STATEMENT OF WORK FOR ROOF REPLACEMENT
American Merchant Marine Museum Statement of Work Roof Replacement Museum U.S. Merchant Marine Academy Kings Point, New York
August 13, 2016
U.S. DEPARTMENT OF TRANSPORTATION
MARITIME ADMINISTRATION
U.S. MERCHANT MARINE ACADEMY
BACKGROUND
The U.S. Merchant Martine Academy (USMMA) is a federal service academy that educates and graduates licensed merchant marine officers who serve America’s marine transportation and defense needs in peace and war. It is part of the Maritime Administration (MARAD), U.S. Department of Transportation.
The USMMA is seeking a qualified contractor, experienced in historical restoration, to provide labor, material, tools, and equipment to restore the roof on the American Merchant Marine Museum (AMMM), which is located at 300 Steamboat Road, Great Neck, New York on the USMMA campus. Both the USMMA and the AMMM are listed on the National Register of Historic Places; USMMA as a National Historic District with the AMMM listed separately.
http://www.marad.dot.gov/wp-content/uploads/pdf/Barstow_House_NR_Nomination.pdf.
The property is considered historically significant on a statewide level as a reminder of the “Golden Age” of the late nineteenth and early twentieth centuries. It is a Mediterranean Revival style that reached its final form with a major reconstruction in1930-1931. The three-story dwelling is of stucco with a terra-cotta tiled roof. The property consists of two contributing features— the William S. Barstow Mansion (the museum) and garage—which retain their integrity from the period of significance, 1915–1960. Therefore, all work shall be consistent with the Secretary of the Interior's Standards for the Treatment of Historic Properties (36 CFR part 68) http://www.nps.gov/tps/standards/four-treatments/treatment-guidelines.pdf.
Additionally, all work shall meet or exceed the standards provided by the Secretary of the Interior’s Standards for Rehabilitation and Illustrated Guidelines on Sustainability for Rehabilitating Historic Buildings http://www.nps.gov/tps/standards/rehabilitation/sustainability-guidelines.pdf and 36 CFR 67.7 - Standards for rehabilitation. http://www.nps.gov/tps/tax-incentives/taxdocs/36cfr67.pdf
SCOPE
The AMMM’s current roof consists of clay mission style barrel tiles. The roof requires restoration, with repair work being needed on the structure just below the tiles. The existing clay tiles will be salvaged and reused providing the tile is still reusable. Tiles needing replacement will be replaced with similar, sound, clay barrel tiles so that the entire roof resembles the original roof. The roof area to be restored is approximately 4,600 square feet.
The USMMA and MARAD’s objective in restoring the AMMM roof is to avoid an adverse effect. The replacement and repairs will prevent the exterior of the building from being penetrated by moisture providing weatherproofing to keep out rain, cold or heat. It must be strong enough to withstand high winds, shed water and bear the weight of heavy snow loads. To accomplish this, it has been determined that 70% of the tile and underlying structure may be salvaged for reuse, ±10%. A contractor, with extensive experience in working on historical structures, will provide methods and material options for the USMMA and MARAD to approve and consider. Should the Contractor determine that less than 70% ±10% of the tile and underlying structure is salvageable, written and visual justification must be provided to the COR for the Government to verify. Any discrepancies in justification will be the responsibility of the Contractor.
Photo 1 – South elevation, looking north
TASKS
The Contractor shall provide the following services:
1. Demolition
1.1. Remove, salvage reusable tile (@70% ±10%) and dispose of the unusable clay tiles on the original decking.
1.2. Remove and dispose of all defective wood blocking, fascia boards, battens (stringers) and debris. Salvage what can be reused.
1.3. Remove and dispose of existing underlayment and base flashings at the walls and chimneys.
2. Roofing Repairs
2.1. Install waterproof polyethylene underlayment membrane.
2.2. Replace wood blocking, battens (stringers) and fascia boards.
2.3. Replace all copper flashing at walls and chimneys.
2.4. Paint vents to match roof tile color.
3. Re-Roofing
3.1.1. Install clay, mission style, barrel roofing tiles with all accessories to include:
3.1.2. Starter strip.
3.1.3. Hip and ridge system.
3.1.4. Sealing membrane. Layer that protects against water and ice seepage.
3.1.5. Snow guards to prevent accumulated snow from falling off roof.
GENERAL
1. The Contractor shall provide all necessary labor, material, equipment, transportation and supervision for the successful performance of all tasks detailed in this statement of work.
