Amendment 0002 - NP CATO 10(5) 11(2) ETC.pdf
PDF 3 MB Posted
- Solicitation number
- 693C73-25-B-000004
About this file
This is Amendment 0002 to solicitation 693C73-25-B-000004 issued by the Federal Highway Administration's Eastern Federal Lands Highway Division for road reconstruction work at Catoctin Mountain Park in Maryland. The amendment removes multiple FAR and Transportation Acquisition Regulation (TAR) clauses related to discrimination and merit-based opportunity pursuant to Executive Order 14173, provides responses to bidder questions, replaces bid schedule pages to revise/add pay items, and replaces several plan sheets to add standards/details, revise quantities, update the construction sign summary, and remove BIL (Bipartisan Infrastructure Law) signage.
The amendment maintains the bid opening date of March 11, 2025 at 2:00 PM EDT. Key schedule details include: Schedule A (Base Contract) with 62 calendar days performance period, Schedule B (Government Option 1) with 58 calendar days, and Schedule C (Government Option 2) with 59 calendar days. If all schedules are awarded together, total performance period is 183 calendar days. Work involves full depth reconstruction and mill/overlay of Foxville-Deerfield Road and Park Central Road, including pavement marking, drainage improvements and other miscellaneous work. Construction activities can begin as early as June 2025 pending required approvals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7325B000004 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
ATTN: CONSTRUCTION
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
ASHBURN VA 20147
ATTN: ACQUISITIONS
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1402/25/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/23/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project CATO 10(5), 11(2), ETC:
The purpose of this Amendment is to:
1. Remove the following Federal Acquisition Regulation (FAR) and Transportation Acquisition
Regulation (TAR) clauses and provisions from this solicitation in their entirety pursuant to Executive Order 14173 titled "Ending Illegal Discrimination and Restoring Merit-Based
Opportunity", effective January 21, 2025:
i. FAR clause 52.222-26 is removed from the FAR & TAR Clauses Incorporated by Reference section of the Index.
ii. FAR clause 52.222-21 is removed from the FAR & TAR Clauses Incorporated by Reference
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 27
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
693C7325B000004/0002 section of the Index.
iii. FAR clause 52.222-27 is removed from the FAR
& TAR Clauses Incorporated by Reference section of the Index.
iv. FAR clause 52.222-9 is removed from the FAR &
TAR Clauses Incorporated by Reference section of the Index.
v. FAR provision 52.222-22 is removed from both
Section D - Representations and Certifications and from the FAR Provisions Incorporated by Full
Text section of the Index.
vi. FAR provision 52.222-23 is removed from both
Section F - Socioeconomic Program Requirements and from the FAR Provisions Incorporated by Full
Text section of the Index.
vii. TAR clause 1252.222-72 is removed from both
Section G - General Contract Requirements and from the TAR Clauses Incorporated by Full Text section of the Index.
2. Provide responses to additional questions/clarifications asked by interested bidders.
3. Replace the Solicitation Bid Schedule (B
Pages) pages B-1 - B-10, to revise and add new pay items.
4. Replace Plans - CATO 10(5) 11(2) ETC sheets
A01, C01, C02, C03, C10, N01, and 524, to add
S01-S23 Standards and Details, revise pay item quantities, revise the Construction Sign Summary, revise notes, and remove BIL signage.
The bid opening date of Tuesday, March 11, 2025, at 2:00 p.m. EDT remains unchanged.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment No. 0002
Project NP CATO 10(5), 11(2), ETC
Catoctin Mountain Park Solicitation: 693C73-25-B-000004
The purpose of this Amendment is to:
1. Remove the following Federal Acquisition Regulation (FAR) and Transportation Acquisition Regulation (TAR) clauses and provisions from this solicitation in their entirety pursuant to Executive Order 14173 titled “Ending Illegal Discrimination and Restoring Merit-Based Opportunity”, effective January 21, 2025:
i. FAR clause 52.222-26 is removed from the FAR & TAR Clauses Incorporated by Reference section of the Index.
ii. FAR clause 52.222-21 is removed from the FAR & TAR Clauses Incorporated by Reference section of the Index.
iii. FAR clause 52.222-27 is removed from the FAR & TAR Clauses Incorporated by Reference section of the Index.
iv. FAR clause 52.222-9 is removed from the FAR & TAR Clauses Incorporated by Reference section of the Index.
v. FAR provision 52.222-22 is removed from both Section D - Representations and Certifications and from the FAR Provisions Incorporated by Full Text section of the Index.
vi. FAR provision 52.222-23 is removed from both Section F - Socioeconomic Program Requirements and from the FAR Provisions Incorporated by Full Text section of the Index.
vii. TAR clause 1252.222-72 is removed from both Section G - General Contract Requirements and from the TAR Clauses Incorporated by Full Text section of the Index.
2. Provide responses to additional questions/clarifications asked by interested bidders.
3. Replace the Solicitation Bid Schedule (B Pages) pages B-1 - B-10, to revise and add new pay items.
4. Replace Plans - CATO 10(5) 11(2) ETC sheets A01, C01, C02, C03, C10, N01, and 524, to add S01-S23 Standards and Details, revise pay item quantities, revise the Construction Sign Summary, revise notes, and remove BIL signage.
The bid opening date of Tuesday, March 11, 2025, at 2:00 p.m. EDT remains unchanged.
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Responses to Questions/Clarifications:
1. Typically, aggregate base is measured by the Ton not by the Cubic Yard. In the Plans, the estimated quantities are listed by the Cubic Yard. Is this able to be switched to Tons for less confusion.
Response: Pay item 30103-4000 Aggregate base grading C or D to remain as shown on the plans (Schedule A and B).
2. Type H markings require a 30 day wait period prior to placement, however there is not a pay item for any temporary striping. There are also no sign details to alert the public about no striping. What is FHWA intent in this situation?
