This project description outlines requirements for a federal construction contract to build a bicycle and pedestrian trail in Lemhi County, Idaho. The work includes constructing a 4.5 mile paved trail from Salmon to Shoup Campground, expanding and resurfacing the campground's parking lot, and minor ancillary tasks. The project scope involves earthwork, aggregate base courses, asphalt paving, culverts, drainage work, erosion control, traffic control, signage, and striping. Anticipated cost is between $1-2 million. The tentative completion deadline is Fall 2020. The solicitation will be issued as a small business set-aside through the Federal Highway Administration Department of Transportation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID LEMHI 93(1)/2L Trails Highway 93 South, Lemhi County, ID.
The work consists constructing a 4.5 mile paved bicycle and pedestrian trail from Salmon Idaho to Shoup Campground park lot, expanding and resurfacing the pavement of Shoup Campground park lot and other small items of work.
Project length: 4.5 Miles
Tentative Fixed Completion Date: Fall 2020 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $1 Million to $2 Million
Location: 1 Miles South of Salmon, Idaho.
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
On e S ch ed ul e
DIVISION 150 – Project Requirements 152 Construction Survey & Staking Yes 153 Contractor Quality Control and Assurance Yes 154 Contractor Sampling & Testing Yes 155 Schedules for Construction Contracts (construction schedules) Yes 157 Soil Erosion & Sediment Control (erosion control devices) Fiber Roll 15,700 LNFT
DIVISION 200 – Earthwork 201 Clearing & Grubbing 0.2 ACRE 203 Removal of Structures & Obstructions (structures, demolition) Removal of Curb, Concrete 390 LNFT 204 Excavation & Embankment Roadway Excavation
3,900 CUYD
Select Borrow (Govt Furnish)
10,600 CUYD
207 Earthwork Geosynthetics Separation Geotextile 28,750 SQYD
DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate Roadway Aggregate 12,303 TON
DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete 6,100 TON
On e S ch ed ul e
DIVISION 600 – Incidental Construction 602 Culverts & Drains (indicate one or both) 24-inch pipe culvert 20 LNFT 607 Cleaning, Relaying, & Repairing Existing Drainage Structures Cleaning Culverts 40 Each 625 Turf Establishment (indicate seeding or mulching separately) 6.2 ACRE 633 Permanent Traffic Control (traffic control devices) Sign System 240 SQFT
Remove and Reset Signs 23 EACH 634 Permanent Pavement Markings (traffic pavement markings) 55,290 LNFT 635 Temporary Traffic Control – Flagger 250 HOURS 635 Temporary Traffic Control – Pilot Car 635 Temporary Traffic Control – Barrels 195 EACH
Signs 431 EACH
| DIVISION 200 – Earthwork |
| DIVISION 300 – Aggregate and Base Courses |
| DIVISION 400 – Asphalt Pavements & Surface Treatments |