This document is a Tabulation of Bids for a federal highway construction project involving Road 22 Repairs in the Ochoco National Forest, located in Crook County, Oregon. The solicitation (No. 69056724B000003) covers road repairs from mile post 0.0 to 8.0, with three separate bid schedules (A, B, and C) and multiple line items including mobilization, excavation, pavement work, traffic control, and signage.
Five contractors submitted bids: JAL Construction, Marcum & Son LLC, Moreno and Nelson Construction Corp, Construction Solutions Group, and Stimpel Webelhaus Associates. Bid totals varied significantly across schedules, with JAL Construction consistently offering the lowest bids: Schedule A at $518,577, Schedule B at $588,037, and Schedule C at $720,072, compared to the highest bidder Stimpel Webelhaus Associates at $1,351,853, $1,447,288, and $1,814,588 respectively. The project was opened on 05/13/25 in Vancouver, WA, by Marino Chea, with the Engineer's Estimate ranging from $1,149,445 to $1,623,445 across the three schedules.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 05/14/25
1 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Contractor Responsive?
Engineer's Estimate
Construction Solutions Group, LLC
JAL CONSTRUCTION, INC.
Marcum & Son LLC
Moreno and Nelson Construction Corp
Stimpel Webelhaus Associates, INC
Alternate Schedule A
$1,149,445.00
$1,031,398.80
$518,577.00
$529,505.60
$850,560.45
$1,351,853.00
Alternate Schedule B
$1,324,445.00
$1,164,244.80
$588,037.00
$615,915.60
$943,418.65
$1,447,288.00
Alternate Schedule C
$1,623,445.00
$1,408,708.80
$720,072.00
$748,175.60
$1,059,215.40
$1,814,588.00
2 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Solcitation No: 69056724B000003
Division: Western Federal Lands
State: OR County: Crook
Federal Land: Ochoco National Forest Opened at: Vancouver, WA
Opened by: Marino Chea
Date: 05/13/25
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
JAL CONSTRUCTION, INC. $518,577.00
PO Box 6269 Bend, OR 97708
Marcum & Son LLC $529,505.60 336 SW Black Butte Blvd Redmond, OR 97756
Moreno and Nelson Construction Corp $850,560.45
665 STINSEN AVE
Walla Walla, WA 99362
Construction Solutions Group, LLC $1,031,398.80 425 Highland Ave St. Louis, MO 63122
Stimpel Webelhaus Associates, INC $1,351,853.00
PO BOX 492335
Redding, CA 96049
Engineer's Estimate $1,149,445.00
3 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
JAL CONSTRUCTION, INC. Lump Sum $50,000.00 Marcum & Son LLC Lump Sum $28,500.00 Moreno and Nelson Construction Corp Lump Sum $17,450.00 Construction Solutions Group, LLC Lump Sum $393,600.00 Stimpel Webelhaus Associates, INC Lump Sum $200,000.00 Engineer's Estimate ALL LPSM Lump Sum $113,268.40
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
JAL CONSTRUCTION, INC. Lump Sum $15,000.00 Marcum & Son LLC Lump Sum $10,000.00 Moreno and Nelson Construction Corp Lump Sum $19,900.00 Construction Solutions Group, LLC Lump Sum $18,000.00 Stimpel Webelhaus Associates, INC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $28,000.00
A0060 15301-0000 CONTRACTOR QUALITY CONTROL
JAL CONSTRUCTION, INC. Lump Sum $10,000.00 Marcum & Son LLC Lump Sum $7,000.00 Moreno and Nelson Construction Corp Lump Sum $17,180.00 Construction Solutions Group, LLC Lump Sum $110,000.00 Stimpel Webelhaus Associates, INC Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $28,000.00
A0080 15401-0000 CONTRACTOR TESTING
JAL CONSTRUCTION, INC. Lump Sum $15,000.00 Marcum & Son LLC Lump Sum $10,000.00 Moreno and Nelson Construction Corp Lump Sum $19,900.00 Construction Solutions Group, LLC Lump Sum $19,000.00 Stimpel Webelhaus Associates, INC Lump Sum $12,500.00 Engineer's Estimate ALL LPSM Lump Sum $19,000.00
A0100 15501-0000 CONSTRUCTION SCHEDULE
JAL CONSTRUCTION, INC. Lump Sum $1,500.00 Marcum & Son LLC Lump Sum $5,500.00 Moreno and Nelson Construction Corp Lump Sum $2,320.00 Construction Solutions Group, LLC Lump Sum $29,000.00 Stimpel Webelhaus Associates, INC Lump Sum $2,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
4 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE
JAL CONSTRUCTION, INC. $5.00 $3,300.00
Marcum & Son LLC $6.00 $3,960.00 Moreno and Nelson Construction Corp $2.25 $1,485.00 Construction Solutions Group, LLC $5.40 $3,564.00 Stimpel Webelhaus Associates, INC $12.00 $7,920.00 Engineer's Estimate 660 LNFT $20.00 $13,200.00
A0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
JAL CONSTRUCTION, INC. $6.00 $480.00
Marcum & Son LLC $8.00 $640.00 Moreno and Nelson Construction Corp $3.75 $300.00 Construction Solutions Group, LLC $4.20 $336.00 Stimpel Webelhaus Associates, INC $10.00 $800.00 Engineer's Estimate 80 LNFT $9.25 $740.00
A0160 20101-0000 CLEARING AND GRUBBING
JAL CONSTRUCTION, INC. $15,000.00 $4,500.00
Marcum & Son LLC $8,500.00 $2,550.00 Moreno and Nelson Construction Corp $64,090.00 $19,227.00 Construction Solutions Group, LLC $18,000.00 $5,400.00 Stimpel Webelhaus Associates, INC $50,000.00 $15,000.00 Engineer's Estimate 0.30 ACRE $50,000.00 $15,000.00
A0180 20301-2400 REMOVAL OF SIGN
JAL CONSTRUCTION, INC. $250.00 $500.00
