Results of Bid Opening - TN ERFO FS 2019-1(3).pdf
PDF 90 KB Posted
- Attached to
- Cherokee National Forest
- Solicitation number
- 693C73-22-B-000010
About this file
This document summarizes a bid opening for a federal construction contract. The bid opening was held on June 14, 2022 by the Eastern Federal Lands Highway Division for Project TN ERFO FS 2019-1(3) located in Cocke and Greene Counties, Tennessee. The project scope involves repairing damaged sites on three forest roads, including constructing rock-filled gabion walls, mechanically stabilized earth walls, road resurfacing, and drainage improvements. Nine contractors submitted bids ranging from $2,636,542.50 to $4,899,333.94 for Schedule A work. The lowest bidder was King General Contractors, Inc. at $2,636,542.50, and the engineer's estimate was $2,507,000. The performance period for Schedule A work is 250 calendar days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Geotechnical Report.pdf | ||
| ADV_Bidders Qualifications Form.doc | DOC document | |
| FP14_Eng.pdf | ||
| IFB Solicitiation - TN ERFO FS 2019-1(3).pdf | ||
| Categorical Exclusion Form (NEPA).pdf | ||
| VETS-4212 - Form - 2021.pdf | ||
| Plans - TN ERFO FS 2019-1(3).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Cherokee National Forest
PROJECT: TN ERFO FS 2019-1(3)
SOLICITATION NO. 693C73-22-B-000010
June 14, 2022 at 2:00 p.m. EST
Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-22-B-000010
Project: TN ERFO FS 2019-1(3)
June 14, 2022, 2:00 p.m. EST
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Aspen Construction Company SCHEDULE A
$4,899,333.94
SCHEDULE A =
$4,899,333.94
Bryant’s Land and
Development Industries, Inc.
SCHEDULE A
$3,429,745.50
SCHEDULE A =
$3,429,745.50
Construction Solutions Group, LLC
SCHEDULE A
$4,293,543.50
SCHEDULE A =
$4,293,543.50
The performance period for the completion of Schedule A is 250 calendar days.
BID OPENING for SOLICITATION NO. 693C73-22-B-000010
Project: TN ERFO FS 2019-1(3)
June 14, 2022, 2:00 p.m. EST
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Estes Bros. Const., Inc. SCHEDULE A
$2,912,620.62
SCHEDULE A =
$2,912,620.62
King General Contractors, Inc. SCHEDULE A
$2,636,542.50
SCHEDULE A =
$2,636,542.50
Kovilic Construction Company, Inc.
SCHEDULE A
$3,425,350.00
SCHEDULE A =
$3,425,350.00
BID OPENING for SOLICITATION NO. 693C73-22-B-000010
Project: TN ERFO FS 2019-1(3)
June 14, 2022, 2:00 p.m. EST
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Mass Crushing and Excavating, Inc.
SCHEDULE A
$3,403,250.00
SCHEDULE A =
$3,403,250.00
V. Pavkov Contracting Co., Inc. SCHEDULE A
$2,809,360.00
SCHEDULE A =
$2,809,360.00
ENGINEER’S ESTIMATE SCHEDULE A
$2,507,000.00
SCHEDULE A =
$2,507,000.00