Response: Follow the thermoplastic pavement marking manufacturer’s recommendations for application. Typically, hydrocarbon thermoplastic will require a 30 day wait period, however, an alkyd thermoplastic may be applied soon after paving.
Include “No Centerline” W8-12 signs for each schedule:
Schedule A: Quantity: 4 Signs Schedule B: Quantity: 2 Signs Schedule C: Quantity: 2 Signs
Schedule Line Item No.
Pay Item Number
Pay Item Description Unit Bid Schedule
Additional New Total Schedule A A1260 63504-1000 TEMPORARY TRAFFIC
CONTROL CONSTRUCTION
SIGN
SQFT 36 90
Schedule B B1290 63504-1000 TEMPORARY TRAFFIC
CONTROL CONSTRUCTION
SIGN
SQFT 18 70
Schedule C C1250 63504-1000 TEMPORARY TRAFFIC
CONTROL CONSTRUCTION
SIGN
SQFT 18 90
See the attached and updated Plan sheet pages.
3. Will signage quantities be updated to remove the bipartisan infrastructure signs?
Response: The bipartisan infrastructure signs will be removed from the project.
4. One note says work is permitted from November 1 to March 31. However, during this time the weather is unpredictable and paving operation are unlikely. Is this the time where unrestricted full closures can occur.
Work may progress throughout the year, including November 1 to March 31. Work on Schedule A can begin as early as June 2025, provided the necessary submittals are submitted, reviewed, and approved, except as stated in the SCRs (see SCRs for more information).
Section 108.03 subsection (3): Time adjustment for unscheduled events. Throughout the performance of the contract, there may be days or times where no work may be performed for Park security reasons. With little or no advanced notice, certain unscheduled events that affect Park roads may require the Contractor to temporarily suspend all construction operations and remove temporary lane closures. An unscheduled event that results in a temporary stoppage of construction activities will be considered the same as a single Rain Day in accordance with Subsection 155.02(h). If the unscheduled event that causes a temporary stoppage of construction activities occurs on the same day as a Rain Day, only the actual Rain Day will count.
Section 156.04.
Maintain one lane of traffic at all times.
• Close Foxville-Deerfield Road and the section of Park Central Road between Manahan
Road and Camp 3 to traffic during construction as approved by the CO. Open the roadway within 24 hours after completion of work or as directed by the CO.
• Do not close the section of Park Central Road between Foxville Road (Route 77) and Camp 3 to traffic during construction. Use single lane closures according to Section 635 and as shown in the plans.
Section 156.05)(b)
• Maintain access to Camp 3 on Park Central Road at all times. Maintain access to Owens Creek Campground on Foxville-Deerfield Road from May 1 to October 31
5. Another note states that work can start in June 2025. Can work under a single lane closure or full closure occur at this time.
Response: See response 4.
6. Can portions of Foxville-Deerfield Road and Park Central Road be closed. Is this a full closure or a one lane closure. Can this closure and work occur starting in June 2025
Response: See response 4.
7. Please Clarify the location of camp #3
Response: Location of Camp #3 is shown on Sheet A05 of the plans (± Sta. 258+00 Schedule B)
8. Does the park have a standard seed mix they would want the contractor to use? If not, would a VDOT roadside seed mix suffice?
Response: See Sheets M01-M05 of the plans, specifically Sheet M04 under criteria for allowed seed mix.
9. Please Confirm the size of culvert we are installing. The pay item B1180 – 18-Inch Equivalent Diameter Arch or Elliptical Pipe Culvert says we are to install an 18” culvert. The plans show we are to install a 14”x23” Reinforced Concrete Pipe.
Response: Install a 23”x14” RCP per the plans. See Sheet K01. See Detail E602-08.
10. In place of Diversion Fence can the contractor elect to use a Wire Backed Silt fence?
Response: No, the diversion fence in this situation is required based upon Maryland Department of Environment Water Management Administration.
11. Per the Drawings we are to install a 23”x14” RCP Pipe. Can you please specify what class RCP we are to install?
Response: Furnish and install Class HE-IV Reinforced Concrete Elliptical Pipe in accordance with
AASHTO M 207.
12. Schedule A shows 350 TN of 'Thin Lift Asphalt Concrete Pavement' (pay item A1180, shown on type sections B04 of plan set). This appears to be undefined within the the project documents as to the mix design. Per the attached, Maryland SHA guidelines show for a 0.75in lift thickness that a 4.75mm aggregate size mix would be the only potential mix which would meet the required lift thickness. Please confirm if this would meet the project requirements, and if a 64-22 liquid would be required as a binder.
Response: See Subsection 431.03 for Thin Lift Asphalt Concrete Pavement requirements. A state approved 4.75 mm mix with PG 64-22 binder that meets the requirements of Table 431-1 will be acceptable.
13. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
Response: The QC manager cannot be Superintendent or SSHO. The Superintendent may be SSHO. See Subsection 153.02 of the FP-14.
14. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
Response: See Section 108 of the FP-14.
15. Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.
Response: The Geotech and Pavement Investigation is included in the advertisement document.
16. Please provide the site visit attendee sign in sheet.
Response: The signing sheet is not required since there no pre-bid meeting.
17. Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?
Response: Fire hydrants available in Camp Round Meadow, which is in close proximity to both Park Central and Foxville Deerfield roads. Meter is not required for the use.
18. Are there any specs for the type of stone to be mortared to the head wall?
Response: The stone to be government furnished per Section 620.03 in the SCR’s.
19. Are we to replace the grate at the inlet shown on detail E604-02A? If so, what line in the pricing schedule should we account for the cost?
Response: No, replace the concrete cover only.
