Amendment 0003 - FW TREM 10(1).pdf
PDF 4 MB Posted
- Attached to
- Trempealeau National Wildlife Refuge
- Solicitation number
- 693C73-24-B-000007
About this file
This amendment modifies a solicitation for a federal construction project. The project involves grading, roadway work, drainage structures, pavement, guardrails and other work at the Trempealeau National Wildlife Refuge in Wisconsin. The amendment revises the bid schedule and plans to add and modify bid items, update specifications, and provide responses to bidder questions. Bids are due from certified small businesses by March 21, 2024. The solicitation seeks completion of work in multiple schedules and options with a total project cost expected between $2 million to $5 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Results of Bid Opening - FW TREM 10(1).pdf | ||
| Amendment 0002 - FW TREM 10(1).pdf | ||
| Amendment 0001 - FW TREM 10(1).pdf | ||
| VETS-4212 Form.pdf | ||
| ADV_Bidders Qualifications Form.doc | DOC document | |
| Categorical Exclusion Form (NEPA).pdf | ||
| FP14_Eng.pdf | ||
| Bridge_Insp_Rpt.pdf | ||
| IFB Solicitation - FW TREM 10(1).pdf | ||
| Plans - FW TREM 10(1).pdf | ||
| GeotechMemo.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7324B000007 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
ATTN: Construction
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
ASHBURN VA 20147
ATTN: Acquisitions
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1403/11/20240003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/02/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project FW-TREM 10(1)
The purpose of this Amendment is to:
1. Replace the Bid Schedule to add and revise bid items.
2. Revise the Special Contract Requirements (J-pages) as follows:
a. Revise Table 109-2 to update the eligible asphalt pay item.
b. Delete Section 401 and add Section 403.
3. Revise the Plans as follows:
a. Revise the Typical Sections to change the asphalt pavement type.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 32
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
693C7324B000007/0003
b. Revise the Tabulation of Quantities and
Summary and Schedule sheets to add and revise bid items.
c. Add a concrete sidewalk detail.
d. Correct the sheet numbering.
4. Provide a summary of responses to questions/clarifications asked by bidders.
5. The bid opening date of March 21, 2024, at
2:00 p.m. EDT remains unchanged.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment No. 0003
Info Page 1 of 1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Project FW-TREM 10(1)
Trempealeau National Wildlife Refuge
Solicitation: 693C73-24-B-000007
The purpose of this Amendment is to:
1. Replace the Bid Schedule to add and revise bid items.
2. Revise the Special Contract Requirements (J-pages) as follows:
a. Revise Table 109-2 to update the eligible asphalt pay item.
b. Delete Section 401 and add Section 403.
3. Revise the Plans as follows:
a. Revise the Typical Sections to change the asphalt pavement type.
b. Revise the Tabulation of Quantities and Summary and Schedule sheets to add and revise bid items.
c. Add a concrete sidewalk detail.
d. Correct the sheet numbering.
4. Provide a summary of responses to questions/clarifications asked by bidders.
5. The bid opening date of March 21, 2024, at 2:00 p.m. EDT remains unchanged.
Bid Schedule Changes Page 1 of 1
Bid Schedule Changes
1. Delete the Solicitation Bid Schedule pages B-1 through B-10 and substitute the amended Bid
Schedule pages B-1 through B-10.
B - 1
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A1000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A1010 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A1020 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A1030 15705-0100 SOIL EROSION CONTROL, SILT FENCE
2,200 LNFT $____________ $____________
A1040 15705-2000 SOIL EROSION CONTROL, FLOATING TURBIDITY CURTAIN
50 LNFT $____________ $____________
A1050 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
1 EACH $____________ $____________
A1060 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
A1070 20120-1000 REMOVAL, INDIVIDUAL TREE
5 EACH $____________ $____________
A1080 20302-1200 REMOVAL OF GUARDRAIL
200 LNFT $____________ $____________
A1090 20302-2100 REMOVAL OF PIPE CULVERT
250 LNFT $____________ $____________
A1100 20401-0000 ROADWAY EXCAVATION
1,190 CUYD $____________ $____________
A1110 20426-1000 DITCH, EXCAVATION
410 CUYD $____________ $____________
A1120 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
2,000 SQYD $____________ $____________
A1130 20801-0000 STRUCTURE EXCAVATION
430 CUYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
Amendment 0003
B - 2
A1140 20815-0000 COFFERDAMS
ALL LPSM $___LPSM_____ $____________
A1150 25102-0400 PLACED RIPRAP, METHOD A, CLASS 4
250 TON $____________ $____________
A1160 30101-4000 AGGREGATE BASE GRADING C OR D
800 TON $____________ $____________
A1170 50101-0800 MINOR CONCRETE PAVEMENT, REINFORCED, 8-INCH DEPTH
2,100 SQYD $____________ $____________
A1180 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
100 CUYD $____________ $____________
A1190 55401-1000 REINFORCING STEEL
12,000 LB $____________ $____________
A1200 58202-0000 HELICAL PILE, IN PLACE
40 EACH $____________ $____________
