AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 3
0001 05/24/2019
AAQ-731 FAC. & AVIATION SAFETY ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ0731-AFN
OKLAHOMA CITY OK 73125
AAQ-731 FAC. & AVIATION SAFETY ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ731-AFN
OKLAHOMA CITY OK 73125
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
6973GH-19-R-00169
1 copies to the issuing office.
05/24/2019
(x)
The purpose of this amendment is to provide the answers to Contractor's questions and to correct an error in section F.1. The proposal due date is not being extended. All proposals are due by 2:00 PM CT on Wednesday, June 26th, 2019. Three attachments have been added to FAACO for this amendment. Please acknowledge this amendment with a signed copy in your proposal package.
1. Questions and Answers for 6973GH-19-R-00169.
2. Pre Bid Sign in 6-5-2019.
3. F.1 has been changed from stating 6:00 AM to 6:00 PM to stating 7:00 AM to 4:30 PM to
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Stephanie Riddle
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
6973GH-19-R-00169/0001
reflect the correct hours stated in the specifications, Attachment 1 in the Section J.
4. All other terms and conditions shall remain in full force and effect.
5. A signed amendment must be included in your proposal package to acknowledge the amendment.
LIST OF CHANGES:
Section F - Deliveries or Performance was revised as follows.
Clause List was revised as follows.
Clause, F.1, is incorporated as follows:
F.1 WORKING HOURS
Work must be conducted between 7:00 a.m. and 4:30 p.m., Monday through Friday, excluding federally established holidays, except when prior approval has been obtained from the Contracting Officer seven (7) days in advance.
Approval for overtime work shall not be construed as an agreement for payment of overtime work.