PROJECT DESCRIPTION_OR FLAP UMATILL 582(1).pdf
PDF 165 KB Posted
- Attached to
- OR FLAP UMATILL 582(1), Mill Creek Road
- Solicitation number
- 69056724B000019
About this file
This document is a project description for the OR FLAP UMATILL 582(1) road improvement project on Mill Creek Road in Umatilla County, Oregon. The project consists of chip seal, crushed aggregate, grading, repair of soldier pile walls with anchored wire mesh, signing, traffic control, and erosion control over a 2.91-mile stretch. The project has an estimated price range of $2 million to $5 million and a tentative completion date of Fall 2025. Two bid schedules will be solicited, but only one will be awarded. The work includes mobilization, surveying, quality control, erosion control, earthwork, aggregate base, chip seal, timber structures, drainage, traffic control, and installation of an anchored wire mesh system for the soldier pile walls. This is a readvertisement of a previously canceled solicitation. The project will be procured through a sealed bid, firm-fixed-price contract under full and open competition.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR FLAP UMATILL 582(1), Mill Creek Road
Umatilla County, Oregon
The work consists of chip seal, crushed aggregate, grading, repair of soldier pile walls with anchored wire mesh, signing, traffic control, erosion control, and other small items of work. There are 2 bid schedules, only 1 will be awarded.
Project length: 2.91 miles
Estimated Price Range: $2 million to $5 million
Location: 13 miles SW of Walla Walla, WA
Tentative Fixed Completion Date: Fall 2025
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
S ch ed u le
A
S ch ed
B
DIVISION 150 – Project Requirements
151 Mobilization (yes/no) Yes Yes
152 Construction Survey & Staking (yes/no) Yes Yes
153 Contractor Quality Control and Assurance (yes/no) Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes
157 Soil Erosion & Sediment Control (erosion control devices) Mulching Hydraulic Method 5 ACRE 5.5 ACRE
157 Soil Erosion & Sediment Control (erosion control devices) Silt Fence, non-reinforced 2,920 LNFT 3,450 LNFT
157 Soil Erosion & Sediment Control (erosion control devices) Silt Fence, reinforced N/A 700 LNFT
157 Soil Erosion & Sediment Control (erosion control devices) Wattle 6,270 LNFT 6,400 LNFT
157 Soil Erosion & Sediment Control (erosion control devices) Check Dam, temp. 10 EACH 11 EACH
157 Soil Erosion & Sediment Control (erosion control devices) Inlet Protection 19 EACH 20 EACH
158 Watering for Dust Control 250 MGAL 320 MGAL ed
S ch ed
DIVISION 200 – Earthwork
201 Clearing & Grubbing
5 ACRE 5.3 ACRE
202 Additional Clearing & Grubbing (clearing & grubbing) Individual tree removal 8 EACH 8 EACH
203 Removal of Structures & Obstructions (structures, demolition) Delineator N/A 18 EACH
204 Roadway Excavation 550 CUYD 580 CUYD
204 Unclassified Borrow 60 CUYD 80 CUYD
207 Earthwork Geosynthetics 170 SQYD 175 SQYD
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap N/A 2 CUYD
DIVISION 300 – Aggregate and Base Courses
301 Aggregate Base Grading D 8,400 TON 9,000 TON
301 Aggregate Base Grading D, Temporary N/A 150 TON
303 Road Reconditioning, 6-inch depth 33,700
SQYD
36,000
SQYD
DIVISION 400 – Asphalt Pavements & Surface Treatments
407 Chip Seal, Type 2B, double course 33,800
SQYD
37,100
SQYD
411 Asphalt Prime Coat (asphalt surface treatment)
33,800
SQYD
37,100
SQYD
DIVISION 550 – Bridge Construction
557 Timber Structures (structures, timber) TREATED (WALLS 1-9) N/A Yes
DIVISION 600 – Incidental Construction
604 Manholes Adjustment, air vacuum valve 1 EACH 1 EACH
604 Manholes Adjustment 9 EACH 9 EACH
605 Underdrain System, Temporary N/A 1,200 LNFT
611 Adjust Valve Box 3 EACH 3 EACH
611 Adjust Valve Box, Test Station 18 EACH 18 EACH
622 Rental Equipment (yes/no) Yes Yes
623 General Labor (yes/no) No No
625 Turf Establishment 5 ACRE 5.5 ACRE
625 Seeding, Hydraulic Method 5 ACRE 5.5 ACRE
633 Delineator Type 1 N/A 18 EACH ed
S ch ed
635 Temporary Traffic Control – Barricade Type 3 N/A 5 EACH
635 Temporary Traffic Control – Tubular marker, Type 28-inch 61 EACH 150 EACH
635 Temporary Traffic Control – Warning Light Type D N/A 2 EACH
635 Temporary Traffic Control – Portable Changeable Message Sign 2 EACH 2 EACH
635 Temporary Traffic Control – Construction Sign 230 SQFT 450 SQFT
635 Temporary Traffic Control – Flagger 1,300 HOUR 2,250 HOUR
635 Temporary Traffic Control – Pilot Car 550 HOUR 550 HOUR
635 Temporary Traffic Control – Traffic Control Supervisor 76 DAY 95 DAY
655 Anchored Wired Mesh System, Wall 1 N/A 100 SQYD
655 Anchored Wired Mesh System, Wall 2 N/A 30 SQYD
655 Anchored Wired Mesh System, Wall 3 N/A 30 SQYD
655 Anchored Wired Mesh System, Wall 4 N/A 63 SQYD
655 Anchored Wired Mesh System, Wall 5 N/A 15 SQYD
655 Anchored Wired Mesh System, Wall 6 N/A 112 SQYD
655 Anchored Wired Mesh System, Wall 7 N/A 20 SQYD
655 Anchored Wired Mesh System, Wall 8 N/A 53 SQYD
655 Anchored Wired Mesh System, Wall 9 N/A 100 SQYD
655 Additional Anchor Nail, Walls 1-8 N/A 30 EACH
655 Additional Anchor Nail, Walls 9 N/A 10 EACH