A1210 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT (20 FEET SPAN, 4 FEET
RISE)
52 LNFT $____________ $____________
A1220 60901-1300 CURB, CONCRETE, 15-INCH DEPTH
95 LNFT $____________ $____________
A1230 60901-1900 CURB, CONCRETE, 20-INCH DEPTH AND VARIES
90 LNFT $____________ $____________
A1240 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
125 LNFT $____________ $____________
A1250 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
2 EACH $____________ $____________
A1260 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM
22 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 3
A1270 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGICAL MONITORING)
ALL LPSM $___LPSM_____ $____________
A1280 62501-0000 TURF ESTABLISHMENT
0.5 ACRE $____________ $____________
A1290 62901-1200 ROLLED EROSION CONTROL PRODUCT, TYPE 5.A
500 SQYD $____________ $____________
A1300 63316-1000 REMOVE AND RESET SIGN
3 EACH $____________ $____________
A1310 63501-0000 TEMPORARY TRAFFIC CONTROL
ALL LPSM $___LPSM_____ $____________
A1320 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION
ALL CTSM $___CTSM_____ $100,000.00
A1330 63701-0000 FIELD OFFICE
1 EACH $____________ $____________
A1340 64501-0000 LOCATE UTILITIES
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 4
B2000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
B2010 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
B2020 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
B2030 15705-0100 SOIL EROSION CONTROL, SILT FENCE
550 LNFT $____________ $____________
B2040 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
B2050 20301-0100 REMOVAL OF BOLLARD
42 EACH $____________ $____________
B2060 20301-2400 REMOVAL OF SIGN
3 EACH $____________ $____________
B2070 20302-0700 REMOVAL OF FENCE
190 LNFT $____________ $____________
B2080 20302-1200 REMOVAL OF GUARDRAIL
440 LNFT $____________ $____________
B2090 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
400 SQYD $____________ $____________
B2100 20315-0000 SAWCUTTING PAVEMENT
110 LNFT $____________ $____________
B2110 20401-0000 ROADWAY EXCAVATION
60 CUYD $____________ $____________
B2120 25125-0000 BOULDER (3' DIAMETER)
22 EACH $____________ $____________
B2130 30101-4000 AGGREGATE BASE GRADING C OR D
130 TON $____________ $____________
Bid Schedule Schedule:B Schedule Type:Options
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 5
0003 B2140 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL , TYPE IV ROUGHNESS
220 TON $____________ $____________
0003 B2145 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA, <0.3 MILLION
ESAL, PG 64-22, TYPE IV PAVEMENT ROUGHNESS)
220 TON $____________ $____________
0003 B2150 40101-0900 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL
90 TON $____________ $____________
0003 B2155 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (3/4-INCH NMSA, <0.3 MILLION
ESAL, PG 64-22)
90 TON $____________ $____________
B2160 41201-0000 TACK COAT
2 TON $____________ $____________
B2170 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
230 LNFT $____________ $____________
B2180 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
2 EACH $____________ $____________
B2190 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM
22 LNFT $____________ $____________
B2200 61902-0000 GATE (REPLACEMENT OF GATE OPENING SYSTEMS)
1 EACH $____________ $____________
B2210 61902-1700 GATE, METAL, 22 FEET WIDTH
1 EACH $____________ $____________
B2220 62617-1400 QUERCUS MACROCARPA, BUR OAK, 7 GALLON, CONTAINER GROWN
1 EACH $____________ $____________
B2230 63301-0000 SIGN SYSTEM (SIGN POSTS WITH STONE MASONRY SIGN BASE)
1 EACH $____________ $____________
Bid Schedule Schedule:B Schedule Type:Options
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 6
B2240 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
55 SQFT $____________ $____________
B2250 63501-0000 TEMPORARY TRAFFIC CONTROL
ALL LPSM $___LPSM_____ $____________
B2260 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION
ALL CTSM $___CTSM_____ $100,000.00
B2270 64501-0000 LOCATE UTILITIES
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:B Schedule Type:Options
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 7
C3000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
C3010 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
C3020 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
C3030 15705-0100 SOIL EROSION CONTROL, SILT FENCE
1,800 LNFT $____________ $____________
C3040 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
C3050 20103-0000 CLEARING AND GRUBBING
2,700 SQYD $____________ $____________
C3060 20301-2400 REMOVAL OF SIGN
17 EACH $____________ $____________
C3070 20302-0700 REMOVAL OF FENCE
30 LNFT $____________ $____________
C3080 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
600 SQYD $____________ $____________
C3090 20401-0000 ROADWAY EXCAVATION
950 CUYD $____________ $____________
C3100 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
26,000 SQYD $____________ $____________
C3110 21101-1000 ROADWAY OBLITERATION, METHOD 1
650 SQYD $____________ $____________
C3120 30101-4000 AGGREGATE BASE GRADING C OR D
100 TON $____________ $____________
C3140 30110-0000 AGGREGATE SURFACE COURSE
6,500 TON $____________ $____________
