Amendment No. 0002 The Bid Opening date will remain May 30, 2019 at 2:00 PM EST.

View the file

Other files for this federal contract opportunity

Other files attached to Arkansas - Buffalo National River Project, newest first.
File Type Posted
Results_of_Bid_Opening_-_AR_ERFO_BUFF_2015-1(2).pdf PDF
AR_ERFO_BUFF_2015-1(2)_FONSI_Amendment_0002.pdf PDF
693C7319B000019_Amendment_0001.pdf PDF
Geotechnical_Recommendations_Memo_Final.pdf PDF
ADV_Bidder's_Qualifications_Form.doc DOC document
NEPA_FONSI.pdf PDF
Load_Rating_Form.pdf PDF
NEPA_EA.pdf PDF
Plans_adv.pdf PDF
IFB_Solicitation_AR_ERFO_BUFF_2015-1(2).pdf PDF
VETS-4212_-_Form_-_2018.pdf PDF
SWPPP.pdf PDF
Synopsis.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7319B000019 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-CO

21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.

Federal Highway Administration

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

See Block 1004/26/20190002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/26/2019

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project: AR ERFO BUFF 2015-1(2)

The purpose of this Amendment is to:

1. Replace the Environmental Assessment (EA) and Finding of No Significant Impacts (FONSI) for Lost Valley Road and Parking Relocation with the FONSI for Erbie Road Improvements.

2. Provide responses and clarify contractors questions.

2. The Bid Opening date of May 30, 2019 at 2:00 P.M. EST will remain the same.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0002

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Project AR ERFO BUFF 2015-1(2)

Buffalo National River Solicitation: 693C73-19-B-000019

The purpose of this Amendment is to:

1) Replace the Environmental Assessment (EA) and Finding of No Significant Impacts (FONSI) for Lost Valley Road and Parking Relocation with the FONSI for Erbie Road Improvements.

2) Provide responses and clarify contractors’ questions.

The Bid Opening date of May 30, 2019, at 2:00 P.M. EST will remain the same.

Response to Bidder Question:

Question: With the clearing being restricted to October 16 to March 31 and a contract completion within 260 consecutive calendar days, it appears that the proposed box culvert and low water crossing would have to be constructed in a time period with a much greater risk of substantial rainfall and severe flooding. How will contract time be assessed if weather does not allow work to continue?

Response: See Subsection 155.04A on page J-6 for how weather delays are handled. See FAR clause 52.249-10(b) for delays related to flooding.

Question: Are there any specific stream protection requirements beyond the stage designs shown that effect means and methods for construction of drainage features? (i.e.

downstream turbidity curtains).

Response: The erosion and sediment control plans provide a general concept for how the work at the Cove Creek crossing might be staged, and the locations and lengths of the temporary diversions shown in the plans are only approximate. The Contractor is responsible for developing temporary diversion and stream protection plans in compliance with all permit requirements, as well as Sections 157 and 650.

Question: Will the contractor be required to apply water for dust control and provide maintenance of gravel and dirt county roads used during the hauling of materials and equipment to the project site?

Response: The Contractor must comply with all county regulations and restrictions when hauling on county roads, including maintenance and watering for dust control. See also FP-14 Section 158.

Question: Will the ditch reconditioning only be done where directed by the contracting officer? What are the expectations for the shape and appearance of ditches at the end of the project?

Response: Yes, the ditch reconditioning will only be done where directed by the Contracting Officer. The planned ditch cross section for reconditioning is shown on the Typical Sections, sheets B01 and B02. The general requirements for shaping and finishing ditches are provided in the FP-14, Subsections 204.12 and 204.13.

Question: Will any clearing of limbs over the top of the proposed roadway improvements be required or allowed?

Response: The Contractor may cut tree limbs over the road only where necessary to safely transport or operate equipment. Clearing of limbs over the top of roadway improvements is allowed from October 16 through March 31 with prior approval of the

CO.

Question: In reference to the Sub-excavation, minimum 36” depth as shown in the Typical Sections on Sheet B01, is the Unclassified Borrow used to backfill the Sub- Excavation paid for under the Unclassified Borrow pay item per cubic yard or is it considered incidental to the Sub-Excavation line item?

Response: The Unclassified Borrow will be used to backfill the Sub-Excavation, as shown in the Typical Sections, and will be paid for by the cubic yard under the Unclassified Borrow pay item.

Amendment 0002 - 693C7319B000019
Amendment 0002 info
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0002
Project AR ERFO BUFF 2015-1(2)
Solicitation: 693C73-19-B-000019

File details come from the government source that posted it.