Results_of_Bid_Opening_-_WI_ERFO_FS_2016-1(2).pdf
PDF 102 KB Posted
- Attached to
- Chequamegon-Nicolet National Forest
- Solicitation number
- 693C73-19-B-000003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Report_Geotech.pdf | ||
| IFB_Solicitation_-_WI_ERFO_FS_2016-1(2).pdf | ||
| Plans_-_WI_ERFO_FS_2016-1(2).pdf | ||
| Report_Hydraulics.pdf | ||
| ROW_TCE.pdf | ||
| NEPA_(Categorical_Exclusion_Form).pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| VETS-4212_Form.pdf | ||
| FP14_Eng.pdf | ||
| CNNF_ERFO_Closure_Order.pdf | ||
| ADV_Subcontracting_plan.doc | DOC document | |
| Synopsis_-_WI_ERFO_FS_2016-1(2).doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
Chequamegon-Nicolet National Forest
PROJECT: WI ERFO FS 2016-1(2)
SOLICITATION NO. 693C73-19-B-000003
February 7, 2019 at 2:00 p.m.
Sterling, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-19-B-000003
PROJECT NUMBER: WI ERFO FS 2016-1(2)
February 7, 2019, 2:00 p.m. local time
BIDDER BID TOTAL DAYS TOTAL PRICE
Construction Solutions Group, LLC
Schedule A $1,870,512.00
Schedule A $1,870,512.00
Kovilic Construction Co., Inc. Schedule A $2,074,295.00
Schedule A $2,074,295.00
M. Jolma, Inc. Schedule A $1,128,022.50
Schedule A $1,128,022.50
Engineer’s Estimate Schedule A $1,530,000.00
Schedule A $1,530,000.00
Construction activities at the project site must be completed by no later than September 23, 2019.