Marcum & Son LLC $250.00 $500.00 Moreno and Nelson Construction Corp $560.00 $1,120.00 Construction Solutions Group, LLC $300.00 $600.00 Stimpel Webelhaus Associates, INC $260.00 $520.00 Engineer's Estimate 2 EACH $280.00 $560.00
A0200 20303-1600 REMOVAL OF PAVEMENT, ASPHALT (8-INCH DEPTH)
JAL CONSTRUCTION, INC. $5.00 $16,500.00
Marcum & Son LLC $10.85 $35,805.00 Moreno and Nelson Construction Corp $46.00 $151,800.00 Construction Solutions Group, LLC $3.60 $11,880.00 Stimpel Webelhaus Associates, INC $22.00 $72,600.00 Engineer's Estimate 3,300 SQYD $34.00 $112,200.00
5 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 20401-0000 ROADWAY EXCAVATION
JAL CONSTRUCTION, INC. $110.00 $2,750.00
Marcum & Son LLC $97.00 $2,425.00 Moreno and Nelson Construction Corp $330.00 $8,250.00 Construction Solutions Group, LLC $48.00 $1,200.00 Stimpel Webelhaus Associates, INC $810.00 $20,250.00 Engineer's Estimate 25 CUYD $230.00 $5,750.00
A0240 20402-0000 SUBEXCAVATION
JAL CONSTRUCTION, INC. $70.00 $7,000.00
Marcum & Son LLC $97.00 $9,700.00 Moreno and Nelson Construction Corp $199.00 $19,900.00 Construction Solutions Group, LLC $60.00 $6,000.00 Stimpel Webelhaus Associates, INC $190.00 $19,000.00 Engineer's Estimate 100 CUYD $130.00 $13,000.00
A0260 20435-1000 BACKFILL, SELECT GRANULAR
JAL CONSTRUCTION, INC. $135.00 $13,500.00
Marcum & Son LLC $132.00 $13,200.00 Moreno and Nelson Construction Corp $158.00 $15,800.00 Construction Solutions Group, LLC $78.00 $7,800.00 Stimpel Webelhaus Associates, INC $430.00 $43,000.00 Engineer's Estimate 100 CUYD $220.00 $22,000.00
A0280 20701-0400 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE D (WOVEN)
JAL CONSTRUCTION, INC. $5.00 $27,500.00
Marcum & Son LLC $2.75 $15,125.00 Moreno and Nelson Construction Corp $5.00 $27,500.00 Construction Solutions Group, LLC $1.80 $9,900.00 Stimpel Webelhaus Associates, INC $17.00 $93,500.00 Engineer's Estimate 5,500 SQYD $7.50 $41,250.00
A0300 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
JAL CONSTRUCTION, INC. $135.00 $60,750.00
Marcum & Son LLC $193.00 $86,850.00 Moreno and Nelson Construction Corp $220.00 $99,000.00 Construction Solutions Group, LLC $90.00 $40,500.00 Stimpel Webelhaus Associates, INC $260.00 $117,000.00 Engineer's Estimate 450 CUYD $300.00 $135,000.00
6 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0320 30201-2000 ROADWAY AGGREGATE, METHOD 2
JAL CONSTRUCTION, INC. $125.00 $43,750.00
Marcum & Son LLC $127.00 $44,450.00 Moreno and Nelson Construction Corp $160.00 $56,000.00 Construction Solutions Group, LLC $68.40 $23,940.00 Stimpel Webelhaus Associates, INC $435.00 $152,250.00 Engineer's Estimate 350 CUYD $130.00 $45,500.00
A0340 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
JAL CONSTRUCTION, INC. $120.00 $114,000.00
Marcum & Son LLC $155.00 $147,250.00 Moreno and Nelson Construction Corp $210.00 $199,500.00 Construction Solutions Group, LLC $192.00 $182,400.00 Stimpel Webelhaus Associates, INC $322.00 $305,900.00 Engineer's Estimate 950 TON $320.00 $304,000.00
A0360 41201-0000 TACK COAT
JAL CONSTRUCTION, INC. $600.00 $1,200.00
Marcum & Son LLC $850.00 $1,700.00 Moreno and Nelson Construction Corp $1,720.00 $3,440.00 Construction Solutions Group, LLC $1,560.00 $3,120.00 Stimpel Webelhaus Associates, INC $2,000.00 $4,000.00 Engineer's Estimate 2.00 TON $1,500.00 $3,000.00
A0380 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $125.00 $1,250.00 Moreno and Nelson Construction Corp $250.00 $2,500.00 Construction Solutions Group, LLC $138.00 $1,380.00 Stimpel Webelhaus Associates, INC $230.00 $2,300.00 Engineer's Estimate 10 HOUR $190.00 $1,900.00
A0400 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $150.00 $1,500.00 Moreno and Nelson Construction Corp $260.00 $2,600.00 Construction Solutions Group, LLC $102.00 $1,020.00 Stimpel Webelhaus Associates, INC $165.00 $1,650.00 Engineer's Estimate 10 HOUR $250.00 $2,500.00
7 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $190.00 $1,900.00 Moreno and Nelson Construction Corp $380.00 $3,800.00 Construction Solutions Group, LLC $102.00 $1,020.00 Stimpel Webelhaus Associates, INC $235.00 $2,350.00 Engineer's Estimate 10 HOUR $240.00 $2,400.00
A0440 62301-0000 GENERAL LABOR
JAL CONSTRUCTION, INC. $100.00 $1,000.00
Marcum & Son LLC $105.00 $1,050.00 Moreno and Nelson Construction Corp $154.00 $1,540.00 Construction Solutions Group, LLC $73.56 $735.60 Stimpel Webelhaus Associates, INC $90.00 $900.00 Engineer's Estimate 10 HOUR $110.00 $1,100.00
A0460 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
JAL CONSTRUCTION, INC. $25.00 $1,125.00
Marcum & Son LLC $45.00 $2,025.00 Moreno and Nelson Construction Corp $14.00 $630.00 Construction Solutions Group, LLC $120.00 $5,400.00 Stimpel Webelhaus Associates, INC $225.00 $10,125.00 Engineer's Estimate 45 SQYD $75.00 $3,375.00
A0480 62502-0000 TURF ESTABLISHMENT
JAL CONSTRUCTION, INC. $80.00 $3,600.00
Marcum & Son LLC $8.00 $360.00 Moreno and Nelson Construction Corp $4.25 $191.25 Construction Solutions Group, LLC $48.00 $2,160.00 Stimpel Webelhaus Associates, INC $225.00 $10,125.00 Engineer's Estimate 45 SQYD $85.00 $3,825.00
A0500 63302-0000 SIGN SYSTEM