20. Please provide a detour plan for pricing purposes.
Response: Detour sign quantities shown in Construction Sign Summary on Sheet C10. Also refer to the Temporary Traffic Control Narrative on Sheet N01, specifically note 16.
21. Section 108.01 states that work is permitted from Nov.1 to March 31 when the weather permits. Is this correct? Please confirm.
Response: Correct, 108.01 (c) states: Work is permitted from Nov.1 to March 31 when weather permits. However, one must consider the entirety Section 108.
22. Can both roads be closed during reconstruction excavation?
Response: The contractor is allowed to close Foxville-Deerfield and Park Central Road if the closures comply with Section 156 of the SCR’s.
23. The ¾ inch paving for Foxville - Deerfield in my experience seems to be light for traffic. When visiting the site, we noticed a tractor and trailer traveling on this road. Please confirm this is what is intended.
Response: The contractor is to follow the proposed plans as designed.
24. a. Is there a waste site for this project on site or will all the material need to be hauled away?
b. Looking at the detail sheet B01, for the shoulder backup on both roads show 5” under pavement and 9” on the shoulders with 3 and 4 Inches of topsoil on top of the stone. We suggest the shoulder should be all stone. If not, the topsoil will be rutted from traffic constantly. c. Please confirm material needed.
In addition, please confirm the shoulder section should be 2” deeper in the subgrade for the shoulders.
Response: 24a: No waste site had been identified for this project. The Contractor will be responsible for hauling and disposing of material as needed.
24b & 24c: Contractor to follow plan details and insert A as shown on Sheet B01.
25. For pay items B1300 & C1270 – 64707-1000 – Mitigation, Archaeological Site Monitoring. Is a written report detailing site monitoring required? Per the Maryland Historic Trust it mentions that monitoring should have “associated reporting, recording and recovery of major features or artifacts uncovered where practical”
Response: Yes, a written report of site monitoring activities is required as part of pay items pay items B1300 & C1270 – 64707-1000.
BID SCHEDULE INSTRUCTIONS
PROJECT: CATO 10(5), 11(2), ETC
BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to
Bidders. While preparing the bid comply with the following:
COMPLETING THE BID SCHEDULE
Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual Schedule of Work by adding the amounts of the listed items and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.
To be eligible for award, bidders must submit prices for each pay item.
Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.
Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.
The amount in Block 17 of the SF 1442 should be completed as follows:
Schedule A - $ .
Schedule B - $ .
Schedule C - $ .
SCHEDULES OF WORK
The Bid Schedule is comprised of the following separate schedules and options:
Schedule A (Base Contract) - Pages B-1 through B-3
Schedule B (Government Option 1) - Pages B-4 through B-6
Schedule C (Government Option 2) - Pages B-7 through B-9
The Government will award the project as a Base Contract (Schedule A) with the option to award Schedules B and C (Government Options 1 and 2); see FAR Clauses 52.217-4 and 52.217-5.
The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedules B and C (Government Options 1 and 2) at that time. If additional funding is required for the award of Schedules B and C (Government Options 1 and 2), and is received after the award of Schedule A (Base Contract), the Government has the right to exercise Schedules B and C (Government Options 1 and 2) at the unit prices bid according to the following schedule:
Schedule B (Government Option 1): No later than the contract completion date for Schedule A (Base Contract).
Schedule C (Government Option 2): No later than the contract completion date for Schedule B (Government Option 1).
COMPLETION OF WORK
The Government has estimated the number of calendar days necessary to complete all work from the effective date of the Notice to Proceed to contract completion for the various award scenarios.
The maximum number of calendar days allowed (i.e. the contract performance period) is shown in Block 11 of the SF-1442 and described below.
If the Government awards the contract as Schedules A + B + C, the performance period to complete all work will be 183 calendar days.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 62 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 58 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 59 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and Special Contract Requirements (SCRs). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc.); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc.); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc.). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCRs).
Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-
15) may result in the start of construction activities to be no earlier than June 2025. See Subsection 108.01 of the SCRs for additional details.
BASIS FOR AWARD
The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation
Total Price of Project, which is defined as:
Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total +
Schedule C (Government Option 2) Bid Total.
B - 1
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
0002 A1000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
0002 A1010 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
0002 A1020 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A1030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
200 LNFT $____________ $____________
A1040 15705-2200 SOIL EROSION CONTROL, DIVERSION FENCE
180 LNFT $____________ $____________
A1050 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
A1060 20302-1200 REMOVAL OF GUARDRAIL
40 LNFT $____________ $____________
A1070 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
11,800 SQYD $____________ $____________
A1080 20401-0000 ROADWAY EXCAVATION
1,800 CUYD $____________ $____________
A1090 30103-4000 AGGREGATE BASE GRADING C OR D
2,400 CUYD $____________ $____________
A1110 31302-0300 AGGREGATE-TOPSOIL COURSE, 3-INCH DEPTH
2,600 SQYD $____________ $____________
A1120 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
1,350 TON $____________ $____________
A1130 40101-0900 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
1,370 TON $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP CATO 10(5), 11(2) ETC
Project Name:RECONSTRUCT ROUTE 11 FOXVILLE-DEERFIELD ROAD AND RESURFACE ROUTE 10 PARK CENTRAL ROAD
B - 2
A1140 41202-0000 TACK COAT
4,800 GAL $____________ $____________
A1150 41301-0100 ASPHALT PAVEMENT MILLING, 3/4-INCH DEPTH
8,000 SQYD $____________ $____________
A1160 41401-3000 CRACKS, CLEANING AND FILLING
1,100 LNFT $____________ $____________
A1170 41801-3000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3 (PARTIAL DEPTH PATCH)
