SCOPE OF WORK
Replace antenna towers Dothan, Alabama
3/15/2018
1.0 GENERAL
All work is on FAA property located near Dothan, Alabama. There’s a gravel driveway & parking area, equipment building, three each 50' guyed towers, utility transformer, diesel tank and, other items located on the site. The FAA wants to replace the three guyed towers with self-supporting towers.
2.0 SCOPE OF WORK
The Contractor shall perform the following work:
Contractor will complete the following work for the UIS Tower Replacement Install two new 50-foot freestanding towers (GFM) rated for >110 mph max wind speed and 1/4” ice at 30 mph.
Towers shall be complete with a fall protection system, six antenna mounts on swing arms, lightning protection, tower counterpoise and connection to the building counterpoise. Towers shall meet FAA Safety Requirements and shall be grounded to the current Lightning Protection, Grounding, Bonding and Shielding standard.
Install 7 new cables from the top of each tower to the building. 3 UHF, 1 VHF, 2 standby antennas (UHF and VHF) and 1 spare cable.
Cabling shall include the following:
A Stainless Steel Junction Box at the top and bottom of the tower for connectors and or suregrounds.
A Stainless Steel Junction Box on the building for polyphaser grounds.
4” Schedule 80 PCV conduit from the top of the tower to the building. The 4/0 connecting the counterpoises will be laid over the conduit as a guard wire.
7/8” Heliax cable or equivalent from the top of the tower to the building.
FAA personnel will perform the following work to transfer the service to the new towers
Install suregrounds at the top of the tower and at the base of the tower.
Install connectors on the 7/8” Heliax cable or equivalent.
Install new antennas provided by the SSC or relocate the old antennas to the new tower.
Install LMR 400 cable with connectors from the antenna to the 7/8” cable
After the new towers are commissioned, the old towers will be removed and all conduit and cable cut off 1 foot below grade. Disturbed areas will be restored to the condition found at the beginning of construction.
The contractor may elect to install all of the new towers and return to the site after the FAA has completed the work or may stage the work so the FAA tasks can be performed during construction
2.1 GENERAL REQUIREMENTS
a.) Contractor shall repair any damage done by him to any entity, at his cost. Contractor shall be covered by minimum locally required liability insurance.
b.) Contractor must provide FAA with a safety and security plan before any work begins. Plan will include procedures for accident prevention, emergency procedures, and phone number & map to nearest emergency medical facility.
c.) All work shall be coordinated, scheduled, & approved by Montgomery FAA Airways Facility Management.
d.) Contractor will be continuously monitored by an FAA Resident Engineer during all work hours.
d.) Contractor's Superintendent shall be present at the work site during all times work is performed. Superintendent shall carry a cell phone and, be prepared to make and receive calls to & from the FAA at all times while on work site.
e.) All materials used must be approved by the FAA before installation. Submittal requirements are contained in the Specifications
2.2 WORK HOURS AND CONDITIONS
a.) Work will only be done during daylight hours between 7:00AM to 5:00PM. Mon thru Fri.
b.) Weekend work will only be authorized if necessary due to weather. No overtime will be allowed c.) Contractor will report & coordinate each days work in advance the Resident Engineer
3.0 SUBMITTALS
All plans, materials, and information will meet FAA approval before NTP. Submittal requirements are contained in the Specifications FAA-DHN- 1305201 June 14, 2017
4.0 PRE BID SITE VISIT
Pre bid site visits for this contract are not required. Contractors should be able to prepare a bid from the contract drawings and specifications. Photographs of the site conditions are contained in the appendix of the specifications. If the bidder desires a site visit, notify the FAA Contracting Officer and they will provide a date for one official site visit with the Engineer. All visitors must be escorted by an employee of FAA or, other authorized personnel.
5.0 DRAWINGS
1. DHN-D-1305201 Sheets G001 -G003, C001-C002, A001, E001-E005
2. Sky Tower 50' tower assembly drawings
5.1 SPECIFICATIONS
1. FAA-DHN- 1305201 June 14, 2017
6.0 LOCATION OF WORK
COORDINATES: N 31° 17' 37.00" W 085° 26' 26.00"
Site is located on the north side of Mance Newton Road between Napier Field Rd and Denton Rd.
The site is approximately 2.0 miles SSE of the Dothan Regional Airport
7.0 CONTACTS
Wendell Poole Manager, MGM SSC FAA Montgomery SSC 4701-A Tower Rd Hope Hull, AL 36043 Office: +1 (334) 281-7658 ext. 3003 Cell: +1 (334) 799-7626 Email: wendell.poole@faa.gov
Jerry Owens
MGM SSC COORDINATOR
FAA Montgomery SSC 4701-A Tower Rd Hope Hull, AL 36043 Office: +1 (334) 281-7658 ext. 3004 Cell: +1 (334) 549-6277 Email: jerry.owens@faa.gov
Stephen Vitale Civil Engineer Comm Eng Center - Atlanta FAA Southern Regional Office 1701 Columbia Ave College Park, GA 30337 Office:+1 (404) 305-7077 Cell: +1 (678) 637-3244 Email: stephen.vitale@faa.gov
8.0 FOR FAA USE ONLY
JCN: 1305201 JON: 1217SO0598
< ~ END OF DOCUMENT ~ >