JAL CONSTRUCTION, INC. $115.00 $24,610.00
Marcum & Son LLC $103.00 $22,042.00 Moreno and Nelson Construction Corp $143.00 $30,602.00 Construction Solutions Group, LLC $123.60 $26,450.40 Stimpel Webelhaus Associates, INC $225.00 $48,150.00 Engineer's Estimate 214 SQFT $250.00 $53,500.00
8 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 63308-3000 OBJECT MARKER, TYPE 3
JAL CONSTRUCTION, INC. $450.00 $900.00
Marcum & Son LLC $450.00 $900.00 Moreno and Nelson Construction Corp $270.00 $540.00 Construction Solutions Group, LLC $108.00 $216.00 Stimpel Webelhaus Associates, INC $600.00 $1,200.00 Engineer's Estimate 2 EACH $490.00 $980.00
A0540 63309-0200 DELINEATOR, TYPE 2 (WHITE)
JAL CONSTRUCTION, INC. $100.00 $6,900.00
Marcum & Son LLC $90.00 $6,210.00 Moreno and Nelson Construction Corp $270.00 $18,630.00 Construction Solutions Group, LLC $108.00 $7,452.00 Stimpel Webelhaus Associates, INC $240.00 $16,560.00 Engineer's Estimate 69 EACH $100.00 $6,900.00
A0560 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)
JAL CONSTRUCTION, INC. $0.35 $57,008.00
Marcum & Son LLC $0.25 $40,720.00 Moreno and Nelson Construction Corp $0.17 $27,689.60 Construction Solutions Group, LLC $0.30 $48,864.00 Stimpel Webelhaus Associates, INC $0.15 $24,432.00 Engineer's Estimate 162,880 LNFT $0.24 $39,091.20
A0580 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN (YELLOW)
JAL CONSTRUCTION, INC. $0.30 $3,714.00
Marcum & Son LLC $0.22 $2,723.60 Moreno and Nelson Construction Corp $0.27 $3,342.60 Construction Solutions Group, LLC $0.26 $3,218.80 Stimpel Webelhaus Associates, INC $0.20 $2,476.00 Engineer's Estimate 12,380 LNFT $0.18 $2,228.40
A0600 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
JAL CONSTRUCTION, INC. $125.00 $750.00
Marcum & Son LLC $185.00 $1,110.00 Moreno and Nelson Construction Corp $280.00 $1,680.00 Construction Solutions Group, LLC $240.00 $1,440.00 Stimpel Webelhaus Associates, INC $275.00 $1,650.00 Engineer's Estimate 6 EACH $220.00 $1,320.00
9 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0620 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
JAL CONSTRUCTION, INC. $30.00 $690.00
Marcum & Son LLC $20.00 $460.00 Moreno and Nelson Construction Corp $21.00 $483.00 Construction Solutions Group, LLC $42.00 $966.00 Stimpel Webelhaus Associates, INC $65.00 $1,495.00 Engineer's Estimate 23 EACH $29.00 $667.00
A0640 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
JAL CONSTRUCTION, INC. $2,500.00 $5,000.00
Marcum & Son LLC $2,500.00 $5,000.00 Moreno and Nelson Construction Corp $1,830.00 $3,660.00 Construction Solutions Group, LLC $2,880.00 $5,760.00 Stimpel Webelhaus Associates, INC $3,750.00 $7,500.00 Engineer's Estimate 2 EACH $11,000.00 $22,000.00
A0660 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
JAL CONSTRUCTION, INC. $40.00 $9,800.00
Marcum & Son LLC $40.00 $9,800.00 Moreno and Nelson Construction Corp $36.00 $8,820.00 Construction Solutions Group, LLC $48.00 $11,760.00 Stimpel Webelhaus Associates, INC $220.00 $53,900.00 Engineer's Estimate 245 SQFT $62.00 $15,190.00
A0680 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
JAL CONSTRUCTION, INC. $100.00 $1,000.00
Marcum & Son LLC $85.00 $850.00 Moreno and Nelson Construction Corp $143.00 $1,430.00 Construction Solutions Group, LLC $87.60 $876.00 Stimpel Webelhaus Associates, INC $130.00 $1,300.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00
A0700 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
JAL CONSTRUCTION, INC. $250.00 $10,750.00
Marcum & Son LLC $150.00 $6,450.00 Moreno and Nelson Construction Corp $1,450.00 $62,350.00 Construction Solutions Group, LLC $1,080.00 $46,440.00 Stimpel Webelhaus Associates, INC $1,500.00 $64,500.00 Engineer's Estimate 43 DAY $2,000.00 $86,000.00
10 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: A
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Total Schedule - All Items
JAL CONSTRUCTION, INC. $518,577.00
Marcum & Son LLC $529,505.60 Moreno and Nelson Construction Corp $850,560.45 Construction Solutions Group, LLC $1,031,398.80 Stimpel Webelhaus Associates, INC $1,351,853.00 Engineer's Estimate $1,149,445.00
11 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Solcitation No: 69056724B000003
Division: Western Federal Lands
State: OR County: Crook
Federal Land: Ochoco National Forest Opened at: Vancouver, WA
Opened by: Marino Chea
Date: 05/13/25
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
JAL CONSTRUCTION, INC. $588,037.00
PO Box 6269 Bend, OR 97708
Marcum & Son LLC $615,915.60 336 SW Black Butte Blvd Redmond, OR 97756
Moreno and Nelson Construction Corp $943,418.65
665 STINSEN AVE
Walla Walla, WA 99362
Construction Solutions Group, LLC $1,164,244.80 425 Highland Ave St. Louis, MO 63122
Stimpel Webelhaus Associates, INC $1,447,288.00
PO BOX 492335
Engineer's Estimate $1,324,445.00
12 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0020 15101-0000 MOBILIZATION
JAL CONSTRUCTION, INC. Lump Sum $60,000.00 Marcum & Son LLC Lump Sum $30,000.00 Moreno and Nelson Construction Corp Lump Sum $16,180.00 Construction Solutions Group, LLC Lump Sum $393,600.00 Stimpel Webelhaus Associates, INC Lump Sum $200,000.00 Engineer's Estimate ALL LPSM Lump Sum $130,080.90