Bid Schedule Schedule:C Schedule Type:Options
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 8
0003 C3150 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL , TYPE IV ROUGHNESS
70 TON $____________ $____________
0003 C3155 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA, <0.3 MILLION
ESAL, PG 64-22, TYPE IV PAVEMENT ROUGHNESS)
70 TON $____________ $____________
C3160 41201-0000 TACK COAT
1 TON $____________ $____________
C3170 60201-0800 24-INCH PIPE CULVERT (CMP)
50 LNFT $____________ $____________
C3180 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (CMP)
2 EACH $____________ $____________
C3190 60915-1000 WHEELSTOP, CONCRETE
7 EACH $____________ $____________
0003 C3195 61501-0100 SIDEWALK, CONCRETE
115 SQYD $____________ $____________
C3200 61902-0000 GATE (AUTOMATIC)
1 EACH $____________ $____________
C3210 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGICAL MONITORING)
ALL LPSM $___LPSM_____ $____________
C3220 62501-0000 TURF ESTABLISHMENT
0.5 ACRE $____________ $____________
C3230 62901-1200 ROLLED EROSION CONTROL PRODUCT, TYPE 5.A
650 SQYD $____________ $____________
C3240 63301-1000 SIGN SYSTEM, GOVERNMENT FURNISHED SIGN
1 EACH $____________ $____________
C3250 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
95 SQFT $____________ $____________
Bid Schedule Schedule:C Schedule Type:Options
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 9
C3260 63316-1000 REMOVE AND RESET SIGN
2 EACH $____________ $____________
C3270 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
220 LNFT $____________ $____________
C3280 63405-3250 PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY SYMBOL
1 EACH $____________ $____________
C3290 63501-0000 TEMPORARY TRAFFIC CONTROL
ALL LPSM $___LPSM_____ $____________
C3300 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION
ALL CTSM $___CTSM_____ $50,000.00
C3310 64501-0000 LOCATE UTILITIES
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:C Schedule Type:Options
Project No:FW-TREM 10(1)
Project Name:Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100)
B - 10
BID SUMMARY
Project FW TREM 10(1)
(1) Schedule A (Base Contract) Bid Total (from Page B-3) = (1) $
(2) Schedule B (Government Option 1) Bid Total (from Page B-6) = (2) $
(3) Schedule C (Government Option 2) Bid Total (from Page B-9) = (3) $
Total Price of Project (for evaluation purposes only)
EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) + (3) $
Maximum Time Allowed for the Contract if Schedules A, B, and C are Awarded at the Same
Time:
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 580 calendar days.
Maximum Time Allowed for Each Schedule of Work if Awarded Separately:
If the Government awards the contract as Schedule A only, the performance period to complete all
Schedule A work will be 580 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 21 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 78 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
Special Contract Requirements Changes Page 1 of 5
Special Contract Requirements (J Pages) Changes
1. Delete Table 109-2 of the Special Contract Requirements, page J-8, and substitute the following:
Table 109-2
Eligible Pay Items for Price Adjustments and Associated Fuel Usage Factors
Eligible Pay Items Fuel Usage Factor
U.S. Customary Units
Fuel Usage Factor
Metric Units
Earthwork Section 204 – Excavation and Embankment
20401 Roadway excavation
0.30 gallons per cubic yard 0.39 gallons per cubic meter
Aggregate and Base Courses Section 301 – Untreated Aggregate Courses
30101 Aggregate base
30110 Aggregate surface course
0.70 gallons per ton 0.77 gallons per metric ton
Asphalt Pavements Section 403 – Asphalt Concrete
40301 Asphalt concrete pavement
2.40 gallons per ton 2.65 gallons per metric ton
* The Government, to agree with the units associated with the applicable Fuel Usage Factor, will convert work quantities as necessary.
2. Delete Section 401 of the Special Contract Requirements, pages J-17 to J-23, and substitute the following:
Delete Section 403 and substitute the following:
Section 403. — ASPHALT CONCRETE
Description
403.01 This work consists of constructing asphalt concrete facilities using a hot or warm mix asphalt (HMA or WMA).
Construction Requirements
403.02 Composition of Mix (Job-Mix Formula). Conform to current state department of transportation material specifications for asphalt concrete.
Submit a state department of transportation JMF approved within the past 12 months for approval at least 30 days before production that meets the current state department of transportation requirements for the location and type of facility being constructed.
Special Contract Requirements Changes Page 2 of 5
For each proposed JMF, submit a production certification conforming to state department of transportation specifications. Submit the strength, quality, and gradation specifications for the asphalt concrete mix. Include copies of laboratory test reports that demonstrate aggregate, asphalt binder, additive, and mix properties meet state department of transportation specifications. Submit the maximum specific gravity (density) of the mix as determined by
AASHTO T 209.
If requested, submit a representative 100-pound loose mix sample 21 days before placement.