2. The Contractor will submit a schedule to the COR 14 days prior to commencing work.
3. The Contractor shall coordinate with the COR to schedule any visits prior to commencing work.
4. The Contractor shall submit all material specifications for COR’s approval prior to commencing work.
5. The Contractor shall ensure that all work conforms to current editions, supplements and revisions of all federal, state and local codes and regulations.
6. The Contractor shall maintain a work area that complies with federal, state, and local safety standards.
7. Any damage to existing facilities or appurtenances shall be repaired or replaced, in kind, by the Contractor at no additional cost to the Government
8. The Contractor shall clean and secure all work areas at the end of each day to maintain the facility’s neat appearance.
9. The Contractor shall provide a signed warranty of any damage and defective material pursuant to the manufacturer’s warranty; improper installation and workmanship for a period of 1 year.
DELIVERABLES
1. Intact and serviceable clay barrel tiles shall be salvaged and reused. New clay tiles being incorporated into existing clay tile roofs shall be of like kind and match existing as closely as possible. Clay tiles from the same manufacturer as the original shall be used if possible. If original manufacturer is no longer in business, a known clay tile manufacturer such as Ludowici may be used providing their product is of like kind to the original.
2. Existing reusable clay tiles removed from the repair area shall be intermingled with new clay tiles to provide a smooth visual transition between new and existing areas.
3. The underlayment membrane shall be a cold applied composite self-adhering membrane, minimum 0.10 mm 0.004 inch thick, high strength polyethylene film with slip resistant embossing.
4. Nails shall be solid copper, Number 11 gauge nails, minimum 8 mm 5/16 inch head. Nails shall be of sufficient length to adequately penetrate the roof sheathing.
5. Miscellaneous fasteners may include but are not limited to: wind locks, hurricane clips, tile attachment brackets, tile nails, twisted wire (tile-tie), deck anchor systems, and flashing cleats. Fasteners shall be made of solid copper (wind locks and hurricane clips can be made of stainless steel).
EVALUATION CRITERIA
The quote that is determined to be the best value to the government will be awarded this procurement. The following criteria will be evaluated in determining best value;
1. Technical approach includes the following:
The Contractor shall provide qualified workers, trained and experienced in installing clay tile roofing systems of this configuration, and shall submit documentation of 5 consecutive years of work of this type. A list of installations shall be provided which identifies when, where, and for whom the installations were made. 35%
| 2. Past Performance | |
| Provide examples and documentation of past performance on projects involving historical structures, specifically in this type of roof replacement. 25% | |
| 3. Price | |
| 40% |
GOVERNMENT FURNISHED PROPERTY, MATERIAL, EQUIPMENT OR INFORMATION.
The Contractor is responsible for removing all debris from the work site. The work site is to be restored to its original condition.
SECURITY CONSIDERATIONS
Contractor shall submit a schedule to the COR at least 14 days prior to commencing work.
PLACE OF PERFORMANCE
Contractor will perform the task at the American Merchant Marine Museum located at the USMMA, 300 Steamboat Road, Great Neck, NY, 11024
PERIOD OF PERFORMANCE
Work is to be completed within 90 calendar days after NTP is approved. Work is to be performed during normal business hours 0800 to 1630, Monday through Friday unless an alternative schedule is granted by the Contracting Officer.
TABLE OF ACRONYMS
| ANSI | American National Standards Institute |
| ASME | (Formally known as) American Society of Mechanical Engineers |
ASHRAE American Society of Heating Refrigeration and Air Conditioning Engineers CFR Code of Federal Regulations
| COR | Contract Officer Representative | |
| EPA | Environmental Protection Agency | |
| IEEE | The Institute of Electrical and Electronics Engineers | |
| MARAD | Maritime Administration |
NEC National Electrical Code ANSI/NFPA 70 NEMA National Electrical Manufacturers Association NFPA National Fire Protection Association
| NTP | Notice to Proceed | |
| USMMA | United States Merchant Marine Academy |
APPENDIX A
APPENDIX B
Photo 2 – East elevation, looking westPhoto 3 – East elevation, looking west
Photo 4 – West elevation, looking east Page 10 of 10 DPW image3.png image4.png image5.jpeg image6.jpeg image7.jpeg image1.gif image2.gif
File details come from the government source that posted it. Updated .