PLUMBING FIXTURES/FAUCETS/PIPING REQUIRED FOR CONNECTION. ‐ Is this new or existing, if new which fixture?

ANSWER: NEW. It is standard that when the words PROVIDE are used in a note, the item is NEW. If it were to be reinstalled using same fixtures, the note would indicate REINSTALL instead.

KEYNOTE 7) PROVIDE CHILD HEIGHT DOUBLE STAINLESS STEEL SINK ASSEMBLY. PROVIDE NEW PLUMBING FIXTURES/FAUCETS/PIPING REQUIRED FOR CONNECTION. ‐ Is this new or existing, if new which fixture?

ANSWER: See Keynote 6 answer.

KEYNOTE 8) PROVIDE ADULT HEIGHT DOUBLE STAINLESS STEEL SINK ASSEMBLY PROVIDE NEW PLUMBING FIXTURES/FAUCETS/PIPING REQUIRED FOR CONNECTION. ‐ Is this new or existing, if new which fixture?

ANSWER: See Keynote 6 answer.

KEYNOTE 9) PROVIDE ADULT HEIGHT ( / • 30") WALL HUNG HAND SINK ASSEMBLY. PROVIDE NEW PLUMBING FIXTURES/FAUCETS/PIPING REQUIRED FOR CONNEC TION. – Assumed S‐4

ANSWER: Yes, S‐4. Model number in the plumbing fixture schedule drawing indicates a wall hung replacement sink. Must be wall hung, but may have approved equal brand.

KEYNOTE 10) PROVIDE CHILD HEIGHT ( / ‐ 24") WALL HUNG HAND SINK ASSEMBLY. ROVIDE

NEW PLUMBING FIXTURES/FAUCETS/PIPING REQUIRED FOR CONNECTION. – Assumed S‐4

ANSWER: Yes, S‐4. See Keynote 9 answer.

KEYNOTE 11) PROVIDE STANDARD SIZED HANDICAP HEIGHT TOILETS WHERE INDICATED. SEE PLUMBING SCHEDULE FOR SPECIFICATIONS. ‐ Assumed WC‐2

ANSWER: No, should be WC‐3. Model number in the plumbing fixture schedule drawing indicates ADA height floor mounted replacement toilet. May have approved equal brand.

AMEND 3
addl answers