403.03 Production Start-Up Procedures. Conform to Subsection 153.04(b).
403.04 Equipment. Conform to Subsection 401.05.
403.05 Surface Preparation. Conform to Subsection 401.06.
403.06 Weather Limitations. Conform to Subsection 401.07.
403.07 Hauling. Conform to Subsection 401.11.
403.08 Placing and Finishing. Do not use mixes produced from different plants unless the mixes are produced according to the same JMF, use material from the same sources, and are approved.
Place HMA at temperatures shown in Table 401-2. Place WMA at temperatures according to
Subsection 401.03(c)(5). Measure temperature of the asphalt concrete mix in the hauling vehicle immediately before dumping into the spreader or measure it in the windrow immediately before pickup.
Place the mix with a paver conforming to Subsection 401.05. Control horizontal alignment using a reference line. Automatically control the grade and slope from reference lines, a ski and slope control device, or dual skis. Use skis having a minimum length of 20 feet.
In areas where mechanical spreading and finishing are impractical, place and finish the asphalt concrete mix by other approved methods to produce a uniform finished surface.
Offset the longitudinal joint according to Subsection 401.13.
403.09 Compacting. Thoroughly and uniformly compact the asphalt surface by rolling. In places inaccessible to rollers, use approved alternate equipment. Do not cause cracking, shoving, or undue displacement.
Monitor the compaction process with nuclear density gauges calibrated according to ASTM
D2950 within 6 months before use. Check the standard and reference on each day of use according to the ASTM D2950 standardization and reference check sections. Compact to at least
91.0 percent of the maximum specific gravity (density) determined in Subsection 403.02.
Special Contract Requirements Changes Page 3 of 5
Do not pass rollers over an unsupported edge of freshly laid asphalt concrete mix. Continue rolling until roller marks are eliminated, cracks are sealed, and the required density is obtained.
For HMA, do not roll the mix after the surface cools below 175 °F.
403.10 Joints, Trimming Edges, and Cleanup. Conform to Subsection 401.15.
403.11 Pavement Straightedge Measurement. Measure the pavement surface using a 10-foot metal straightedge at right angles and parallel to the centerline. Defective areas are deviations between the surface and the bottom of the straightedge more than ¼ inch measured between two contacts of the straightedge or deviations more than ¼ inch measured at the end of the straightedge.
Correct defective areas according to Subsection 401.16(g). Obtain approval for the method of correction.
403.12 Acceptance. See Table 403-1 for sampling, testing, and acceptance requirements. If no asphalt concrete type is designated, evaluate according to Type I in Table 403-1.
Asphalt binder will be evaluated under Subsection 106.03.
Asphalt concrete mix properties will be evaluated under Subsections 106.03 and 106.04.
Construction of asphalt concrete facilities will be evaluated under Subsections 106.02 and
106.04.
Pavement straightedge measurement will be evaluated under Subsection 106.04.
Measurement
403.13 Measure the Section 403 pay items listed in the bid schedule according to Subsection
109.02.
Payment
403.14 The accepted quantities will be paid at the contract price per unit of measurement for the
Section 403 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Special Contract Requirements Changes Page 4 of 5
Table 403-1
Sampling, Testing, and Acceptance Requirements Material or
Product
(Subsection)
Type of
Acceptance
(Subsection)
Characteristic Test Methods
Specifications
Sampling
Frequency
Point of
Sampling
Split
Sample
Reporting
Time Remarks
Mix Design
Asphalt concrete, Type I
Measured & tested for conformance
(106.04)
Job-mix formula
Subsection
403.02 If requested
Flowing mix stream (bin or belt discharge) or behind the paver before compaction
Yes
Before approval of job-mix formula
Tested by the
Government
Production
Asphalt concrete, Type I
Measured & tested for conformance
(106.04)
Job-mix formula
Subsection
403.02
1 per
700 tons
Behind the paver before compaction Yes 24 hours −
Density(1)
AASHTO
T 166
In-place after compacting
Deliver cores to CO after testing is completed
Maximum specific gravity(2),(3)
AASHTO
T 209
Behind the paver before compaction
Surface tolerance
Straightedge measurement, Subsection
403.11
Continuously, after compaction
Finished pavement surface No " −
Placement temperature
First load and as directed thereafter
Hauling vehicle before dumping, or windrow before pickup
Upon completion of measurement
Process control
(153.03)
Gradation at the plant
AASHTO
T 27 & T 11
Contractor determined
Cold feed or hot bins as applicable No 24 hours −
Moisture content of aggregates
AASHTO
T 255 " Stockpile " " −
Density ASTM D2950 1 per 500 ft In-place after compacting
Special Contract Requirements Changes Page 5 of 5
Table 403-1 (continued)
Sampling, Testing, and Acceptance Requirements Material or
Product
(Subsection)
Type of
Acceptance
(Subsection)
Characteristic Test Methods
Specifications
Sampling
Frequency
Point of
Sampling
Split
Sample
Reporting
Time Remarks
Asphalt concrete, Type II
Measured & tested for conformance
(106.04)
Density ASTM D2950 1 per 500 ft In-place after compacting No 24 hours −
Surface tolerance
Straightedge measurement, Subsection
403.11
Continuously, after compaction
Finished pavement surface
Placement temperature
First load and as directed thereafter
Hauling vehicle before dumping, or windrow before pickup
Upon completion of measurement
(1) For asphalt concrete Type I, cut two 6-inch diameter side by side cores. Obtain cores as soon as the pavement has cooled sufficiently to allow coring, but not later than 12 hours after final rolling. Remove them with a core retriever and fill and compact the core holes with asphalt concrete mixture. Label the cores and protect them from damage due to handling and temperature. Submit one core for verification testing. Dry the other core to constant mass at 125±5 °F or vacuum dry it according to ASTM D7227 before performing the core density and measuring the thickness. Use 62.245 pounds per cubic foot to convert specific gravity to density.
