The RFP Proposal Package (both Technical and Price proposals) due date is changed to March 12, 2019, by 2:00 p.m. EST.

View the file

Other files

File Type Posted
Amendment_0002_-_NP-BLRI_PVT_PRES_FY18.pdf PDF
RFP_Solicitation_-_NP-BLRI_PVT_PRES_FY18.pdf PDF
Plans_-_NP-BLRI_PVT_PRES_FY18.pdf PDF
VETS-4212_-_Form_-_2018.pdf PDF
FP14_Eng.pdf PDF
Subcontracting_Plan.doc DOC document
ADV_Offeror's_Qualifications_Form.doc DOC document
NEPA_CE.pdf PDF
Synopsis_-_NP-BLRI_PVT_PRES_FY18.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7319R000004 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-CO

21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.

Federal Highway Administration

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

SEE BLOCK 1403/05/20190001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/05/2019

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

NP BLRI PVT PRES FY18 - Blue Ridge Parkway Pavement Preservation

The purpose of this Amendment is to:

1) Replace the B-Pages to add a pavement marking removal pay item.

2) Revise the Special Contract Requirements (J Pages) as follows:

a) Section 203 to add remove pavement markings prior to placing pavement preservation treatment according to Subsection 420.04

b) Section 420 to add removal of pavement markings will be evaluated under Section 203.

c) Section 420 to add measure the Removal of pavement markings according to Section 203.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 28

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

693C7319R000004/0001

d) Section 420 to add removal of pavement markings will be paid according to Section 203.

3) Revise the Plans to replace Sheets B01, C01, C02, C03, C04, C12 and C13.

4) Provide a response to the question asked by a potential bidder.

5) The RFP Proposal Package (both Technical and

Price proposals) due date is changed to March 12, 2019, by 2:00 p.m. EST.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Amendment No. 0001

Amendment Info Page 1 out of 2

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Project NP BLRI PVT PRES FY18

Blue Ridge Parkway Solicitation: 693C73-19-R-000004

The purpose of this Amendment is to:

1) Replace the B-Pages to add a pavement marking removal pay item.

2) Revise the Special Contract Requirements (J Pages) as follows:

a) Section 203 to add remove pavement markings prior to placing pavement preservation treatment according to Subsection 420.04

b) Section 420 to add removal of pavement markings will be evaluated under Section 203.

c) Section 420 to add measure the Removal of pavement markings according to Section 203.

d) Section 420 to add removal of pavement markings will be paid according to Section 203.

3) Revise the Plans to replace Sheets B01, C01, C02, C03, C04, C12 and C13.

4) Provide a response to the question asked by a potential bidder.

5) The RFP Proposal Package (both Technical and Price proposals) due date is changed to March 12, 2019, by 2:00 p.m. EST.

B-Pages changes

Delete the Solicitation Bid Schedule pages B-1 through B-17, and substitute the amended Bid Schedule pages B-1 through B-17.

Special Contract Requirement changes

1. Add the following to Subsection 203.04 of the Special Contract Requirements, page J-10:

Remove pavement markings prior to placing pavement preservation treatment according to Subsection 420.04

2. Add the following to Subsection 420.06 of the Special Contract Requirements, page J-51:

Removal of pavement markings will be evaluated under Section 203.

Amendment Info Page 2 out of 2

3. Add the following to Subsection 420.07 of the Special Contract Requirements, page J-51:

Measure the removal of pavement markings according to Subsection 203.04.

4. Add the following to Subsection 420.08 of the Special Contract Requirements, page J-51:

Removal of pavement markings will be paid according to Section 203.

Plan Sheet changes Delete Plan Sheets B01, C01, C02, C03, C04, C12 and C13, and substitute the amended Plan Sheets B01, C01, C02, C03, C04, C12 and C13.

1) Sheet B01, (Note 8 added).

2) Sheet C01, (New pay item added).

3) Sheet C02, (New pay item added).

4) Sheet C03, (New pay item added).

5) Sheet C04, (New pay item added).

6) Sheet C12, (New pay item added).

7) Sheet C13, (New pay item added).

