TTC PACS QA.pdf

PDF 80 KB Posted

Attached to
TTC Ops Second Floor Storefront Wall & Doors Project
Solicitation number
693JJ624Q000015
Issued by

About this file

This document contains questions and answers related to a federal contract opportunity for the TTC Lenel On Guard Security System (PACS) project. The key details are:

The solicitation number is 693JJ624Q000016. The questions cover topics such as wiring/mounting requirements, use of j-hooks, protected vs. unprotected spaces, responsibility for telephone line installation, and door frame construction. The related federal contract opportunity is solicitation 693JJ624Q000015 for the TTC Ops Second Floor Storefront Wall & Doors Project, which is a commercial item acquisition under FAR Parts 12 and 13. The work involves installing a framed glass wall with sidelights and floor to ceiling double doors in the Operations Building at the Transportation Technology Center (TTC) in Pueblo, CO. The period of performance is up to 6 months, with a firm fixed-price contract and a 12-month warranty. The acquisition is a small business set-aside.

View the file

Other files

File Type Posted
Combined Synposis TTC Wall.pdf PDF
Attachment No.1_SOW_TTC Wall.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TTC Lenel On Guard Security System (PACS) Wednesday, August 21, 2024

693JJ624Q000016

Q&A

Questions Answers Is it possible to get an extension on the proposal due date till Monday, September 9, 2024? Unfortunately, No we are at year end.

Section D. (pg 4) Wiring/Mounting - States “All wires outside the panel enclosures by placing the wire in Conduit EMT or FLEX, cable troughs and raceways.” Are J-Hooks an acceptable wire path above the ceiling?

J hook above th ceiling tile is acceptable so long as they insert the plastic keeper to keep the wires from popping out in case they are disturbed.

Section D. (pg 4) wiring/mounting - states “The Contractor shall use EMT for all wiring located outside the protected space.

Unprotected space shall be defined as all wire runs outside of the agency space” – Please provide what is Protected and Unprotected spaces.

Please use EMT throughout for this project, protected and unprotected space.

E. (pg 5) Alarm Panel - Is the Contractor responsible for installing/running the POTS Telephone Line to the NID?

The Government will order the POTS line, however the contractor will need to advice on where the line should terminate.

Exhibit A - 1. (pg 8) Suite Entry Card Readers & PAC Controls - Section states " Each card reader-controlled door shall include magnetic door contact (recessed are preferred but surface mounted if required)” Are the door frames concrete filled?

Three door frames are filled with some type of masonry material and the remaining are not.