(2) After production paving has begun, use the average maximum specific gravity value (AASHTO T 209) for each day to adjust the percent compaction for the cores that represent that day’s paving.
(3) Do not use the supplemental procedure for mixtures containing porous aggregate (dry back method of AASHTO T 209)
Plan Sheet Changes Page 1 of 1
Plan Sheet Changes
1. Delete Plan Sheets B01, B03, B07, C01, C02, C04, and S23, and substitute amended Plan
Sheets B01, B03, B07, C01, C02, C04, and S23.
2. Add new Plan Sheet S14A.
LC
(Route 010)
Entrance Road
PROPOSED:
LC
(Route 010)
Entrance Road
Travel laneTravel lane
EXISTING:
PROPOSED:
Lateral limit of disturbance
9'9' of power line Approximate location
Shld.
2'2'
Shld.
1V:3H
Match existing Match existing
ASPHALT CONCRETE PAVEMENT OVERLAY
116+25 to 117+43
113+00 to 115+00
100+15 to 101+70
1V:
3H
Tack coat
PG 64-22, Type IV pavement roughness) " NMSA, <0.3 Million ESAL,2
2" ACP, Type I (
Profile grade unknown depth Existing asphalt pavement, Existing ground
LC
(Route 010)
Entrance Road
Travel laneTravel lane
EXISTING:
PROPOSED:
Lateral limit of disturbance
9'9'
Match existing Match existing
ROADWAY RECONSTRUCTION
Tack coat
Profile grade unknown depth Existing asphalt pavement, Aggregate shoulder (typ.)
117+43 to 117+70
115+00 to 116+25
PG 64-22)
" NMSA, <0.3 million ESAL, ¾4" ACP, Type I ( concrete pavement full depth
Saw cut and remove asphalt
Existing ground
1V:3H
'1V:
3H
2'
Shld. Shld.
2' of power line Approximate location
Aggregate shoulder (typ.)
6" Aggregate Base, grading C or D
Roadway excavation accordance with Section 625.
except paved or rock surfaces. Establish turf in
Apply turf establishment on all disturbed areas, Note:
Geotextile, Class 2, Type E
(No pay) Saw cut
(No pay) Saw cut
PG 64-22, Type IV pavement roughness) " NMSA, <0.3 Million ESAL,2
2" ACP, Type I (
NO. DATE BY REVISIONS
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
SCHEDULE B
ENTRANCE ROAD
TREMPEALEAU NATIONAL WILDLIFE REFUGE
TYPICAL SECTIONS
NO SCALE
:1
P
M a r c h
B fh fl fi le s e rv e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v
\C A
D D
\B
-B
T
R E
M
(2
F W
S re v
T Y
P .d g n
STATE PROJECT
NUMBER
SHEET
WI FW-TREM 10(1) B01
SAMMS 2012218848
1 03/07/2024 CHD Changed kind of asphalt from Section 401 to Section 403.
(Route 010)
Entrance Road
Travel laneTravel lane
EXISTING:
PROPOSED:
Lateral limit of disturbance
13'13' existing Match existing Match
ROADWAY RECONSTRUCTION AT BRIDGE APPROACH
Tack coat
Profile grade unknown depth Existing asphalt pavement, Aggregate shoulder (typ.)
112+85 to 113+00
(place in two equal lifts with tack coat between lifts)
6" ACP, Type I (¾" NMSA, <0.3 Million ESAL, PG 64-22) concrete pavement full depth
Saw cut and remove asphalt
Existing ground
1V:3H
'1V:
3H
2'
Shld. Shld.
2' of power line Approximate location
A
A
1V:
2H
End of bridge
2' 4'
Tack coat
Roadway excavation
SECTION A-A
profile grade Match existingconcrete pavement full depth
Saw cut and remove asphalt
Aggregate base, Grading C or D profile grade Match existing
15'
Limit of Roadway Reconstruction accordance with Section 625.
except paved or rock surfaces. Establish turf in
Apply turf establishment on all disturbed areas, Note:
6" Aggregate Base, grading C or D
Geotextile, Class 2, Type E
Roadway excavation
Geotextile, Class 2, Type E (No pay) Saw cut
(No pay) Saw cut
(No pay) Saw cut
PG 64-22, Type IV pavement roughness) " NMSA, <0.3 Million ESAL,2
2" ACP, Type I (
PG 64-22, Type IV pavement roughness) " NMSA, <0.3 Million ESAL,2
2" ACP, Type I (
(place in two equal lifts with tack coat between lifts)
6" ACP, Type I (¾" NMSA, <0.3 Million ESAL, PG 64-22)
NO. DATE BY REVISIONS
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
SCHEDULE B
ENTRANCE ROAD
NO SCALE
:1 a r c h
B fh fl fi le s e rv e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v
\C A
D D
\B
-B
T
R E
M
(2
F W
S re v
T Y
P .d g n
STATE PROJECT
NUMBER
SHEET
WI FW-TREM 10(1) B03
SAMMS 2012218848
CHD03/07/2024 Changed kind of asphalt from Section 401 to Section 403.