450 SQYD $____________ $____________
A1180 43101-0000 THIN LIFT ASPHALT CONCRETE PAVEMENT
350 TON $____________ $____________
A1190 61701-4000 GUARDRAIL SYSTEM SBTB
40 LNFT $____________ $____________
A1200 62502-0000 TURF ESTABLISHMENT
3,900 SQYD $____________ $____________
A1210 63316-1000 REMOVE AND RESET SIGN
7 EACH $____________ $____________
A1220 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
40,000 LNFT $____________ $____________
A1230 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
18 EACH $____________ $____________
A1240 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
4 EACH $____________ $____________
A1250 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
76 LNFT $____________ $____________
0002 A1260 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
90 SQFT $____________ $____________
A1270 63701-0000 FIELD OFFICE
1 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
B - 3
A1280 64620-0400 REMOVE AND RESET MAILBOX
1 EACH $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
B - 4
0002 B1000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
0002 B1010 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
0002 B1020 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
B1030 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION
8 EACH $____________ $____________
B1040 20301-1900 REMOVAL OF PIPE CULVERT
1 EACH $____________ $____________
B1050 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
15,500 SQYD $____________ $____________
B1060 20401-0000 ROADWAY EXCAVATION
4,000 CUYD $____________ $____________
B1070 20402-0000 SUBEXCAVATION
35 CUYD $____________ $____________
B1080 20802-0000 FOUNDATION FILL
4 CUYD $____________ $____________
B1090 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
4 CUYD $____________ $____________
B1100 30103-4000 AGGREGATE BASE GRADING C OR D
3,200 CUYD $____________ $____________
B1120 31302-0300 AGGREGATE-TOPSOIL COURSE, 3-INCH DEPTH
1,500 SQYD $____________ $____________
B1130 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
1,800 TON $____________ $____________
Bid Schedule Schedule:B Schedule Type:Options
B - 5
B1150 40101-0900 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
3,200 TON $____________ $____________
B1160 41202-0000 TACK COAT
4,800 GAL $____________ $____________
B1170 60103-1880 CONCRETE, HEADWALL FOR 18-INCH EQUIVALENT DIAMETER PIPE
CULVERT
2 EACH $____________ $____________
B1180 60202-0200 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
30 LNFT $____________ $____________
B1190 60211-0600 END SECTION FOR 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL
PIPE CULVERT
1 EACH $____________ $____________
B1200 60409-1000 INLET TOP, CONCRETE
2 EACH $____________ $____________
B1210 60706-0000 CLEANING DRAINAGE STRUCTURE
1 EACH $____________ $____________
B1220 61401-0000 LEAN CONCRETE BACKFILL
1 CUYD $____________ $____________
B1230 62012-1000 STONE MASONRY WALL (STACKED STONE FOR CULVERT HEADWALL)
1 CUYD $____________ $____________
B1240 62502-0000 TURF ESTABLISHMENT
2,300 SQYD $____________ $____________
B1250 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
24,000 LNFT $____________ $____________
B1260 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
18 EACH $____________ $____________
Bid Schedule Schedule:B Schedule Type:Options
B - 6
B1270 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
4 EACH $____________ $____________
B1280 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
56 LNFT $____________ $____________
0002 B1290 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
70 SQFT $____________ $____________
B1300 64707-1000 MITIGATION, ARCHAEOLOGICAL SITE MONITORING
10 HOUR $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:B Schedule Type:Options
B - 7
0002 C1000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
0002 C1010 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
0002 C1020 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
C1030 15705-0100 SOIL EROSION CONTROL, SILT FENCE (WIRE-BACKED)
250 LNFT $____________ $____________
C1040 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION
15 EACH $____________ $____________
C1050 20401-0000 ROADWAY EXCAVATION
30 CUYD $____________ $____________
C1060 30302-1000 DITCH RECONDITIONING
175 LNFT $____________ $____________
C1070 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH
300 SQYD $____________ $____________
C1080 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
5,200 TON $____________ $____________
C1100 41202-0000 TACK COAT
6,400 GAL $____________ $____________
C1110 41301-0700 ASPHALT PAVEMENT MILLING, 2 1/2-INCH DEPTH
30,500 SQYD $____________ $____________
C1120 41301-1000 ASPHALT PAVEMENT MILLING, 4-INCH DEPTH
2,650 SQYD $____________ $____________
C1130 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2 (FULL DEPTH PATCH)
210 SQYD $____________ $____________
Bid Schedule Schedule:C Schedule Type:Options
B - 8
C1140 41801-3000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3 (PARTIAL DEPTH PATCH)
210 SQYD $____________ $____________
C1150 60706-0000 CLEANING DRAINAGE STRUCTURE
3 EACH $____________ $____________
C1160 60920-0000 RESET WHEELSTOP
4 EACH $____________ $____________
C1170 61901-0000 FENCE (TEMPORARY NON-GROUND PENETRATING)
300 LNFT $____________ $____________
C1180 62502-0000 TURF ESTABLISHMENT
310 SQYD $____________ $____________
C1190 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
3 SQFT $____________ $____________
C1200 63305-1700 POSTS, WOOD, 4-INCH X 4-INCH
10 LNFT $____________ $____________
C1210 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
54,000 LNFT $____________ $____________
C1220 63405-3250 PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY SYMBOL
1 EACH $____________ $____________
C1230 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
54 EACH $____________ $____________
C1240 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
3 EACH $____________ $____________
0002 C1250 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
90 SQFT $____________ $____________
C1260 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
990 HOUR $____________ $____________
C1270 64707-1000 MITIGATION, ARCHAEOLOGICAL SITE MONITORING
10 HOUR $____________ $____________
Bid Schedule Schedule:C Schedule Type:Options
B - 9
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:C Schedule Type:Options
B - 10
BID SUMMARY
Project CATO 10(5), 11(2), ETC
(1) Schedule A (Base Contract) BID Total (from Page B-3) = (1) $
(2) Schedule B (Government Option 1) BID Total (from Page B-6) = (2) $
(3) Schedule C (Government Option 2) BID Total (from Page B-9) = (3) $
Total Price of Project (for evaluation purposes only)
EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) + (3) $
Maximum Time Allowed for the Contract if Schedules A, B, and C are Awarded at the Same Time:
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 183 calendar days.
