This document is a bid tabulation for an Invitation to Bid (ITB) issued by the State of Nebraska, Department of Administrative Services, Materiel Division, State Purchasing Bureau for the purpose of selecting a contractor to provide an LED red/white obstruction lighting system for the K25OG translator tower. The ITB requested pricing for the lighting system, disassembly/removal of the existing lighting system, and freight. Four bidders responded, with the lowest responsive bid of $35,600 from AFCOMM, LLC DBA SLATERCOM-WCD. The other bids were $47,982.88, $58,745.00, and $65,500.00. The contract has a 30-day delivery time after receipt of order.
The pricing terms, payment terms, and delivery times are provided for each bidder. There are no set-asides or other special requirements mentioned. The contract appears to be a one-time purchase with no renewal options.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 6753 OF Addendum One Questions and Answers.pdf | ||
| Drake Lighting.pdf | ||
| National Tower Control.pdf | ||
| Precision Communications.pdf | ||
| 6753 OF Intent to Award Letter JD.pdf | ||
| 6753 OF.pdf | ||
| Slatercom.pdf | ||
| 6753 OF Bid Tabulation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Procurement Contracts Officer: Julie Dabydeen 6753 OF
NETV
Opening Date: 01/27/23
LED LED RED/WHITE
OBSTRUCTION LIGHTING
SYSTEM FOR K25OG
TRANSLATOR TOWER
Description Qty UOM Unit Price Ext. Price Unit Price Ext. Price Unit Price Ext. Price Unit Price Ext. Price
LED RED/WHITE
OBSTRUCTION LIGHTING
SYSTEM K25OG
TRANSLATOR TOWER
INCLUDING INSTALLATION
COSTS
1 EA $ 57,945.00 $ 57,945.00 $ 20,000.00 $ 20,000.00 $ 34,991.44 $ 34,991.44 $ 39,000.00 $ 39,000.00
DISASSEMBLY/REMOVAL
EXISTING LIGHTING
SYSTEM & CONTROL
1 EA $ 0* $ 0* $ 14,800.00 $ 14,800.00 $ 11,991.44 $ 11,991.44 $ 26,000.00 $ 26,000.00
3 FREIGHT 1 EA $ 800.00 $ 800.00 $ 800.00 $ 800.00 $ 1,000.00 $ 1,000.00 $ 500.00 $ 500.00
$ 58,745.00 $ 35,600.00 $ 47,982.88 $ 65,500.00
No Bids None
AFCOMM, LLC DBA
SLATERCOM-WCD
NA% NA
Line 2- *included in above price for install
$58,745 TOTAL COST
PRECISION
COMMUNICATIONS LLC
NA% NA
90-120
DRAKE LIGHTING NATIONAL TOWER CONTROLS
(See Quote)
0% 30 Total