B0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
JAL CONSTRUCTION, INC. Lump Sum $15,000.00 Marcum & Son LLC Lump Sum $12,000.00 Moreno and Nelson Construction Corp Lump Sum $19,580.00 Construction Solutions Group, LLC Lump Sum $18,000.00 Stimpel Webelhaus Associates, INC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $33,000.00
B0060 15301-0000 CONTRACTOR QUALITY CONTROL
JAL CONSTRUCTION, INC. Lump Sum $10,000.00 Marcum & Son LLC Lump Sum $10,000.00 Moreno and Nelson Construction Corp Lump Sum $17,000.00 Construction Solutions Group, LLC Lump Sum $110,000.00 Stimpel Webelhaus Associates, INC Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $33,000.00
B0080 15401-0000 CONTRACTOR TESTING
JAL CONSTRUCTION, INC. Lump Sum $15,000.00 Marcum & Son LLC Lump Sum $12,000.00 Moreno and Nelson Construction Corp Lump Sum $19,580.00 Construction Solutions Group, LLC Lump Sum $19,000.00 Stimpel Webelhaus Associates, INC Lump Sum $12,500.00 Engineer's Estimate ALL LPSM Lump Sum $22,000.00
B0100 15501-0000 CONSTRUCTION SCHEDULE
JAL CONSTRUCTION, INC. Lump Sum $1,500.00 Marcum & Son LLC Lump Sum $5,500.00 Moreno and Nelson Construction Corp Lump Sum $2,290.00 Construction Solutions Group, LLC Lump Sum $29,000.00
Engineer's Estimate ALL LPSM Lump Sum $5,000.00
13 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE
JAL CONSTRUCTION, INC. $5.00 $3,300.00
Marcum & Son LLC $6.00 $3,960.00 Moreno and Nelson Construction Corp $2.00 $1,320.00 Construction Solutions Group, LLC $5.40 $3,564.00 Stimpel Webelhaus Associates, INC $12.00 $7,920.00 Engineer's Estimate 660 LNFT $20.00 $13,200.00
B0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
JAL CONSTRUCTION, INC. $6.00 $480.00
Marcum & Son LLC $8.00 $640.00 Moreno and Nelson Construction Corp $3.75 $300.00 Construction Solutions Group, LLC $4.20 $336.00 Stimpel Webelhaus Associates, INC $10.00 $800.00 Engineer's Estimate 80 LNFT $9.25 $740.00
B0160 20101-0000 CLEARING AND GRUBBING
JAL CONSTRUCTION, INC. $15,000.00 $4,500.00
Marcum & Son LLC $8,500.00 $2,550.00 Moreno and Nelson Construction Corp $63,410.00 $19,023.00 Construction Solutions Group, LLC $18,000.00 $5,400.00 Stimpel Webelhaus Associates, INC $50,000.00 $15,000.00 Engineer's Estimate 0.30 ACRE $50,000.00 $15,000.00
B0180 20301-2400 REMOVAL OF SIGN
JAL CONSTRUCTION, INC. $250.00 $500.00
Marcum & Son LLC $250.00 $500.00 Moreno and Nelson Construction Corp $550.00 $1,100.00 Construction Solutions Group, LLC $300.00 $600.00 Stimpel Webelhaus Associates, INC $260.00 $520.00 Engineer's Estimate 2 EACH $280.00 $560.00
B0200 20303-1600 REMOVAL OF PAVEMENT, ASPHALT (8-INCH DEPTH)
JAL CONSTRUCTION, INC. $5.00 $16,500.00
Marcum & Son LLC $10.85 $35,805.00 Moreno and Nelson Construction Corp $45.00 $148,500.00 Construction Solutions Group, LLC $3.60 $11,880.00
14 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0220 20401-0000 ROADWAY EXCAVATION
JAL CONSTRUCTION, INC. $110.00 $2,750.00
Marcum & Son LLC $97.00 $2,425.00 Moreno and Nelson Construction Corp $330.00 $8,250.00 Construction Solutions Group, LLC $48.00 $1,200.00 Stimpel Webelhaus Associates, INC $810.00 $20,250.00 Engineer's Estimate 25 CUYD $230.00 $5,750.00
B0240 20402-0000 SUBEXCAVATION
JAL CONSTRUCTION, INC. $70.00 $7,000.00
Marcum & Son LLC $97.00 $9,700.00 Moreno and Nelson Construction Corp $196.00 $19,600.00 Construction Solutions Group, LLC $60.00 $6,000.00 Stimpel Webelhaus Associates, INC $190.00 $19,000.00 Engineer's Estimate 100 CUYD $130.00 $13,000.00
B0260 20435-1000 BACKFILL, SELECT GRANULAR
JAL CONSTRUCTION, INC. $135.00 $13,500.00
Marcum & Son LLC $132.00 $13,200.00 Moreno and Nelson Construction Corp $157.00 $15,700.00 Construction Solutions Group, LLC $78.00 $7,800.00 Stimpel Webelhaus Associates, INC $430.00 $43,000.00 Engineer's Estimate 100 CUYD $220.00 $22,000.00
B0280 20701-0400 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE D (WOVEN)
JAL CONSTRUCTION, INC. $5.00 $27,500.00
Marcum & Son LLC $2.75 $15,125.00 Moreno and Nelson Construction Corp $4.75 $26,125.00 Construction Solutions Group, LLC $1.80 $9,900.00 Stimpel Webelhaus Associates, INC $17.00 $93,500.00 Engineer's Estimate 5,500 SQYD $7.50 $41,250.00
B0300 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
JAL CONSTRUCTION, INC. $135.00 $60,750.00
Marcum & Son LLC $193.00 $86,850.00 Moreno and Nelson Construction Corp $220.00 $99,000.00 Construction Solutions Group, LLC $90.00 $40,500.00 Stimpel Webelhaus Associates, INC $260.00 $117,000.00 Engineer's Estimate 450 CUYD $300.00 $135,000.00
15 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0320 30201-2000 ROADWAY AGGREGATE, METHOD 2
JAL CONSTRUCTION, INC. $125.00 $43,750.00
Marcum & Son LLC $127.00 $44,450.00 Moreno and Nelson Construction Corp $158.00 $55,300.00 Construction Solutions Group, LLC $68.40 $23,940.00 Stimpel Webelhaus Associates, INC $435.00 $152,250.00 Engineer's Estimate 350 CUYD $130.00 $45,500.00
B0340 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
JAL CONSTRUCTION, INC. $120.00 $162,000.00