Maximum Time Allowed for Each Schedule of Work if Awarded Separately:
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 62 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 58 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 59 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
R D
Title Sheet
Symbols And Abbreviations
Location Maps
Horizontal Alignment Information
Typical Sections
MDE Standard Erosion and Sediment Control Notes
DESCRIPTION
INDEX TO SHEETS
PLANS FOR PROPOSED
PLANS PREPARED FOR
US DEPARTMENT OF INTERIOR
FREDERICK COUNTY, MARYLAND
EASTERN FEDERAL LANDS HIGHWAY DIVISION
ASHBURN, VIRGINIA
DESCRIPTION OF PROJECT
IMPROVEMENT:
PROJECT LENGTH:
ADT
AADT
SADT
ADT
V (MPH)
189 (2038)
30mph (Posted/Observed)
SPECIFICATIONS:
DESIGN DESIGNATION:
%Buses
DHV: 19vph
PROJECT NP CATO 10(5), 11(2) ETC
PROJECT NP CATO 10(5), 11(2) ETC
CATOCTIN MOUNTAIN PARK
NATIONAL PARK SERVICE
NP CATO 10(5), 11(2) ETC
PROJECT
miscellaneous work.
marking, minor drainage improvements, and other of Foxville-Deerfield Road and Park Central Road, pavement Work includes full depth reconstruction and mill and overlay
1.86 Miles
125 (2018)
210 (2018)
265 (2018)
Know what'sbelow.
before you dig.Call
R
U.S. Department of Transportation
Administration Federal Highway
SHEET
NO
A01
A02-A03
A04-A05
A06-A30
B01-B06
C01-C03
E01-E30
LANE MILES:
100% PLANS
and Bridges on Federal Highway Projects", FP-14.
"Standard Specifications for Construction of Roads
BRIDGE:
ROAD: WIDTH
18'±
20'±
SURFACE BASE
Aggregate
Aggregate
Existing
Existing
SUBGRADE
Asphalt
Asphalt
N/A
Park Central Road (Existing)
Foxville-Deerfield Road (Existing)
Project Manager
Eden Jemal, EFLHD
Lead Designer
Alazar Feleke, EFLHD
Highway Design Manager
WSP USA
JUNE 2023
Tabulation of Quantities
Park Central Road Construction Plans
PLANS PREPARED BY
Foxville-Deerfield Road Construction Plans D01-D14
M01-M02
N
AND PARK CENTRAL ROAD (ROUTE 10)
FOXVILLE-DEERFIELD ROAD (ROUTE 11)
ROADWAY RECONSTRUCTION AND RESURFACING OF
C
C
B
C
B
A
Schedule
PARK CENTRAL PICNIC PARKING
WOLF ROCK PULL-OFF
CAMP 3 TURN AROUND
PARK CENTRAL ROAD
PARK CENTRAL ROAD
FOXVILLE-DEERFIELD ROAD
Description
322+97.14 to 323+86.23
800+00 to 803+42.84
700+17.80 to 701+76.90
260+50.00 to 394+00.00
200+55.25 to 260+50.00
10+83.58 to 109+46.99
Station to Station
0.017
0.065
0.03
2.52
1.14
1.86
(miles) Length
- /Cycle 6
- /Cycle 6
-/ Cycle 6
- /Cycle 6
- /Cycle 6
- /Cycle 6
Cycle # RIP Milepost/
Route #
Foxville-Deerfield Road Park Central Road
189 (2038)
30mph (Posted/Observed)
19vph
125 (2018)
210 (2018)
265 (2018)
1% 1%
3.72 Miles
Foxville-Deerfield Road Park Central Road
3.66 Miles
7.32 Miles
SCALE IN MILES
0.5 1.0
%Trucks 1% 1%
N
KEY MAP
STATE OF MARYLAND
SALISBURY
BALTIMORE
CUMBERLAND
FREDERICK
0 4040
SCALE IN MILES
FO
X
V
IL
LE
-D
E E R
FI
E
LD
R
O A
D
PARK CENTRAL ROAD
FOXVILLE RD
CATOCTIN
H O
L L
O W
P01-P03 Permanent Pavement Marking Plan
A31-A32 Survey Information
S01-S23 Standards and Details
C04-C10 Summaries and Schedules
N01 Temporary Traffic Control Narrative
M03-M05 MDE Standard Erosion and Sediment Control Details
NPS PMIS No. 241558 NPS PMIS No. 172898
811 or 800-257-7777
Drainage ProfileK01
NoneC/A None
Existinge(max) Existing
NO. DATE BY REVISIONS
D
I m p e r ia l S h e e t c b m s \w s p
-u s -p w -0
\d
\A
N
P -C
A T
O
(5
(2 tt l.
