This document is a set of Questions and Answers related to the Request for Proposals (RFP) for the Mobile Asphalt Technology Center (MATC) Program under Solicitation Number 693JJ324R000009.

The key points are:

  • The correct labor category title is "Project Manager", not "Program Manager".
  • Attachment J.1 refers to the "Equipment Load Program" under Section C of the Statement of Work (SOW), not Section 1.3 as stated.
  • This non-personal services contract is to provide personnel, material, equipment, services, and other resources to perform the MATC Program for the Department of Transportation Federal Highway Administration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mobile Asphalt Technology Center (MATC) Program

RFP 693JJ324R000009

Question and Answers

1. The body of the RFP and Attachment J.2 refer to the Program Manager, while Attachment 1 refers to the Project Manager. Which is the correct labor category title?

Project Manager is correct.

2. Attachment J.1 says that the “PE is expected to be heavily involved with tasks in Section 1.3 of this SOW”. However, there is no Section 1.3 in the SOW (although the Equipment Loan Program is listed as the third service in Section C.1. Is the Equipment Load Program what is listed as “Section 1.3” in Attachment 1? If not, please provide the correct SOW Section?

The appropriate section is “Section C”. See Attachment J.1 for changed.