6913G626SN1002 Poland Ave MARAD Warehouse Fire Water Main Repair SOW.pdf
PDF 475 KB Posted
- Solicitation number
- 6913G626SN1002
About this file
This is a Statement of Work (SOW) for repair of a leaking fire water main distribution system at the DOT/MARAD Warehouse at Poland Avenue in New Orleans, Louisiana.
The project involves conducting targeted excavations to identify and repair failed sections of an 8-inch diameter buried fire water pipe located approximately 5 to 10 feet below grade. The contractor must provide all labor, materials, equipment, and supervision across three contract line items (CLINs): CLIN 00100 (Preparation and Excavation), CLIN 00200 (Pipe Repair for Known Leaking Locations), and OPTION CLIN 00300 (Additional Pipe Repairs). Work includes site preparation and mobilization, utility location and marking, excavation with hand tools or soft digging methods within 18-24 inches of marked utilities, shoring for excavations exceeding 5 feet, dewatering if needed, removal and replacement of broken pipe sections with NFPA 24-compliant materials, hydrostatic testing at 200 psi or 50 psi above working pressure (whichever is greater) for at least 2 hours, and restoration of landscaping and site conditions. All pipe repair operations must be performed by appropriately licensed pipefitters or plumbers under supervision of a licensed master plumber, and the contractor must be licensed through the Louisiana State Licensing Board for Contractors. The project must comply with International Fire Code 2021 and NFPA standards 13 and 24. DOT has already obtained construction permits from the Port of New Orleans, U.S. Army Corps of Engineers, local flood authority/levee board, and City of New Orleans. The performance period for CLINs 00100 and 00200 extends from contract award through October 30, 2026, with OPTION CLIN 00300 scheduled through March 31, 2027 if exercised (funded as a not-to-exceed CLIN at $50,000).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR V3252046
Section C - Statement of Work
C.1 Introduction The DOT/MARAD Warehouse at Poland Avenue (the Facility) has confirmed leaks in the fire water main distribution pipe, indicating failure of a section(s) of pipe buried below grade. These leaks compromise the water supply to the Facility’s automatic sprinkler systems and adjacent fire hydrants, creating significant risk to life safety and property. Until the leaks are repaired, there is no water available within or adjacent to the warehouse to suppress fires.
Figure 1 below displays the original site plan showing the fire water system, with the approximate section of buried pipe highlighted in yellow, and the general areas with the identified leaks circled in green. This segment connects to the city’s 8” main on the left (upriver) side of the drawing below and has two connections originating from a separate parcel of property across the street, further downriver. This property is undergoing redevelopment that resulted in water shutoffs, rendering the MARAD facility reliant on a potential single point of connection to the city’s main water pipeline, “upstream” from the active leaks.
Figure 1: Water System Original Diagram circa 1960 (source: U.S. Army, drawing provided by the Port of New Orleans)
Previous exploration into resolving the leaks included site visits to identify the locations of the active leaks, and a subsequent site visit identified that there may be insufficient clearance beneath the wharf deck for excavating equipment or specialized equipment.
Once repaired, restoring water pressure to the system may provide adequate water pressure at the hydrants serving the warehouse, or reveal additional system deficiencies. Resolving the known leaks will inform understanding of the condition of the remaining water distribution system and provide motivation for subsequent spot repair(s) or more comprehensive system replacement.
The highlighted section of the fire main is approximately 5 to 10-feet below grade, below the embankment adjacent to the wharf where it connects (still below grade) to vertical riser sections supplying water to areas above the wharf deck including adjacent fire hydrants and the warehouse’s sprinkler system.
The objective of this SOW is to conduct targeted excavation(s) of the leaking area(s) to identify failed sections of pipe and perform repairs/replacement of failed sections of pipe. Excavations shall be typical for pipe repair of 6- to 10-inch diameter buried water pipes with depth and width of trench(es) minimized to the maximum extent practicable, while providing clearance for hand tools and repair actions. See image below for example of anticipated dimensions or clearances:
Figure 2: Typical trench dimensions for water pipe excavation.
Excavations shall ensure sufficient clearance from footings or other structural support elements associated with areas near the wharf structure.
This project is not intended to facilitate wholesale replacement of the water distribution piping.
Once active leaks are identified and repaired, pressure measurements and other testing procedures can inform hydraulic calculations, to guide future efforts to repair or replace the fire water distribution system and fire suppression sprinkler system.
Repaired sections of pipe shall tie into the existing distribution piping, restore water supply to the external fire hydrants adjacent to the warehouse, and restore water supply to the fire suppression sprinkler system in the warehouse.