Marcum & Son LLC $155.00 $209,250.00 Moreno and Nelson Construction Corp $210.00 $283,500.00 Construction Solutions Group, LLC $192.00 $259,200.00 Stimpel Webelhaus Associates, INC $280.00 $378,000.00 Engineer's Estimate 1,350 TON $320.00 $432,000.00
B0360 41201-0000 TACK COAT
JAL CONSTRUCTION, INC. $600.00 $1,800.00
Marcum & Son LLC $850.00 $2,550.00 Moreno and Nelson Construction Corp $1,700.00 $5,100.00 Construction Solutions Group, LLC $1,560.00 $4,680.00 Stimpel Webelhaus Associates, INC $2,000.00 $6,000.00 Engineer's Estimate 3.00 TON $1,500.00 $4,500.00
B0380 41301-0800 ASPHALT PAVEMENT MILLING, 3-INCH DEPTH
JAL CONSTRUCTION, INC. $5.00 $12,550.00
Marcum & Son LLC $6.00 $15,060.00 Moreno and Nelson Construction Corp $7.00 $17,570.00 Construction Solutions Group, LLC $21.60 $54,216.00 Stimpel Webelhaus Associates, INC $8.50 $21,335.00 Engineer's Estimate 2,510 SQYD $6.25 $15,687.50
B0400 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $125.00 $1,250.00 Moreno and Nelson Construction Corp $250.00 $2,500.00 Construction Solutions Group, LLC $138.00 $1,380.00 Stimpel Webelhaus Associates, INC $230.00 $2,300.00 Engineer's Estimate 10 HOUR $190.00 $1,900.00
16 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0420 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $150.00 $1,500.00 Moreno and Nelson Construction Corp $250.00 $2,500.00 Construction Solutions Group, LLC $102.00 $1,020.00 Stimpel Webelhaus Associates, INC $165.00 $1,650.00 Engineer's Estimate 10 HOUR $250.00 $2,500.00
B0440 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $190.00 $1,900.00 Moreno and Nelson Construction Corp $380.00 $3,800.00 Construction Solutions Group, LLC $102.00 $1,020.00 Stimpel Webelhaus Associates, INC $235.00 $2,350.00 Engineer's Estimate 10 HOUR $240.00 $2,400.00
B0460 62301-0000 GENERAL LABOR
JAL CONSTRUCTION, INC. $100.00 $1,000.00
Marcum & Son LLC $105.00 $1,050.00 Moreno and Nelson Construction Corp $152.00 $1,520.00 Construction Solutions Group, LLC $73.56 $735.60 Stimpel Webelhaus Associates, INC $90.00 $900.00 Engineer's Estimate 10 HOUR $110.00 $1,100.00
B0480 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
JAL CONSTRUCTION, INC. $25.00 $1,125.00
Marcum & Son LLC $45.00 $2,025.00 Moreno and Nelson Construction Corp $14.00 $630.00 Construction Solutions Group, LLC $120.00 $5,400.00 Stimpel Webelhaus Associates, INC $225.00 $10,125.00 Engineer's Estimate 45 SQYD $75.00 $3,375.00
B0500 62502-0000 TURF ESTABLISHMENT
JAL CONSTRUCTION, INC. $90.00 $4,050.00
Marcum & Son LLC $8.00 $360.00 Moreno and Nelson Construction Corp $4.25 $191.25 Construction Solutions Group, LLC $54.00 $2,430.00 Stimpel Webelhaus Associates, INC $225.00 $10,125.00 Engineer's Estimate 45 SQYD $85.00 $3,825.00
17 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0520 63302-0000 SIGN SYSTEM
JAL CONSTRUCTION, INC. $105.00 $22,470.00
Marcum & Son LLC $103.00 $22,042.00 Moreno and Nelson Construction Corp $142.00 $30,388.00 Construction Solutions Group, LLC $123.60 $26,450.40 Stimpel Webelhaus Associates, INC $225.00 $48,150.00 Engineer's Estimate 214 SQFT $250.00 $53,500.00
B0540 63308-3000 OBJECT MARKER, TYPE 3
JAL CONSTRUCTION, INC. $450.00 $900.00
Marcum & Son LLC $450.00 $900.00 Moreno and Nelson Construction Corp $260.00 $520.00 Construction Solutions Group, LLC $108.00 $216.00 Stimpel Webelhaus Associates, INC $600.00 $1,200.00 Engineer's Estimate 2 EACH $490.00 $980.00
B0560 63309-0200 DELINEATOR, TYPE 2 (WHITE)
JAL CONSTRUCTION, INC. $100.00 $6,900.00
Marcum & Son LLC $90.00 $6,210.00 Moreno and Nelson Construction Corp $260.00 $17,940.00 Construction Solutions Group, LLC $108.00 $7,452.00 Stimpel Webelhaus Associates, INC $240.00 $16,560.00 Engineer's Estimate 69 EACH $100.00 $6,900.00
B0580 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)
JAL CONSTRUCTION, INC. $0.35 $57,008.00
Marcum & Son LLC $0.25 $40,720.00 Moreno and Nelson Construction Corp $0.17 $27,689.60 Construction Solutions Group, LLC $0.30 $48,864.00 Stimpel Webelhaus Associates, INC $0.15 $24,432.00 Engineer's Estimate 162,880 LNFT $0.24 $39,091.20
B0600 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN (YELLOW)
JAL CONSTRUCTION, INC. $0.30 $3,714.00
Marcum & Son LLC $0.22 $2,723.60 Moreno and Nelson Construction Corp $0.26 $3,218.80 Construction Solutions Group, LLC $0.26 $3,218.80 Stimpel Webelhaus Associates, INC $0.20 $2,476.00 Engineer's Estimate 12,380 LNFT $0.18 $2,228.40
18 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0620 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
JAL CONSTRUCTION, INC. $125.00 $750.00
Marcum & Son LLC $185.00 $1,110.00 Moreno and Nelson Construction Corp $280.00 $1,680.00 Construction Solutions Group, LLC $240.00 $1,440.00 Stimpel Webelhaus Associates, INC $275.00 $1,650.00 Engineer's Estimate 6 EACH $220.00 $1,320.00
B0640 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
JAL CONSTRUCTION, INC. $30.00 $690.00
Marcum & Son LLC $20.00 $460.00 Moreno and Nelson Construction Corp $21.00 $483.00 Construction Solutions Group, LLC $42.00 $966.00 Stimpel Webelhaus Associates, INC $65.00 $1,495.00 Engineer's Estimate 23 EACH $29.00 $667.00