(Route 901)
West Prairie Road Entrance Parking
Parking Area Width
EXISTING: PROPOSED:
44'
1V:3H
Match existing
ASPHALT CONCRETE PAVEMENT OVERLAY
WEST PRAIRIE ROAD ENTRANCE PARKING
1V:
3H
L C
(Route 100)
Marshland Road
PROPOSED:
Varies (32' max.)
MARSHLAND ROAD AND MARSHLAND TRAILHEAD PARKING
Profile grade
Existing ground
Existing ground
Tack coat
Profile grade
1V:4 H
1V:2H
4% 2% 4%
Travel Lane
10' with tack coat between lifts)
Type IV pavement roughness) (place in two equal lifts
4" ACP, Type I (½" NMSA, <0.3 Million ESAL, PG 64-22, grading C or D, 6" depth
Aggregate base, Aggregate surface course, 6" depth
EXISTING:
PG 64-22, Type IV pavement roughness)
2" ACP, Type I (½" NMSA, <0.3 Million ESAL, Geotextile, Class 2, Type E
Separation-stabilization
Geotextile, Class 2, Type E
Separation-stabilization
Shld.
2'
Shld.
2' accordance with Section 625.
except paved or rock surfaces. Establish turf in
Apply turf establishment on all disturbed areas, Note:
10'
Travel Lane
10'
4%
Marshland Trailhead Parking Area
Varies
Sidewalk Great River Trail
10'
1V:2H
2% 2%
LC
Trail grading C or D, 6" depth
Aggregate base, Concrete surface course, 6" depth
Aggregate surface course, 6" depth
NO. DATE BY REVISIONS
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION
NO SCALE
SCHEDULES B AND C
PARKING AREAS
:1 a r c h
B fh fl fi le s e rv e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v
\C A
D D
\B
-B
T
R E
M
(2
F W
S re v
T Y
P .d g n
STATE PROJECT
NUMBER
SHEET
WI FW-TREM 10(1) B07
SAMMS 2012218848
CHD03/07/2024 Changed kind of asphalt from Section 401 to Section 403.
NO. DATE BY REVISIONS
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION TREMPEALEAU NATIONAL WILDLIFE REFUGE
TABULATION OF QUANTITIES
SCHEDULES A AND B
SCHEDULE BSCHEDULE A
SAMMS 2012218848
STATE PROJECT
NUMBER
SHEET
WI FW-TREM 10(1) C01
CHD03/07/2024 Deleted pay item for ACP from Section 401.
03/07/2024 CHD Added pay item for ACP from Section 403.
:5 a r c h
C fh fl fi le s e rv e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v
\C A
D D
\C
-0
T R
E M
(1
F
W S re v
Q
T Y
.d g n
TABULATION OF QUANTITIES
SCHEDULE C
SCHEDULE C
1 03/07/2024 CHD Deleted pay item for ACP from Section 401.
03/07/2024
CHD
Added pay items for ACP from Section 403 and concrete sidewalk.
SAMMS 2012218848
STATE PROJECT
NUMBER
SHEET
WI FW-TREM 10(1) C02
:2 a r c h
C fh fl fi le s e rv e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v
\C A
D D
\C
-0
T R
E M
(1
F
W S re v
Q
T Y
.d g n
SUMMARIES AND SCHEDULES
SCHEDULES B AND C
MISCELLANEOUS SUMMARY - SCHEDULE B
MISCELLANEOUS SUMMARY - SCHEDULE B
MISCELLANEOUS SUMMARY - SCHEDULE C
SAMMS 2012218848
STATE PROJECT
NUMBER
SHEET
WI FW-TREM 10(1) C04
:3 a r c h
C fh fl fi le s e rv e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v
\C A
D D
\C
-0
T R
E M
(1
F
W S re v
Q
T Y
.d g n
Deleted pay item for ACP from Section 401, Schedule B.CHD03/07/20241
1 03/07/2024 CHD Added pay item for ACP from Section 403, Schedule B.
1 03/07/2024 CHD Added Miscellaneous Summary - Schedule C table.