C.2 Requirements The Contractor shall provide all labor, materials, equipment, and supervision to perform the following tasks:
C.2.1 CLIN 00100 – Preparation and Excavation C.2.1.1 Project Preparation and Mobilization o Permitting: DOT obtained the construction permits from the Port of New Orleans, US Army Corps of Engineers (USACE), local flood authority / levee board, and City of New Orleans. The contractor is required to follow all requirements and restrictions of these permits.
o Mobilization: Move required labor, materials, equipment, and tools to the site.
o Site Safety and Security: Establish a physical safety and security barrier around the work areas to prevent against accidents and unauthorized access. Due to a legacy of unauthorized access to areas beneath the wharf, Contractor equipment and materials are recommended to be secured or removed at the end of each workday. A laydown area will be provided within the warehouse Facility.
o Follow local regulations to identify and mark underground utilities, to prevent damage during excavation. Notify Louisiana 811 two to five business days before digging. Mark work areas with paint, flags, or stakes as appropriate.
o Inspect the site area as needed. Coordinate with the City of New Orleans Sewerage and Water Board to manipulate water valves to facilitate locating the leaks.
o Prior to excavation, ensure the City of New Orleans Sewer and Water Board has closed all necessary valves to turn off water flow to the affected area.
o Provide support for adjacent structures or utilities that may be affected by the work.
C.2.1.2 Excavation o Excavation: Trench or dig to expose the broken pipe, ensure safety standards are met and preserved (e.g., Occupational Safety and Health Administration – OSHA requirements).
Ensure excavation is clear of restricted areas and performed in accordance with applicable USACE guidance.
Only hand tools or soft digging methods may be used within 18-24 inches of marked utility lines.
o Shoring: Shoring is required for excavation greater than 5-feet in depth.
o Dewatering: Remove groundwater from the excavated area using submersible pumps, if needed.
C.2.2 CLIN 00200 – Pipe Repair for Known Leaking Locations C.2.2.1 Pipe Repair and Replacement o Remove the broken pipe, valves, or fittings.
o Install new pipe sections, fittings, and couplings.
Use approved piping materials compliant with NFPA 24.
Existing drawings indicate 8” diameter pipe.
Repair sleeves are permitted (mechanical or stainless steel) for localized breaks.
o If needed, install or repair existing concrete thrust blocks as required at bends and T-fittings for underground pipe stability.
C.2.2.2 Testing and Commissioning o Hydrostatically test the repaired system at 200 psi or 50 psi more than the system working pressure, whichever is greater, per NFPA 24. Maintain pressure at gauge pressure of ±5 psi for at least 2-hours to ensure integrity.
o Coordinate with City of New Orleans Sewer and Water Board to reopen valves to restore water supply from city water main and verify system performance.
o Check for leaks at joints and connections.
o Perform visual inspection of the site to identify any additional obvious fire main leaks.
o Open the hydrants located on the wharf proximate to the Facility to ensure water is flowing to the affected hydrants and pressure is restored.
o Flush the system to remove contaminants per NFPA 24.
C.2.2.3 Final Site Work and Closeout o Remove shoring elements, backfill the trench and compact soil to original grade.
o Restore landscaping, paving, concrete, aggregate, etc. that was removed. Ensure disturbed areas and grounds are restored to original condition.
o Remove all tools, equipment, and debris from the site.
o Provide as-built drawings and completed test reports, ensuring compliance with NFPA standards.
C.2.3 OPTION CLIN 00300 – Additional Pipe Repairs CLIN 00200 requires the Contractor to perform visual inspection of the site to identify any additional obvious fire main leaks outside of the original scope of work, after completion of the contracted repairs and restoration of fire main water. DOT also anticipates independently performing additional leak detection investigations after fire main water is restored, utilizing ground penetrating radar, acoustic leak detection, and/or other technologies.
For OPTION CLIN 00300, the Contractor shall provide all labor, materials, equipment, and supervision to perform the following tasks:
C.2.3.1 Repairs o For the additional leaks located under CLIN 00200 or identified by the DOT through other leak detection technologies, the Contractor shall excavate the additional areas with fire main leaks, repair the pipe sections, test and commission the fire main as required by CLIN 00100 and CLIN 00200 above.
If OPTION CLIN 00300 is exercised, this CLIN will be fully funded as a Not-to-Exceed CLIN. The Contractor shall perform additional leak excavation and repairs up to $50,000. Any unallocated costs will be descoped from the contract at contract closeout.
Note that repair of any additional leaks will first require the DOT to modify the construction permits from the Port of New Orleans, US Army Corps of Engineers (USACE), local flood authority / levee board, and City of New Orleans prior to commencing any additional construction activities.