d g n
:2
P
M
F e b r u a r y
STATE PROJECT
NUMBER
SHEET
MD NP CATO 10(5), 11(2) ETC A01
NPS Drawing No. 841/179558NPS PMIS No. 241558/172898
AMENDMENT NO. 2
02/19/25 JR REMOVED SHEET S24
TABULATION OF QUANTITIES
FOXVILLE-DEERFIELD ROAD
SCHEDULE A
SHEET 1 OF 3
1EACHREMOVE AND RESET MAILBOX 64620-0400A1280
1EACHFIELD OFFICE 63701-0000A1270
90SQFTCONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, 63504-1000A1260
76LNFTTYPE 3
TEMPORARY TRAFFIC CONTROL, BARRICADE 63503-0300A1250
4EACHCHANGEABLE MESSAGE SIGN
TEMPORARY TRAFFIC CONTROL, PORTABLE 63502-2000A1240
18EACHTEMPORARY TRAFFIC CONTROL, DRUM 63502-1300A1230
40,000LNFTPAVEMENT MARKINGS, TYPE H, SOLID 63401-1500A1220
7EACHREMOVE AND RESET SIGN 63316-1000A1210
3,900SQYDTURF ESTABLISHMENT 62502-0000A1200
40LNFTGUARDRAIL SYSTEM SBTB 61701-4000A1190
350TONTHIN LIFT ASPHALT CONCRETE PAVEMENT 43101-0000A1180
450SQYD(PARTIAL DEPTH PATCH)
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3 41801-3000A1170
1,100LNFTCRACKS, CLEANING AND FILLING 41401-3000A1160
8,000SQYDASPHALT PAVEMENT MILLING, 3/4-INCH DEPTH 41301-0100A1150
4,800GALTACK COAT 41202-0000A1140
1,370TON
AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
MIX, 3/4-INCH NOMINAL MAXIMUM SIZE
ASPHALT CONCRETE PAVEMENT, GYRATORY
40101-0900A1130
1,350TON
AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
MIX, 1/2-INCH NOMINAL MAXIMUM SIZE
ASPHALT CONCRETE PAVEMENT, GYRATORY
40101-0500A1120
2,600SQYDAGGREGATE-TOPSOIL COURSE, 3-INCH DEPTH 31302-0300A1110
2,400CUYDAGGREGATE BASE GRADING C OR D 30103-4000A1090
1,800CUYDROADWAY EXCAVATION 20401-0000A1080
11,800SQYDREMOVAL OF PAVEMENT, ASPHALT 20303-1600A1070
40LNFTREMOVAL OF GUARDRAIL 20302-1200A1060
ALLLPSMSTORM WATER POLLUTION PREVENTION PLAN 15720-0000A1050
180LNFTSOIL EROSION CONTROL, DIVERSION FENCE 15705-2200A1040
200LNFTSOIL EROSION CONTROL, FIBER ROLL 15705-1400A1030
ALLLPSMCONTRACTOR TESTING 15401-0000A1020
ALLLPSMCONSTRUCTION SURVEY AND STAKING 15201-0000A1010
ALLLPSMMOBILIZATION 15101-0000A1000
Bid Schedule
Estimated Quantities
UnitPay Item DescriptionNumber Pay Item Line Item No.
Schedule A
NO. DATE BY REVISIONS
ASHBURN, VIRGINIA
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION CATOCTIN MOUNTAIN PARK
:1
A a rc h
D e f a u lt b m s \w s p
-u s -p w -0
\d
\N
P -C
A T
O b d r.
d g n
C01
02/19/25 JR REVISED QUANTITY TO 90
AMENDMENT NO. 2 STATE PROJECT
NUMBER
SHEET
MD NP CATO 10(5), 11(2) ETC
NPS Drawing No. 841/179558NPS PMIS No. 241558/172898
PARK CENTRAL ROAD
SCHEDULE B
SHEET 2 OF 3
10HOURMONITORING
MITIGATION, ARCHAEOLOGICAL SITE 64707-1000B1300
70SQFTCONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, 63504-1000B1290
56LNFTTYPE 3
TEMPORARY TRAFFIC CONTROL, BARRICADE 63503-0300B1280
4EACHCHANGEABLE MESSAGE SIGN
TEMPORARY TRAFFIC CONTROL, PORTABLE 63502-2000B1270
18EACHTEMPORARY TRAFFIC CONTROL, DRUM 63502-1300B1260
24,000LNFTPAVEMENT MARKINGS, TYPE H, SOLID 63401-1500B1250
2,300SQYDTURF ESTABLISHMENT 62502-0000B1240
1CUYDCULVERT HEADWALL)
STONE MASONRY WALL (STACKED STONE FOR 62012-1000B1230
1CUYDLEAN CONCRETE BACKFILL 61401-0000B1220
1EACHCLEANING DRAINAGE STRUCTURE 60706-0000B1210
2EACHINLET TOP, CONCRETE 60409-1000B1200
1EACHDIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
END SECTION FOR 18-INCH EQUIVALENT 60211-0600B1190
30LNFTELLIPTICAL PIPE CULVERT
18-INCH EQUIVALENT DIAMETER ARCH OR 60202-0200B1180
2EACHEQUIVALENT DIAMETER PIPE CULVERT
CONCRETE, HEADWALL FOR 18-INCH 60103-1880B1170
4,800GALTACK COAT 41202-0000B1160
3,200TON
AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
MIX, 3/4-INCH NOMINAL MAXIMUM SIZE
ASPHALT CONCRETE PAVEMENT, GYRATORY
40101-0900B1150
1,800TON
AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
MIX, 1/2-INCH NOMINAL MAXIMUM SIZE
ASPHALT CONCRETE PAVEMENT, GYRATORY
40101-0500B1130
1,500SQYDAGGREGATE-TOPSOIL COURSE, 3-INCH DEPTH 31302-0300B1120
3,200CUYDAGGREGATE BASE GRADING C OR D 30103-4000B1100
4CUYDPLACED RIPRAP, METHOD A, CLASS 2 25101-0200B1090
4CUYDFOUNDATION FILL 20802-0000B1080
35CUYDSUBEXCAVATION 20402-0000B1070
4,000CUYDROADWAY EXCAVATION 20401-0000B1060
15,500SQYDREMOVAL OF PAVEMENT, ASPHALT 20303-1600B1050
1EACHREMOVAL OF PIPE CULVERT 20301-1900B1040
8EACHSOIL EROSION CONTROL, INLET PROTECTION 15706-1000B1030
ALLLPSMCONTRACTOR TESTING 15401-0000B1020
ALLLPSMCONSTRUCTION SURVEY AND STAKING 15201-0000B1010
ALLLPSMMOBILIZATION 15101-0000B1000
Bid Schedule
Estimated Quantities
UnitPay Item DescriptionNumber Pay Item Line Item No.