B0660 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
JAL CONSTRUCTION, INC. $2,500.00 $5,000.00
Marcum & Son LLC $2,500.00 $5,000.00 Moreno and Nelson Construction Corp $1,810.00 $3,620.00 Construction Solutions Group, LLC $2,880.00 $5,760.00 Stimpel Webelhaus Associates, INC $3,750.00 $7,500.00 Engineer's Estimate 2 EACH $11,000.00 $22,000.00
B0680 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
JAL CONSTRUCTION, INC. $40.00 $9,800.00
Marcum & Son LLC $40.00 $9,800.00 Moreno and Nelson Construction Corp $36.00 $8,820.00 Construction Solutions Group, LLC $48.00 $11,760.00 Stimpel Webelhaus Associates, INC $220.00 $53,900.00 Engineer's Estimate 245 SQFT $62.00 $15,190.00
B0700 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
JAL CONSTRUCTION, INC. $100.00 $1,000.00
Marcum & Son LLC $85.00 $850.00 Moreno and Nelson Construction Corp $141.00 $1,410.00 Construction Solutions Group, LLC $87.60 $876.00 Stimpel Webelhaus Associates, INC $130.00 $1,300.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00
19 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: B
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0720 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
JAL CONSTRUCTION, INC. $250.00 $10,750.00
Marcum & Son LLC $150.00 $6,450.00 Moreno and Nelson Construction Corp $1,430.00 $61,490.00 Construction Solutions Group, LLC $1,080.00 $46,440.00 Stimpel Webelhaus Associates, INC $1,500.00 $64,500.00 Engineer's Estimate 43 DAY $2,000.00 $86,000.00
Total Schedule - All Items
JAL CONSTRUCTION, INC. $588,037.00
Marcum & Son LLC $615,915.60 Moreno and Nelson Construction Corp $943,418.65 Construction Solutions Group, LLC $1,164,244.80 Stimpel Webelhaus Associates, INC $1,447,288.00 Engineer's Estimate $1,324,445.00
20 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Solcitation No: 69056724B000003
Division: Western Federal Lands
State: OR County: Crook
Federal Land: Ochoco National Forest Opened at: Vancouver, WA
Opened by: Marino Chea
Date: 05/13/25
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
JAL CONSTRUCTION, INC. $720,072.00
PO Box 6269 Bend, OR 97708
Marcum & Son LLC $748,175.60 336 SW Black Butte Blvd Redmond, OR 97756
Moreno and Nelson Construction Corp $1,059,215.40
665 STINSEN AVE
Walla Walla, WA 99362
Construction Solutions Group, LLC $1,408,708.80 425 Highland Ave St. Louis, MO 63122
Stimpel Webelhaus Associates, INC $1,814,588.00
PO BOX 492335
Engineer's Estimate $1,623,445.00
21 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0020 15101-0000 MOBILIZATION
JAL CONSTRUCTION, INC. Lump Sum $70,000.00 Marcum & Son LLC Lump Sum $31,500.00 Moreno and Nelson Construction Corp Lump Sum $16,500.00 Construction Solutions Group, LLC Lump Sum $443,600.00 Stimpel Webelhaus Associates, INC Lump Sum $200,000.00 Engineer's Estimate ALL LPSM Lump Sum $159,458.40
C0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
JAL CONSTRUCTION, INC. Lump Sum $15,000.00 Marcum & Son LLC Lump Sum $13,000.00 Moreno and Nelson Construction Corp Lump Sum $16,000.00 Construction Solutions Group, LLC Lump Sum $18,000.00 Stimpel Webelhaus Associates, INC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00
C0060 15301-0000 CONTRACTOR QUALITY CONTROL
JAL CONSTRUCTION, INC. Lump Sum $12,500.00 Marcum & Son LLC Lump Sum $11,000.00 Moreno and Nelson Construction Corp Lump Sum $16,000.00 Construction Solutions Group, LLC Lump Sum $147,000.00 Stimpel Webelhaus Associates, INC Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00
C0080 15401-0000 CONTRACTOR TESTING
JAL CONSTRUCTION, INC. Lump Sum $17,500.00 Marcum & Son LLC Lump Sum $12,000.00 Moreno and Nelson Construction Corp Lump Sum $16,000.00 Construction Solutions Group, LLC Lump Sum $19,000.00 Stimpel Webelhaus Associates, INC Lump Sum $12,500.00 Engineer's Estimate ALL LPSM Lump Sum $27,000.00
C0100 15501-0000 CONSTRUCTION SCHEDULE
JAL CONSTRUCTION, INC. Lump Sum $1,500.00 Marcum & Son LLC Lump Sum $5,500.00 Moreno and Nelson Construction Corp Lump Sum $2,260.00 Construction Solutions Group, LLC Lump Sum $29,000.00
Engineer's Estimate ALL LPSM Lump Sum $7,000.00
22 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE
JAL CONSTRUCTION, INC. $5.00 $3,300.00
Marcum & Son LLC $6.00 $3,960.00 Moreno and Nelson Construction Corp $2.00 $1,320.00 Construction Solutions Group, LLC $5.40 $3,564.00 Stimpel Webelhaus Associates, INC $12.00 $7,920.00 Engineer's Estimate 660 LNFT $20.00 $13,200.00
C0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
JAL CONSTRUCTION, INC. $6.00 $6,300.00
Marcum & Son LLC $8.00 $8,400.00 Moreno and Nelson Construction Corp $3.50 $3,675.00 Construction Solutions Group, LLC $4.20 $4,410.00 Stimpel Webelhaus Associates, INC $7.00 $7,350.00 Engineer's Estimate 1,050 LNFT $9.25 $9,712.50
C0160 20101-0000 CLEARING AND GRUBBING
JAL CONSTRUCTION, INC. $15,000.00 $6,000.00
Marcum & Son LLC $8,500.00 $3,400.00 Moreno and Nelson Construction Corp $56,820.00 $22,728.00 Construction Solutions Group, LLC $18,000.00 $7,200.00 Stimpel Webelhaus Associates, INC $50,000.00 $20,000.00 Engineer's Estimate 0.40 ACRE $55,000.00 $22,000.00
C0180 20301-2400 REMOVAL OF SIGN