C.3 General Requirements C.3.1 Coordination of Activities: Coordinate work activities with the following stakeholders:
o Volpe Center: Scott Lian: (617) 494-2811, scott.lian@dot.gov; Daniel Mannheim: (857) 331-3545, daniel.mannheim@dot.gov; and Gretchen Reese: (617) 494-3193, gretchen.reese@dot.gov o Maritime Administration: Darrell Butler: (504) 940-1003, Darrell1.Butler@dot.gov o Port of New Orleans: Kyle Gilmore, Dir. of Real Estate: (504) 373-3577 (cell), kyle.gilmore@portnola.com; and James Soileau, Permit Manager: (225) 317-3300 (cell), james.soileau@portnola.com o Private Developer of Adjacent Parcel: Brian Gibbs, EMDRC, LLC., (504) 908-8871, paamodt1@gmail.com o Sewerage and Water Board of New Orleans (SWBNO):
Only contact SWBNO for fire main valve operation. SWBNO Plumbing
Department, 625 Saint Joseph Street Room 133, New Orleans, LA 70165. 504- 585-2124, https://www.swbno.org/About/ContactUs o New Orleans Levee District Coordination facilitated by Port of New Orleans o U.S. Army Corps of Engineers, New Orleans District (NOD) Coordination facilitated by Port of New Orleans & Levee Board
C.3.2 DOT obtained construction permits from the Port of New Orleans, US Army Corps of Engineers (USACE), local flood authority / levee board, and City of New Orleans. The contractor is required to follow all requirements and restrictions of these permits.
C.3.3 Minimize Excavation Requirements: Due to heavy restrictions on excavating within the levee wall, the contractor shall minimize digging to the maximum extent possible.
mailto:scott.lian@dot.gov mailto:daniel.mannheim@dot.gov mailto:gretchen.reese@dot.gov mailto:kyle.gilmore@portnola.com mailto:james.soileau@portnola.com mailto:paamodt1@gmail.com https://www.swbno.org/About/ContactUs
C.3.4 Site Constraints: Conduct all work without excavation in restricted zones. Any required access pits or digging must be located outside exclusion zone(s) and be restored to original conditions upon completion.
C.3.5 Material Standards: The new pipe and fittings must be NFPA compliant, listed by a Nationally Recognized Testing Laboratory (NRTL) for fire service application, and be compatible with existing distribution mains.
C.3.6 Connection and Integration: Properly transition and connect the new or repaired section(s) to the existing fire main infrastructure. Any new valves must open by counter-clockwise rotation and be provided with permanent identification tags.
C.4 Applicable Standards The project must conform to the following International Code Council and National Fire Protection Association (NFPA) standards:
o International Fire Code, 2021, as adopted and amended by the City of New Orleans o NFPA 13 (Standard for the Installation of Sprinkler Systems) o NFPA 24 (Standard for the Installation of Private Fire Service Mains and Their
Appurtenances)
C.5 Personnel Qualifications o Pipe repair operations must be performed by appropriately licensed pipefitters/ plumbers and performed under supervision of a licensed master plumber.
o Contractor(s) must be licensed through the Louisiana State Licensing Board for
Contractors.
C.6 Submittals and Quality Control o Provide copies of licenses and certificates of insurance prior to commencing work.
o Provide final as-built drawings and completed test reports, ensuring compliance with
NFPA standards.
C.7 Government Furnished Information o Permit Number OL2026-00124 obtained by DOT for the repairs in this SOW o Historical Site Plans and Water Supply Drawings (unverified) o GPRS Utility Findings Maps (dated June 25, 2026)
C.8 Period of Performance The period of performance of CLIN 00100 and CLIN 00200 shall be from date of award through October 30, 2026.
The period of performance of OPTION CLIN 00300 is from date of option exercise through March 31, 2027.
| Section C - Statement of Work |
| C.1 Introduction |
| C.2 Requirements |
| C.2.1 CLIN 00100 – Preparation and Excavation |
| C.2.1.1 Project Preparation and Mobilization |
| C.2.1.2 Excavation |
| C.2.2 CLIN 00200 – Pipe Repair for Known Leaking Locations |
| C.2.2.1 Pipe Repair and Replacement |
| C.2.2.2 Testing and Commissioning |
| C.2.2.3 Final Site Work and Closeout |
| C.2.3 OPTION CLIN 00300 – Additional Pipe Repairs |
| C.2.3.1 Repairs |
| C.3 General Requirements |
| C.4 Applicable Standards |
| C.5 Personnel Qualifications |
| C.6 Submittals and Quality Control |
| C.7 Government Furnished Information |
| C.8 Period of Performance |