Schedule B
NO. DATE BY REVISIONS
ASHBURN, VIRGINIA
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION CATOCTIN MOUNTAIN PARK
:1 a rc h
D e f a b m s \w s p
-u s -p w -0
\d
\N
P -C
A T
O b d r.
d g n
C02
02/19/25 JR REVISED QUANTITY TO 70
AMENDMENT NO. 2 STATE PROJECT
NUMBER
SHEET
PARK CENTRAL ROAD
SCHEDULE C
SHEET 3 OF 3
10HOURMONITORING
MITIGATION, ARCHAEOLOGICAL SITE 64707-1000C1270
990HOURTEMPORARY TRAFFIC CONTROL, FLAGGER 63506-0500C1260
90SQFTCONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, 63504-1000C1250
3EACHCHANGEABLE MESSAGE SIGN
TEMPORARY TRAFFIC CONTROL, PORTABLE 63502-2000C1240
54EACHTEMPORARY TRAFFIC CONTROL, DRUM 63502-1300C1230
1EACHSYMBOL
PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY 63405-3250C1220
54,000LNFTPAVEMENT MARKINGS, TYPE H, SOLID 63401-1500C1210
10LNFTPOSTS, WOOD, 4-INCH X 4-INCH 63305-1700C1200
3SQFTSIGNS, ALUMINUM PANELS, TYPE 3 SHEETING 63304-0900C1190
310SQYDTURF ESTABLISHMENT 62502-0000C1180
300LNFTPENETRATING)
FENCE (TEMPORARY NON-GROUND 61901-0000C1170
4EACHRESET WHEELSTOP 60920-0000C1160
3EACHCLEANING DRAINAGE STRUCTURE 60706-0000C1150
210SQYD(PARTIAL DEPTH PATCH)
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3 41801-3000C1140
210SQYD(FULL DEPTH PATCH)
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2 41801-2000C1130
2,650SQYDASPHALT PAVEMENT MILLING, 4-INCH DEPTH 41301-1000C1120
30,500SQYDASPHALT PAVEMENT MILLING, 2 1/2-INCH DEPTH 41301-0700C1110
6,400GALTACK COAT 41202-0000C1100
5,200TON
AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
MIX, 1/2-INCH NOMINAL MAXIMUM SIZE
ASPHALT CONCRETE PAVEMENT, GYRATORY
40101-0500C1080
300SQYDAGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH 31302-0400C1070
175LNFTDITCH RECONDITIONING 30302-1000C1060
30CUYDROADWAY EXCAVATION 20401-0000C1050
15EACHSOIL EROSION CONTROL, INLET PROTECTION 15706-1000C1040
250LNFTBACKED)
SOIL EROSION CONTROL, SILT FENCE (WIRE-15705-0100C1030
ALLLPSMCONTRACTOR TESTING 15401-0000C1020
ALLLPSMCONSTRUCTION SURVEY AND STAKING 15201-0000C1010
ALLLPSMMOBILIZATION 15101-0000C1000
Bid Schedule
Estimated Quantities
UnitPay Item DescriptionNumber Pay Item Line Item No.
NO. DATE BY REVISIONS
ASHBURN, VIRGINIA
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION CATOCTIN MOUNTAIN PARK
:1 a rc h
D e f a b m s \w s p
-u s -p w -0
\d
\N
P -C
A T
O b d r.
d g n
C03
AMENDMENT NO. 2
02/19/25 JR REVISED QUANTITY TO 90
STATE PROJECT
NUMBER
SHEET
SUMMARIES AND SCHEDULES
SHEET 7 OF 7
NO. DATE BY REVISIONS
ASHBURN, VIRGINIA
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION CATOCTIN MOUNTAIN PARK
:1 a rc h
D e f a b m s \w s p
-u s -p w -0
\d
\N
P -C
A T
O b d r.
d g n
C10
02/19/25 JR REMOVED BIL SIGNS, ADDED W8-12 SIGNS
AMENDMENT NO. 2 STATE PROJECT
NUMBER
SHEET
8. Contractor employee's personal vehicles are not permitted to park along roadway shoulders.
conducted if able to be completed in one day's or night's operation.
e) Do not leave lane closures unattended. Pavement repairs, such as Patching or Milling and Overlay, should only be
CO.
d) During periods of inactivity, re-open the roadway to two-way, two lane traffic unless approved otherwise by the
c) Lane closures are permitted weekdays and weeknights, except for the periods listed in General Note #9 and #10.
mile for all activities on Park Central Road.2 1 b) The maximum length of a lane closure is
a) A maximum of one single lane temporary closure is permitted during Schedule C.
except as noted in General Note #9 (d).
7. Maintain two-way, one lane of traffic using flaggers according to Standard 635-6 through active construction zones,
6. Maintain access on Park Central Road (Schedule C) using lane closures with flaggers.
Foxville-Deerfield Road from May 1 to October 31.
5. Maintain access to Camp 3 on Park Central Road at all times. Maintain access to Owen Creeks Campground on to Camp 3 and of Foxville-Deerfield Road, using Temporary Traffic Control, Barricade, Type 3.
4. Perform work for Schedule A and B under full roadway closure of Park Central Road from Manahan Road
3. Do not stop traffic for more than 10 minutes at each single lane closure.
2. Cover all conflicting signs during construction operations.
c) Remove temporary traffic control devices upon contract completion or when directed otherwise by the CO.
additional devices for lane closure according to Detail E635-01 and Standards 635-1 and 635-6.
through the completion of all construction activities according to Detail E635-01 and Standard 635-1. Install
b) Install temporary traffic control devices for advanced signing prior to beginning the project and maintain devices
a) Obtain approval from the CO for location and spacing of temporary traffic control devices.