JAL CONSTRUCTION, INC. $250.00 $500.00
Marcum & Son LLC $250.00 $500.00 Moreno and Nelson Construction Corp $540.00 $1,080.00 Construction Solutions Group, LLC $300.00 $600.00 Stimpel Webelhaus Associates, INC $260.00 $520.00 Engineer's Estimate 2 EACH $280.00 $560.00
C0200 20303-1600 REMOVAL OF PAVEMENT, ASPHALT (8-INCH DEPTH)
JAL CONSTRUCTION, INC. $5.00 $16,500.00
Marcum & Son LLC $10.85 $35,805.00 Moreno and Nelson Construction Corp $45.00 $148,500.00 Construction Solutions Group, LLC $3.60 $11,880.00
23 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0220 20401-0000 ROADWAY EXCAVATION
JAL CONSTRUCTION, INC. $110.00 $11,000.00
Marcum & Son LLC $97.00 $9,700.00 Moreno and Nelson Construction Corp $144.00 $14,400.00 Construction Solutions Group, LLC $48.00 $4,800.00 Stimpel Webelhaus Associates, INC $570.00 $57,000.00 Engineer's Estimate 100 CUYD $230.00 $23,000.00
C0240 20402-0000 SUBEXCAVATION
JAL CONSTRUCTION, INC. $70.00 $7,000.00
Marcum & Son LLC $97.00 $9,700.00 Moreno and Nelson Construction Corp $194.00 $19,400.00 Construction Solutions Group, LLC $60.00 $6,000.00 Stimpel Webelhaus Associates, INC $190.00 $19,000.00 Engineer's Estimate 100 CUYD $130.00 $13,000.00
C0260 20403-0000 UNCLASSIFIED BORROW
JAL CONSTRUCTION, INC. $110.00 $22,000.00
Marcum & Son LLC $132.00 $26,400.00 Moreno and Nelson Construction Corp $86.00 $17,200.00 Construction Solutions Group, LLC $78.00 $15,600.00 Stimpel Webelhaus Associates, INC $430.00 $86,000.00 Engineer's Estimate 200 CUYD $80.00 $16,000.00
C0280 20435-1000 BACKFILL, SELECT GRANULAR
JAL CONSTRUCTION, INC. $135.00 $13,500.00
Marcum & Son LLC $132.00 $13,200.00 Moreno and Nelson Construction Corp $154.00 $15,400.00 Construction Solutions Group, LLC $78.00 $7,800.00 Stimpel Webelhaus Associates, INC $430.00 $43,000.00 Engineer's Estimate 100 CUYD $220.00 $22,000.00
C0300 20701-0400 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE D (WOVEN)
JAL CONSTRUCTION, INC. $5.00 $32,500.00
Marcum & Son LLC $2.75 $17,875.00 Moreno and Nelson Construction Corp $4.75 $30,875.00 Construction Solutions Group, LLC $1.80 $11,700.00 Stimpel Webelhaus Associates, INC $17.00 $110,500.00 Engineer's Estimate 6,500 SQYD $7.50 $48,750.00
24 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0320 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
JAL CONSTRUCTION, INC. $135.00 $60,750.00
Marcum & Son LLC $193.00 $86,850.00 Moreno and Nelson Construction Corp $210.00 $94,500.00 Construction Solutions Group, LLC $90.00 $40,500.00 Stimpel Webelhaus Associates, INC $260.00 $117,000.00 Engineer's Estimate 450 CUYD $300.00 $135,000.00
C0340 30201-2000 ROADWAY AGGREGATE, METHOD 2
JAL CONSTRUCTION, INC. $125.00 $75,000.00
Marcum & Son LLC $127.00 $76,200.00 Moreno and Nelson Construction Corp $123.00 $73,800.00 Construction Solutions Group, LLC $68.40 $41,040.00 Stimpel Webelhaus Associates, INC $350.00 $210,000.00 Engineer's Estimate 600 CUYD $130.00 $78,000.00
C0360 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
JAL CONSTRUCTION, INC. $120.00 $198,000.00
Marcum & Son LLC $155.00 $255,750.00 Moreno and Nelson Construction Corp $210.00 $346,500.00 Construction Solutions Group, LLC $192.00 $316,800.00 Stimpel Webelhaus Associates, INC $270.00 $445,500.00 Engineer's Estimate 1,650 TON $320.00 $528,000.00
C0380 41201-0000 TACK COAT
JAL CONSTRUCTION, INC. $600.00 $1,800.00
Marcum & Son LLC $850.00 $2,550.00 Moreno and Nelson Construction Corp $1,670.00 $5,010.00 Construction Solutions Group, LLC $1,560.00 $4,680.00 Stimpel Webelhaus Associates, INC $2,000.00 $6,000.00 Engineer's Estimate 3.00 TON $1,500.00 $4,500.00
C0400 41301-0800 ASPHALT PAVEMENT MILLING, 3-INCH DEPTH
JAL CONSTRUCTION, INC. $5.00 $12,550.00
Marcum & Son LLC $5.00 $12,550.00 Moreno and Nelson Construction Corp $7.00 $17,570.00 Construction Solutions Group, LLC $21.60 $54,216.00 Stimpel Webelhaus Associates, INC $8.50 $21,335.00 Engineer's Estimate 2,510 SQYD $6.25 $15,687.50
25 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0420 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $125.00 $1,250.00 Moreno and Nelson Construction Corp $250.00 $2,500.00 Construction Solutions Group, LLC $138.00 $1,380.00 Stimpel Webelhaus Associates, INC $230.00 $2,300.00 Engineer's Estimate 10 HOUR $190.00 $1,900.00
C0440 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $150.00 $1,500.00 Moreno and Nelson Construction Corp $250.00 $2,500.00 Construction Solutions Group, LLC $102.00 $1,020.00 Stimpel Webelhaus Associates, INC $165.00 $1,650.00 Engineer's Estimate 10 HOUR $250.00 $2,500.00
C0460 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
JAL CONSTRUCTION, INC. $150.00 $1,500.00
Marcum & Son LLC $190.00 $1,900.00 Moreno and Nelson Construction Corp $370.00 $3,700.00 Construction Solutions Group, LLC $102.00 $1,020.00 Stimpel Webelhaus Associates, INC $235.00 $2,350.00 Engineer's Estimate 10 HOUR $240.00 $2,400.00
C0480 62301-0000 GENERAL LABOR
JAL CONSTRUCTION, INC. $100.00 $1,000.00
Marcum & Son LLC $105.00 $1,050.00 Moreno and Nelson Construction Corp $150.00 $1,500.00 Construction Solutions Group, LLC $73.56 $735.60 Stimpel Webelhaus Associates, INC $90.00 $900.00 Engineer's Estimate 10 HOUR $110.00 $1,100.00