1 03/07/2024 CHD Revised to Schedules B and C in the title block.
into triangular shape
1" X 3" stock cut
Wood Stakes
12" - 18"
Space fasteners at 12" centers
Double row of fasteners at erosion stop
Overlap edges by 3" at 50' intervals (up slope face)
6'' deep x 6'' wide transverse trenchlower blanket and anchor
Place upper blanket over
Overlap RECP ends 6"
RECP
RECP
See Section A-A
Erosion stop (check slot)
See Step 2
See Step 1
See Step 4
See Step 3
DETAIL A
TYPICAL GROUND FASTENERS
SECTION A-A
EROSION STOP (CHECK SLOT)
A
Backfill with soil and tamp
Fastener (typ.)
No. 11 gauge wire
Typical staples
Step 4:
Step 3:
Step 2:
Step 1:
the slopes as follows:
Install Rolled Erosion Control Product (RECP) along
INSTALLATION PROCEDURES:
A
SLOPE STABILIZATION WITH RECP
CONTROL PRODUCT (RECP)
WITH ROLLED EROSION
SLOPE STABILIZATION
E629-01
NO SCALE
See Detail A with ground fasteners
Stake at 36" to 60" intervals by the manufacturer.
Apply seed and fertilizer as recommended
See Detail A.
Secure RECP with wood or metal fasteners.
slope. Do not stretch RECP.
(in the direction of flow). Anchor at top of face Unroll and lay RECP out down slope ground. Do not track slope face.
prevent the RECP from laying flush with the rocks, trash, and other material which will
Grade, smooth, and compact slope. Remove
DETAIL APPROVED FOR USE
REVISED: SEPTEMBER 2020
APPROVED: MAY 2011
:0
A a r c h
S h e e t f h f l1 f il e s e r v e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
\P r o j_
D e v \C
A D
D \S td D e t\
S s t6 d e ta il .d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
STATE PROJECT
NUMBER
SHEET
WI FW TREM 10(1) S23
SAMMS 2012218848
EFLHD DETAIL
See Note 3
4'' Concrete
4'' Bedding material
NOTES:
1.
712.01(b)(1).
joint filler conforming to Subsection -inch preformed expansion 2
Install as shown in the plans.
Place contraction joints at intervals of 10 feet at intervals of not more than 20 feet.
-inch transverse expansion joints 4
Place
2.
3.
Variable slope e (var.)
Pavement structure
SIDEWALK
CONCRETE SIDEWALK
E615-01A
NO SCALE
pavement structure
Match e (var.) of
Width varies (5' to 23') 10'
(By others, not in contract)
Proposed Great River Trail
3" Limestone screenings
6'' Base aggregate Dense 3/4-inch
FW TREM 10(1)WI S14A
SAMMS 2012218848
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
:5 a r c h
S h e e t fh fl fi le s e rv e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S
F W
S \T
R E
M \1
(1
P ro j_
D e v \C
A D
D \S td -D e t\
S A
-s t6
A d e ta il .d g n
STATE PROJECT
NUMBER
SHEET
EFLHD DETAIL
Questions and Clarifications Page 1 of 4
Questions / Clarifications The following questions and issues were submitted to EFLHD, at EFLHD.Contracts@dot.gov. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included. The Government’s direct response to the sender may also have been updated below for better clarity.
1. Can you provide information on the load requirements for the piles? We need to know what sizes to order. Any more information you can add will help. Depths, loading, capacity requirements etc.
Response: Design of helical piles is the contractor’s responsibility and must be performed by a professional engineer proficient in the design of helical piles. Refer to Subsections 104.03 and 582.03(b) for additional information.
2. On Wisconsin DNR permit to dredge within a slough # IP-WC-2023-62-00943. Item # 13 states that all of the removed material must be placed in the location shown on applicant’s plan. Can this location be provided?
Response: Dredged material can be temporarily staged on paved surfaces such as parking areas as approved by the CO, but final disposal must occur per Subsection 203.05(a).
3. Can other material from the project be placed at this location?
Response: No. Other material will need to be handled, disposed of, or re-used per the applicable sections of the specifications.
4. For the bid items System Installation, Electrical Company Compensation: Will this item be used for reimbursement of all utility relocation and electrical work? Specifications state that the government has performed initial coordination with utility owners that have facilities located within project limits: Can a list of these utilities with contacts be provided?
Response: According to Section 645, it is the contractor’s responsibility to identify and locate utilities. For information only, the Government has coordinated with the following utility companies:
- Xcel Energy
- RIVERLAND ENERGY COOPERATIVE
- BRIGHTSPEED (formerly LUMEN)
- Tri-County Communication Coop., Inc., aka: WESTERN WI COMMUNICATIONS LLC
- Village of Trempealeau
- MIDWEST NATURAL GAS INC.
Questions and Clarifications Page 2 of 4
5. For bid item Helical Pile, In Place: testing requirements and frequency of test to be determined by designing engineer?
Response: Include testing requirements with the submittals required by Subsection 582.03.
Full scale compression load test is not required. The capacity of each helical pile shall be verified during installation using the capacity to torque load correlations. We recommend that a helical pile torque/anchor capacity relationship analysis be performed by the successful bidder prior to mobilization of the equipment to the site. The proposed torque motor(s) shall have adequate energy to efficiently install the piles to the specified capacities without inducing excessive stresses on the helical piles.