Special Contract Requirements Section 156, Section 635, and the latest edition of the MUTCD.
1. Provide and maintain temporary traffic control devices for the duration of the project in accordance with FP-14 and
GENERAL NOTES:
pavement marking, minor drainage improvements, and other miscellaneous work.
This project consists of full depth reconstruction and mill and overlay of Foxville-Deerfield Road and Park Central Road, PROJECT DESCRIPTION:
CONTROL NARRATIVE
TEMPORARY TRAFFIC
(Schedule C) to ensure one sign is present at the start and end points of construction limits during work on the project.
(Schedule A), and 1 at the beginning of Park Central Road (Schedule B) and 1 at the end of Park Central Road
17. Place 1 Bipartisan Infrastructure Law Project Sign at the beginning and 1 at the end of Foxville-Deerfield Road or south of Owens Creek Campground on Foxville-Deerfield Road (Schedule A).
outside of operational season dates. Use Manahan Road as a detour route during full roadway closure either north from May 1 to October 31. Roadway reconstruction preventing access to Owens Creek Campground is permitted
16. Close Foxville-Deerfield Road in sections to maintain access to Owens Creek Campground during operational season
Central Road (Schedule B), and 1 at the beginning and 2 at the end of Park Central Road (Schedule C).
intersection of Park Central Road and Foxville-Deerfield Road (Schedule A), 3 at the beginning and 1 at the end of Park at the beginning and 1 at the end of Foxville-Deerfield Road and 1 at the portable changeable message signs15. Place 2
14. Use Type III retroreflective sheeting for all construction signs.
Obtain approval from the CO before using any other area for staging or stockpiling.
13. Staging location is defined in Subsection 156.07(d). Obtain approval from the CO before using designated staging location.
the message and maintenance of signs.
Contractor is responsible for the portable changeable message signs 24 hours a day, including inputting and changing approved by the CO. Coordinate message text on the portable changeable message signs through the CO. The
12. Place post-mounted advance warning signs and portable changeable message signs at approximate locations as and ending at 7:00 a.m. the following day.
11. Work is permitted at night with lighting plan approved by the CO. Nighttime hours are defined as beginning at 7:00 p.m.
stoppage of construction activities occurs on the same day as a Rain Day, only the actual Rain Day will count.
as a single Rain Day in accordance with Subsection 155.02(h) If the unscheduled event that causes a temporary An unscheduled event that results in a temporary stoppage of construction activities will be considered the same require the Contractor to temporarily suspend all construction operations and remove temporary lane closures.
Park security reasons. With little or no advanced notice, certain unscheduled events that affect Park roads may
10. Throughout the performance of the contract, there may be days or times where no work may be performed for at least 7 days before the planned work.
If the Contractor finds it necessary to work on one of these restricted days, request approval from the CO
d) No work will be permitted on days with special events occurring in the vicinity as determined by the CO.
c) Work is permitted from November 1 to March 31 when weather permits as defined in Subsection 108.01(c).
b) No work will be permitted from 7:00 p.m. on Friday to 7:00 a.m. on the following Monday.
a) No work will be permitted on National legal holidays.
9. Construction operations are limited as follows:
NO. DATE BY REVISIONS
ASHBURN, VIRGINIA
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION CATOCTIN MOUNTAIN PARK
:1 a rc h
D e f a b m s \w s p
-u s -p w -0
\d
\N
P -C
A T
O b d r.
d g n
N01
02/19/25 JR REMOVED NOTE 17
AMENDMENT NO. 2 STATE PROJECT
NUMBER
SHEET
500 feet on roadways with speed limits greater than 45 mph.iii.
200 feet on roadways with speed limits of 30 to 45 mph, andii.
150 feet on roadways with speed limits of less than 30 mph,i.
minimum spacing from other traffic control signs should be:
Shall not interfere with temporary traffic control devices, and the d) the final inspection or project closeout has not yet occurred.
Shall be removed at the conclusion of work on the project, even if c) some future date.
used to provide advance notification of road work that will begin at
Shall not be installed prior to the commencement of work or be b) as directed by the Contracting Officer.
Shall be located at the start and end points of construction limits or a)
Project information signs using the official Investing In America emblem:
Installation shall be in accordance with Detail E635-01.
based.
be limited to one per direction of travel on the roadway on which the project is
Project information signs using the official Investing In America emblem shall
3.
2.
1.
NO. DATE BY REVISIONS
NOTES:
635-A
LAW SIGN
BIPARTISAN INFRASTRUCTURE
:0
P
J u n e
S td
-6 c b m s \w s p -u s -p w -0
\d
\S td -A
.d g n
CFLHD SPECIAL
SPECIAL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
STATE PROJECT
NUMBER
SHEET
MD NP CATO 10(5), 11(2) ETC S24
NPS Drawing No. 841/179558NPS PMIS No. 241558/172898
AMENDMENT NO. 2
02/19/25 JR REMOVED BIL SIGN
| Amendment No. 0002 |
| Project NP CATO 10(5), 11(2), ETC |
| Catoctin Mountain Park |
| Solicitation: 693C73-25-B-000004 |
| Bid Schedule Instructions.pdf |
| BID SCHEDULE INSTRUCTIONS |
| COMPLETING THE BID SCHEDULE |
| SCHEDULES OF WORK |
| The Government will award the project as a Base Contract (Schedule A) with the option to award Schedules B and C (Government Options 1 and 2); see FAR Clauses 52.217-4 and 52.217-5. |
| Schedule A (Base Contract). |
| Schedule B (Government Option 1). |
| COMPLETION OF WORK |