C0500 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
JAL CONSTRUCTION, INC. $8.00 $3,600.00
Marcum & Son LLC $15.00 $6,750.00 Moreno and Nelson Construction Corp $14.00 $6,300.00 Construction Solutions Group, LLC $120.00 $54,000.00 Stimpel Webelhaus Associates, INC $115.00 $51,750.00 Engineer's Estimate 450 SQYD $25.00 $11,250.00
26 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0520 62502-0000 TURF ESTABLISHMENT
JAL CONSTRUCTION, INC. $12.00 $5,400.00
Marcum & Son LLC $8.00 $3,600.00 Moreno and Nelson Construction Corp $3.50 $1,575.00 Construction Solutions Group, LLC $9.60 $4,320.00 Stimpel Webelhaus Associates, INC $115.00 $51,750.00 Engineer's Estimate 450 SQYD $35.00 $15,750.00
C0540 63302-0000 SIGN SYSTEM
JAL CONSTRUCTION, INC. $115.00 $24,610.00
Marcum & Son LLC $103.00 $22,042.00 Moreno and Nelson Construction Corp $139.00 $29,746.00 Construction Solutions Group, LLC $123.60 $26,450.40 Stimpel Webelhaus Associates, INC $225.00 $48,150.00 Engineer's Estimate 214 SQFT $250.00 $53,500.00
C0560 63308-3000 OBJECT MARKER, TYPE 3
JAL CONSTRUCTION, INC. $450.00 $900.00
Marcum & Son LLC $85.00 $170.00 Moreno and Nelson Construction Corp $260.00 $520.00 Construction Solutions Group, LLC $108.00 $216.00 Stimpel Webelhaus Associates, INC $600.00 $1,200.00 Engineer's Estimate 2 EACH $490.00 $980.00
C0580 63309-0200 DELINEATOR, TYPE 2 (WHITE)
JAL CONSTRUCTION, INC. $100.00 $6,900.00
Marcum & Son LLC $90.00 $6,210.00 Moreno and Nelson Construction Corp $260.00 $17,940.00 Construction Solutions Group, LLC $108.00 $7,452.00 Stimpel Webelhaus Associates, INC $240.00 $16,560.00 Engineer's Estimate 69 EACH $100.00 $6,900.00
C0600 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)
JAL CONSTRUCTION, INC. $0.35 $57,008.00
Marcum & Son LLC $0.25 $40,720.00 Moreno and Nelson Construction Corp $0.17 $27,689.60 Construction Solutions Group, LLC $0.30 $48,864.00 Stimpel Webelhaus Associates, INC $0.15 $24,432.00 Engineer's Estimate 162,880 LNFT $0.24 $39,091.20
27 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0620 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN (YELLOW)
JAL CONSTRUCTION, INC. $0.30 $3,714.00
Marcum & Son LLC $0.22 $2,723.60 Moreno and Nelson Construction Corp $0.26 $3,218.80 Construction Solutions Group, LLC $0.26 $3,218.80 Stimpel Webelhaus Associates, INC $0.20 $2,476.00 Engineer's Estimate 12,380 LNFT $0.18 $2,228.40
C0640 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
JAL CONSTRUCTION, INC. $125.00 $750.00
Marcum & Son LLC $185.00 $1,110.00 Moreno and Nelson Construction Corp $270.00 $1,620.00 Construction Solutions Group, LLC $240.00 $1,440.00 Stimpel Webelhaus Associates, INC $275.00 $1,650.00 Engineer's Estimate 6 EACH $220.00 $1,320.00
C0660 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
JAL CONSTRUCTION, INC. $30.00 $690.00
Marcum & Son LLC $20.00 $460.00 Moreno and Nelson Construction Corp $21.00 $483.00 Construction Solutions Group, LLC $42.00 $966.00 Stimpel Webelhaus Associates, INC $65.00 $1,495.00 Engineer's Estimate 23 EACH $29.00 $667.00
C0680 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
JAL CONSTRUCTION, INC. $2,500.00 $5,000.00
Marcum & Son LLC $2,500.00 $5,000.00 Moreno and Nelson Construction Corp $1,780.00 $3,560.00 Construction Solutions Group, LLC $2,880.00 $5,760.00 Stimpel Webelhaus Associates, INC $3,750.00 $7,500.00 Engineer's Estimate 2 EACH $11,000.00 $22,000.00
C0700 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
JAL CONSTRUCTION, INC. $40.00 $9,800.00
Marcum & Son LLC $40.00 $9,800.00 Moreno and Nelson Construction Corp $35.00 $8,575.00 Construction Solutions Group, LLC $48.00 $11,760.00 Stimpel Webelhaus Associates, INC $220.00 $53,900.00 Engineer's Estimate 245 SQFT $62.00 $15,190.00
28 out of 28
Project No: OR FS OCHOC607 22(1)
Project Name: ROAD 22 REPAIRS MP 0.0 TO 8.0
Schedule: C
Schedule Type: Alternate
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C0720 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
JAL CONSTRUCTION, INC. $100.00 $1,000.00
Marcum & Son LLC $85.00 $850.00 Moreno and Nelson Construction Corp $139.00 $1,390.00 Construction Solutions Group, LLC $87.60 $876.00 Stimpel Webelhaus Associates, INC $130.00 $1,300.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00
C0740 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
JAL CONSTRUCTION, INC. $250.00 $12,000.00
Marcum & Son LLC $150.00 $7,200.00 Moreno and Nelson Construction Corp $1,410.00 $67,680.00 Construction Solutions Group, LLC $1,080.00 $51,840.00 Stimpel Webelhaus Associates, INC $1,500.00 $72,000.00 Engineer's Estimate 48 DAY $2,700.00 $129,600.00
Total Schedule - All Items
JAL CONSTRUCTION, INC. $720,072.00
Marcum & Son LLC $748,175.60 Moreno and Nelson Construction Corp $1,059,215.40 Construction Solutions Group, LLC $1,408,708.80 Stimpel Webelhaus Associates, INC $1,814,588.00 Engineer's Estimate $1,623,445.00
| 2025-05-14T09:24:41-0700 | |
| MARINO CHEA |
| 2025-05-14T09:25:19-0700 | |
| MARINO CHEA |
| 2025-05-14T09:25:53-0700 | |
| MARINO CHEA |