Results_of_Bid_Opening_(ROBO)_-_FW-OCBA_T302(1).pdf

PDF 108 KB Posted

Attached to
Occoquan Bay National Wildlife Refuge - FW-OCBA T302(1)
Solicitation number
693C73-19-B-000034
Issued by

About this file

Results of Bid Opening (ROBO)

View the file

Other files

File Type Posted
Amendment_0001_-_FW-OCBA_T302(1).pdf PDF
ADV_Bidder's_Qualifications_Form.doc DOC document
VETS-4212_-_Form_-_2018.pdf PDF
IFB_Solicitation_-_FW-OCBA_T302(1).pdf PDF
FP14_Eng.pdf PDF
NEPA_CE.pdf PDF
Hydraulic_Memo.pdf PDF
Plans_-_FW-OCBA_T302(1).pdf PDF
Synopsis_-_FW-OCBA_T302(1).doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening for

Occoquan Bay National Wildlife Refuge

PROJECT: FW-OCBA T302(1)

SOLICITATION NO. 693C73-19-B-000034

August 15, 2019 at 2:00 p.m.

Sterling, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-19-B-000034 Project: FW-OCBA T302(1) August 15, 2019, 2:00 p.m. local time

BIDDER’S BID TOTALS TOTAL PRICE

Aspens Construction Company SCHEDULE A

$329,870.00

SCHEDULE B (OPTION 1)

$110,000.00

SCHEDULE C (OPTION 2)

$114,200.00

SCHEDULE D (OPTION 3)

$109,800.00

SCHEDULE E (OPTION 4)

$138,130.00

SCHEDULES A THRU E

$802,000.00

Kovilic Construction Co, Inc SCHEDULE A

$531,950.00

SCHEDULE B (OPTION 1)

$332,850.00

SCHEDULE C (OPTION 2)

$312,875.00

SCHEDULE D (OPTION 3)

$316,650.00

SCHEDULE E (OPTION 4)

$422,000.00

SCHEDULES A THRU E

$1,916,325.00

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all contract work will be 185 calendar days.

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-19-B-000034 Project: FW-OCBA T302(1) August 15, 2019, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all contract work will be 185 calendar days.

BIDDER’S BID TOTALS TOTAL PRICE

Eclipse Co. SCHEDULE A

$713,050.10

SCHEDULE B (OPTION 1)

$570,957.50

SCHEDULE C (OPTION 2)

$567,745.00

SCHEDULE D (OPTION 3)

$570,245.00

SCHEDULE E (OPTION 4)

$660,220.00

SCHEDULES A THRU E

$3,082,217.60

Engineer’s Estimate SCHEDULE A

$195,000.00

SCHEDULE B (OPTION 1)

$115,000.00

SCHEDULE C (OPTION 2)

$115,000.00

SCHEDULE D (OPTION 3)

$115,000.00

SCHEDULE E (OPTION 4)

$135,000.00

SCHEDULES A THRU E

$675,000.00

Slide Number 1
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-19-B-000034 Project: FW-OCBA T302(1)�August 15, 2019, 2:00 p.m. local time �
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION� BID OPENING for SOLICITATION NO. 693C73-19-B-000034 Project: FW-OCBA T302(1)�August 15, 2019, 2:00 p.m. local time �If the Government awards the contract as Schedules A + B + C + D + E, the performance period to�complete all contract work will be 185 calendar days.