This document contains questions and answers regarding a forthcoming federal solicitation to rehabilitate portions of the Going-to-the-Sun Road and replace a bridge in Glacier National Park. The solicitation has not yet been released but is anticipated to be posted to SAM.gov in the near future. Prospective bidders are advised to monitor that site and follow the solicitation to receive automatic notifications. Questions received prior to solicitation release should not be submitted and bidders should wait for the official solicitation documents, which will be the governing documents for questions and bidding. The project involves electrical work for which bidders may have additional questions once the solicitation is released. The involved agency is the Department of Transportation Federal Highway Administration.

View the file

Other files

File Type Posted
QA_09-07-21.pdf PDF
Prelim Letter_10(45) 2021.pdf PDF
Pre Liminary glac01045_Plans_081921.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT PRA GLAC 10(45)

Rehabilitate Final 9.3 miles of the Going-to-the-Sun Road & Replace Bridge Over McDonald Creek

# General Technical Question Answer Date

1 X

Currently Glacier National Park is ticketed entry before 6:00 A.M. and after 5:00 P.M. Will contractors be granted a pass to enter to view the project or would we need to purchase a pass or enter after gate hours?

Glacier Park Ticketed Entry stopped on Labor Day so ticketed entry is no longer required.

9/7/21

2 X

63621-1000 Utility, Pull Box, (Electrical) We only see a detail for the communications pull box on plan sheet C.4

The preliminary plans posted on Sam.Gov have been posted to aid prospective bidders in identifying the location and type of work for this project. The preliminary plans are only intended to assist in prospective bidders while doing a field review of the project prior to project advertisement period. The preliminary plans are not to be used for bidding purposes

5-Oct-21

3 X

Also when is the anticipated bid date? Please monitor the SAM site for actual date of solicitation release (https://sam.gov/). To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

5-Oct-21

4 X

Thank you for the reply and thank you for advising to view the sites before the weather changes.

We recently visited the sites and will have some electrical questions regarding solicitations 10(44) and 10(45). Should we submit our questions now or wait until the solicitations are published?

Please wait for the solicitation documents to be posted.

Solicitation documents are the officials documents that should be used for questions and bidding purposes. Please monitor (https://sam.gov/) for the official solicitation release. Should you still have questions once the solicitation is released, please do not hesitate to inquire at wfl.plans-spec e-mail address.

5-Oct-21

Check General or Technical