6903 Z1 Rebid Evaluation Criteria.docx
DOCX document 27 KB Posted
- Attached to
- Contract Engineer for Project Management and Construction of 3 FM Radio Stations in Nebraska
- Solicitation number
- 6903 Z1 REBID
- Issued by
- Platte County, Nebraska
About this file
This document is an Evaluation Criteria for Request for Proposal (RFP) Number 6903 Z1 Rebid issued by the State of Nebraska, Department of Administrative Services (DAS), Materiel Division, State Purchasing Bureau (SPB). The RFP is for the purpose of selecting a qualified Contract Engineer for Project Management and Construction of 3 FM Radio Stations in Nebraska. Proposals will be evaluated based on Corporate Overview (35 points), Technical Approach (45 points), and Cost Proposal (20 points), for a total of 100 points. The lowest cost proposal will receive the maximum 20 points for the Cost Proposal, and other proposals will receive points proportionately based on the formula provided. The mandatory requirements for the proposal include the Request for Proposal form, Corporate Overview, Technical Approach, and Cost Proposal.
The RFP has an opening date of July 8, 2024. The resulting contract may not be an exclusive contract, as the State reserves the right to contract for the same or similar services from other sources. Pricing information, funding sources, and any set-asides are not provided in the document.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EVALUATION CRITERIA
RFP NUMBER 6903 Z1 Rebid 3 FM Stations Opening Date: July 8, 2024
Mandatory Requirements The proposals will first be examined to determine if all mandatory requirements listed below have been addressed to warrant further evaluation. Proposals not meeting mandatory requirements will be excluded from further evaluation. The mandatory requirement items are as follows:
Request for Proposal For Contractual Services form, signed in ink, Corporate Overview, Technical Approach; and Cost Proposal.
Evaluation Criteria All responses to this Request for Proposal, which fulfill all mandatory requirements, will be evaluated. Each category will have a maximum possible point potential. Areas that will be addressed and scored during the evaluation include:
| Evaluation Criteria |
| Possible Points |
| Part 1 Corporate Overview |
| 35 |
Part 2 Technical Approach (Project & Business Requirements)
| Part 3 Cost Proposal Points |
| 20 |
| Total Points without Oral Interviews |
| 100 |
Part 4 – Cost Proposal Points Cost points should be calculated as follows:
0. Establish lowest cost submitted – lowest cost submitted receives the maximum points.
0. To assign points to all others, the following formula should be followed:
Lowest Cost Submitted Cost Submitted x Maximum Possible Cost Points = Cost Points to Award (see samples below)
Formula
Sample
Sample
Sample
Lowest Cost Submitted
$100,000
$100,000
$100,000
Cost Submitted
$100,000
$200,000
$150,000 x Maximum Possible Cost Points
= Points To Award
26.7
File details come from the government source that posted it. Updated .