Response to Bidder Question:

Question: On page J-51 section 420.05 in the SCRs, is says "Remove existing pavement markings by sandblasting, micromilling, or other methods, that will not damage the surface or texture of the pavement..." There is no bid item for removal of pavement markings. Is it the intent to remove all pavement markings for the entire project? And is the removal of pavement markings required for all three types of pavement pres, Type I, Type II, and Type III?

Response: Amendment 0001 clarifies the intent of pavement marking removal. A pay item for pavement marking removal has been added. The RFP Proposal Package (both Technical and Price proposals) due date is changed to March 12, 2019, at 2:00 p.m.

B - 1

Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount

A0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

A0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

A0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

380 LNFT $____________ $____________

A0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

36,780 LNFT $____________ $____________

A0050 42001-0000 PAVEMENT PRESERVATION TREATMENT

236,500 SQYD $____________ $____________

A0060 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

174,200 LNFT $____________ $____________

A0070 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

9,700 LNFT $____________ $____________

A0080 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

A0090 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

A0100 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

A0110 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

A0120 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

145,100 LNFT $____________ $____________

A0130 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

610 SQFT $____________ $____________

A0140 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

2,640 HOUR $____________ $____________

Bid Schedule Schedule:A Schedule Type:Base

Project No:NP BLRI PVT PRES FY 18

Project Name:Pavement Preservation work at Blue Ridge Parkway for FY 18

B - 2

A0150 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

800 HOUR $____________ $____________

A0160 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:A Schedule Type:Base

Project No:NP BLRI PVT PRES FY 18

B - 3

B0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

B0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

B0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

250 LNFT $____________ $____________

B0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

21,500 LNFT $____________ $____________

B0050 42001-0000 PAVEMENT PRESERVATION TREATMENT

138,520 SQYD $____________ $____________

B0060 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

101,800 LNFT $____________ $____________

B0070 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

5,700 LNFT $____________ $____________

B0080 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

B0090 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

B0100 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

B0110 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

B0120 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

84,770 LNFT $____________ $____________

B0130 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

550 SQFT $____________ $____________

B0140 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

1,640 HOUR $____________ $____________

Bid Schedule Schedule:B Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 4

B0150 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

480 HOUR $____________ $____________

B0160 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:B Schedule Type:Options

B - 5

C0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

C0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

C0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

230 LNFT $____________ $____________

C0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

23,580 LNFT $____________ $____________

C0050 42001-0000 PAVEMENT PRESERVATION TREATMENT

151,600 SQYD $____________ $____________

C0060 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

111,700 LNFT $____________ $____________

C0070 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

6,200 LNFT $____________ $____________

C0080 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

C0090 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

C0100 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

C0110 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

C0120 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

93,000 LNFT $____________ $____________

C0130 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

550 SQFT $____________ $____________

C0140 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

1,690 HOUR $____________ $____________

Bid Schedule Schedule:C Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 6

C0150 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

530 HOUR $____________ $____________

C0160 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:C Schedule Type:Options

B - 7

D0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

D0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

D0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

340 LNFT $____________ $____________

D0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

29,500 LNFT $____________ $____________

D0050 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

741 SQYD $____________ $____________

D0060 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2

893 SQYD $____________ $____________

D0070 42001-0000 PAVEMENT PRESERVATION TREATMENT

190,000 SQYD $____________ $____________

D0080 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

139,700 LNFT $____________ $____________

D0090 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

7,800 LNFT $____________ $____________

D0100 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

D0110 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

D0120 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

D0130 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

D0140 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

116,400 LNFT $____________ $____________

Bid Schedule Schedule:D Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 8

D0150 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

580 SQFT $____________ $____________

D0160 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

1,900 HOUR $____________ $____________

D0170 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

770 HOUR $____________ $____________

D0180 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:D Schedule Type:Options