6. Are there any further construction details for the precast box culverts (pay item 60220-0000), including any desired wall thickness or rebar designs?
Response: Design of precast box culverts is the contractor’s responsibility and must be performed by a professional engineer proficient in the design of concrete box culverts and headwalls. Refer to Subsections 104.03 and 602.03 for additional information.
7. If this (the pre-cast box culvert) is to be contractor design build, what are the loading requirements for the structure?
Response: This structure length falls into the category of a bridge. HL-93 loading is required for live loading. Refer to Subsection 602.03 for additional information.
8. If this is a design/build scenario, what is the minimum low chord elevation of the deck of the culvert?
Response: The culverts are 20-foot span by 4-foot rise, and the required elevations for installation are provided on the K sheets.
9. Are the helical piling (pay item 58202-0000) to be installed under the headwalls as well of the culvert barrel? We are presuming the contractor will have to engineer the loads each helical will bear, and this information will be critical in helical design if the # of helicals is to stay constant at 20 per structure.
Response: Design of precast box culverts and helical piling is the contractor’s responsibility and must be performed by a professional engineer proficient in the design of concrete box culverts and headwalls, and helical piles. Refer to Subsections 104.03, 582.03(b), and Subsection 602.03 for additional information.
10. In the drainage profile sections (Schedule A) the way the culverts are drawn do not show any methodology for connecting the helical piling to the culvert. How is that to be done with a pre-cast unit? Are grout pockets anticipated?
Response: Design of precast box culverts and helical piling is the contractor’s responsibility and must be performed by a professional engineer proficient in the design of concrete box culverts and headwalls, and helical piles. Refer to Subsections 104.03, 582.03(b), and Subsection 602.03 for additional information.
11. Would the client accept a cast in place abutment option with a pre-cast deck panel in lieu of a fully precast box culvert?
Response: Submit a bid based on the advertisement documents. After award the contractor may submit a Value Engineering (VE) proposal for review and possible approval by the Government. See Subsection 103.03 for VE requirements.
Questions and Clarifications Page 3 of 4
12. Schedule C construction plan #D08 states to install concrete sidewalk. It states to see detail E615-01A which does not appear to be in the plan set. There is not a quantity given or a bid item for this. Can more information be provided for this item?
Response: An amendment will be issued to provide Detail E615-01A and add a pay item and quantity for the sidewalk.
13. It is not explicitly clear in the plans what the underground electrical relocation work will entail and what level of effort or amount of support will be required to perform this work as it relates to utility locates, biological monitoring support, erosion control, on-site supervision, etc… We are also unable to determine to what extent we can execute work on the remaining portions of the contract while utility work is on-going or have an idea of the length of time it will take to perform the utility work.
Can more details be provided of what the underground electrical relocation will entail and the approximate locations of the new location?
Response: There are no details for the underground electrical relocation on Entrance Road.
The approximate location of the new electrical service on Marshland Road is shown on sheet D08 of the plans. No other information is available.
As stated in Subsection 636.11A, the utility owners are responsible for the design and construction of work on their facilities. The utility owners are also responsible for the on-site supervision of their own forces. The contractor is responsible for coordinating the utility work with the owners. This includes establishing work schedules with the utility owners and ensuring there are no conflicts between the new or relocated utilities and the roadway work.
The contractor may work on other portions of the project that do not affect, and are not affected by, the utility relocation activities.
The contractor is responsible for conducting the required biological monitoring for all construction activities on the project. The contractor is also responsible for ensuring the appropriate erosion and sediment control measures are implemented for all disturbed areas as required by permits obtained for the project. This includes work performed by utility companies in conjunction with this project.
14. The SCR’s make mention of testing regarding the asphalt control strip, and we wanted to make sure that a control strip will be required considering the small amount of asphalt being placed.
Response: A control strip is not required. An amendment will be issued to revise the asphalt concrete pavement from Section 401 to Section 403.
15. We were unable to locate any details or typical drawings related to the wingwalls or headwalls and the associated rebar for those structures. Can typical drawings or details be provided for these items?
Response: Design of precast box culverts and the cast-in-place elements of box culverts is the contractor’s responsibility and must be performed by a professional engineer proficient in the design of concrete box culverts and headwalls. Refer to Subsections 104.03 and 602.03 for additional information.
Questions and Clarifications Page 4 of 4
16. We are trying to determine where the 12,000# of rebar and 100 CY of concrete are going- the wingwalls on the culverts are only about 1 CY each, and the sign base does not have nearly that much concrete either. The rebar only adds up to several hundred, not 12,000 lbs. Any guidance in these areas would be appreciated.
Response: Pay Item 55201-0200 (Line Item A1180) and Pay Item 55401-1000 (Line Item A1190) are estimated quantities for the headwalls, wingwalls, and footings for Pay Item 60220-0000 (Line Item A1210). The concrete for the sign base in Schedule B is included in Pay Item 63301-0000 (Line Item B2230).