This is a Pricing Schedule for RFQ No. 6913G626Q300047 issued for Advanced Acoustic Model Development and demonstration of a conceptual tool to predict sonic boom footprints over a range of meteorological conditions. The contract is structured as a firm fixed price award with four Contract Line Item Numbers (CLINs) containing multiple tasks and subtasks with defined deliverables and due dates.
CLIN 00100 requires monthly progress reports due by the 15th of each month through contract completion, with a quantity of 12 reports. CLIN 00200 encompasses code maintenance and support activities due by 01-31-27, including code updates and bug fixes (Task 2.A), source code review with written or verbal explanations (Task 2.B), software repository and test case updates (Task 2.C), and monthly one-on-one coding sessions (Task 2.D). CLIN 00300 requires AAM user base technical support including test cases, due by 5-14-27. CLIN 00400 involves calculating sonic boom impacts and demonstrating a conceptual sonic boom impact tool, with multiple subtasks: a kick-off meeting within 2 weeks of Notice to Proceed (NTP); atmospheric data and sonic boom impact contours within 3 months of NTP (Task 4.A); a presentation or virtual/in-person meeting within 5 months of NTP (Task 4.B); results for two scenarios within 5 months of NTP (Task 4.B); and a memo documenting tool requirements within 6 months of NTP (Task 4.C). The pricing schedule provides columns for unit cost, quantity, and total cost, with a final line for the total firm fixed price to be completed by the contractor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ No. 6913G626Q300047
Advanced Acoustic Model Development and : Demonstrate Conceptual Tool to Predict Sonic Boom Footprints over a Range of Meteorological Conditions
Pricing Schedule
CLIN TASK DESCRIPTION DELIVERABLE
DUE
DATE
UNIT
COST
QTY COST
00100 1.0 Monthly Reporting
Monthly Progress Report
15th of Each Month through completion
00200
2.A Code Updates / Bug Fixes / Maintenance
Code Updates
01-31-27
2.B Source Code Review
Verbal or written explanation of issues
2.C
Software Repository and Test Case Updates
Code and Test Case Updates
2.D One-on-one Coding Sessions
Monthly Meetings
00300 3 AAM User Base Technical Support
Technical Support, Test Cases
5-14-27
00400
4A Calculate Sonic Boom Impacts
Kick-off meeting
Within 2 weeks of notice to proceed
(NTP)
4.A Calculate Sonic Boom Impacts
Atmospheric Data, Sonic Boom Impact Contours
Within 3 months of
NTP
4.B Demonstrate a Conceptual Sonic Boom Impact Tool
Presentation, Virtual or In-person Meeting
Within 5 months of
NTP
4.B Demonstrate a Conceptual Sonic Boom Impact Tool
Results for Two Scenarios
Within 5 months of
NTP
RFQ No. 6913G626Q300047
CLIN TASK DESCRIPTION DELIVERABLE
DUE
DATE
UNIT
COST
QTY COST
4.C Demonstrate a Conceptual Sonic Boom Impact Tool
Memo Documenting Tool Requirements
Within 6 months of
NTP
TOTAL FIRM FIXED PRICE