B - 9

E0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

E0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

E0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

170 LNFT $____________ $____________

E0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

16,240 LNFT $____________ $____________

E0050 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

697 SQYD $____________ $____________

E0060 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2

2,337 SQYD $____________ $____________

E0070 42001-0000 PAVEMENT PRESERVATION TREATMENT

104,500 SQYD $____________ $____________

E0080 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

76,900 LNFT $____________ $____________

E0090 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

4,300 LNFT $____________ $____________

E0100 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

E0110 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

E0120 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

E0130 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

E0140 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

64,000 LNFT $____________ $____________

Bid Schedule Schedule:E Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 10

E0150 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

530 SQFT $____________ $____________

E0160 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

1,320 HOUR $____________ $____________

E0170 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

560 HOUR $____________ $____________

E0180 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:E Schedule Type:Options

B - 11

F0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

F0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

F0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

320 LNFT $____________ $____________

F0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

31,260 LNFT $____________ $____________

F0050 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

70 SQYD $____________ $____________

F0060 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2

22 SQYD $____________ $____________

F0070 41801-3000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3

95 SQYD $____________ $____________

F0080 42001-0000 PAVEMENT PRESERVATION TREATMENT

200,900 SQYD $____________ $____________

F0090 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

148,000 LNFT $____________ $____________

F0100 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

8,300 LNFT $____________ $____________

F0110 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

F0120 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

F0130 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

F0140 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

Bid Schedule Schedule:F Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 12

F0150 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

123,300 LNFT $____________ $____________

F0160 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

590 SQFT $____________ $____________

F0170 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

2,640 HOUR $____________ $____________

F0180 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

720 HOUR $____________ $____________

F0190 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:F Schedule Type:Options

B - 13

G0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

G0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

G0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

290 LNFT $____________ $____________

G0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

31,260 LNFT $____________ $____________

G0050 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

70 SQYD $____________ $____________

G0060 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2

22 SQYD $____________ $____________

G0070 41801-3000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3

95 SQYD $____________ $____________

G0080 42001-0000 PAVEMENT PRESERVATION TREATMENT

201,220 SQYD $____________ $____________

G0090 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

148,000 LNFT $____________ $____________

G0100 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

8,300 LNFT $____________ $____________

G0110 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

G0120 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

G0130 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

G0140 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

Bid Schedule Schedule:G Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 14

G0150 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

123,300 LNFT $____________ $____________

G0160 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

590 SQFT $____________ $____________

G0170 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

2,850 HOUR $____________ $____________

G0180 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

720 HOUR $____________ $____________

G0190 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:G Schedule Type:Options

B - 15

H0010 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

H0020 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

H0030 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

340 LNFT $____________ $____________

H0040 20302-2600 REMOVAL OF PAVEMENT MARKINGS

31,240 LNFT $____________ $____________

H0050 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

70 SQYD $____________ $____________

H0060 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2

22 SQYD $____________ $____________

H0070 41801-3000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3

95 SQYD $____________ $____________

H0080 42001-0000 PAVEMENT PRESERVATION TREATMENT

200,900 SQYD $____________ $____________

H0090 63401-0500 PAVEMENT MARKINGS, TYPE C, SOLID

147,900 LNFT $____________ $____________

H0100 63401-0600 PAVEMENT MARKINGS, TYPE C, BROKEN

8,300 LNFT $____________ $____________

H0110 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

H0120 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

H0130 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

H0140 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

100 LNFT $____________ $____________

Bid Schedule Schedule:H Schedule Type:Options

Project No:NP BLRI PVT PRES FY 18

B - 16

H0150 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

123,200 LNFT $____________ $____________

H0160 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

570 SQFT $____________ $____________

H0170 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

3,070 HOUR $____________ $____________

H0180 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

720 HOUR $____________ $____________

H0190 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:H Schedule Type:Options

B - 17

I0001 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

I0003 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

I0005 41402-2000 CRACKS, CLEANING AND SEALING

100.0 MILE $____________ $____________

I0007 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

270 EACH $____________ $____________

I0009 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

50 EACH $____________ $____________

I0011 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

2 EACH $____________ $____________

I0013 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

1,060 SQFT $____________ $____________

I0015 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

9,080 HOUR $____________ $____________

I0017 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

930 HOUR $____________ $____________

I0019 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:I Schedule Type:Options

Amendment 1 Info.pdf
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0001
Project NP BLRI PVT PRES FY18
Blue Ridge Parkway
Solicitation: 693C73-19-R-000004