673 22 120 010000 Gen Requirements.pdf
PDF 339 KB Posted
- Solicitation number
- 36C24823R0037
About this file
This federal contract opportunity notice is for a Design-Build project to improve the campus grounds at the James A. Haley Veterans Hospital in Tampa, Florida. The solicitation number is 36C24823R0037 and will be posted on or about November 16, 2022. The general contractor will subcontract preparation of construction documents to a registered architect-engineer for VA approval. Work includes addition of U.S. military flags, a U.S. flag, and installation of a patriotic mural. The NAICS code is 236220 with a small business size standard of $39.5M. The estimated value is between $2,000,000 and $5,000,000. The project is 100% set aside for service-disabled veteran-owned small businesses. The contracting officer is Kenneth Caryer and he can be contacted at (813) 616-9487 or Kenneth.Caryer@va.gov. Apparent successful offerors must be verified and listed in VIP by the VA's Center for Verification and Evaluation by the time of proposal submission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24823R0037.docx | DOCX document | |
| Tampa site map.pdf | ||
| 673 22 120 Perspective.pdf | ||
| 673 22 120 Design Build SOW - Oct 2022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Improve James A. Haley veteran’ Hospital Campus Grounds
Design Build; 673-22-120 June 14 ,2022 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 NOT USED
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 CO/COR Office
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.18 NOT USED
1.19 TEMPORARY USE OF NEW ELEVATORS
1.20 TEMPORARY TOILETS
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
1.22 NOT USED
1.23 TESTS
1.24 NOT USED
1.25 NOT USED
Design Build; 673-22-120 June 14 ,2022 ii
1.26 NOT USED
1.27 STORAGE SPACE
1.28 CONSTRUCTION SIGN
1.29 SAFETY SIGN
1.30 PHOTOGRAPHIC DOCUMENTATION
1.31 NOT USED
1.32 NOT USED
1.33 NOT USED
Appendix A - Approved OSHA Training Providers List
Appendix B - VA Adopted Codes
Appendix C - Facilities Management Service - Alert
Appendix D - Safety and Infection Control Guide
Attachments 1a & 1b - Fire Sprinkler Work Notifications
Attachment 2 - Notification of Hot Work Operations by Contractor
Personnel (Burn Permit)
Attachment 3 - Fire Safety Inspection Checklist for Hot Work
Operations Area
Attachment 4 - Construction Fire Safety Check List
Attachments 5a & 5b - Contractor Work Plan & Peer Review
Attachment 6 - VA Information and Information System Security/Privacy
Language
Design Build 673-22-120 June 23 ,2022
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for James A. Haley Veterans
Hospital Project-Improve JAHVH Campus grounds with VA approved construction documents prepared by General Contractor’s Architect in a
Design Build contract, the VA approved and required drawings and specifications shall be the basis of construction and no part of the approved construction document shall be revise, alter and/ or change without the VA approval.
B. The General Contractor’s A/E shall be the Architect of records from start to the completion of the project. The VA shall require a Biweekly site visits and site meeting by the A/E to answer, resolve and approve design related question, and plan interpretation to give clarity to original design.
C. The General Contractor’s Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. The DB contractor shall submit in 10 days after issuance of NTP for VA approval a Works Schedule with values (Gantt Chart), and Schedule of
Values (Form AIA G 702 & 703). The DB contractor shall mobilize only after the approval of the schedules mentioned.
01 00 00 -2
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. The current version of hospital HPMs and SOPs listed below shall be followed:
• HPM 138-03 Safety and Health During Construction Activities
• HPM 138-04 Lockout – Tagout Program
• HPM 138-15 Interim Life Safety Measures
• HPM 138-23 Utility Shutdown Procedures
• HPM 138-24 Infection Control During Construction and Renovation
• SOP 138d-03 Ceiling, Floor, Wall or Partition Penetration Permit
System
• SOP
138e-02
Fire Sprinkler Valve
Supervision Program.
• SOP 138e-10 Hot Work Operations
• SOP 138e-11 Notification of Fire Alarm Impairment
• SOP 138e-17 Smoke Detector Cover Log
F. Prior to commencing work, general contractor shall provide proof that an OSHA certified “competent person” (CP) [(29 CFR 1926.20(b)(2)] will maintain a presence at the work site whenever the general or subcontractors are present.
01 00 00 -3
G. Training:
(1) Beginning July 31, 2005, all supervisory type personnel/ employees of general contractor and subcontractors shall have the
30-hour OSHA certified Construction Safety course and other relevant competency training, as determined by VA CP with input from the ICRA team.
(2) Beginning July 31, 2005, all non-supervisory type personnel/ employees of general contractor and subcontractors shall have the
10-hour OSHA certified Construction Safety Course and other relevant competency training, as determined by VA CP with input from the ICRA team.
(3) Submit copies of certificates and training records for all such personnel and employees that may be and/or will be on the work site(s) to the COTR and Contracting Officer for approval before the start of any work on-site.
H. Related Work: This specification section applies to ALL Divisions (0 through 34) of work under ALL other specification sections. A partial list of Codes and Standards adopted by the Department of Veterans Affairs is attached in Appendix B.
I. Normal Operation / Construction Hours: Construction operations at the James A. Haley VA Hospital are 7:30 AM to 4:30 PM, Monday through Friday, except for Federal Holidays. Requests to work beyond normal work hours shall be submitted in writing to the COR for approval and will include a description of work to be performed. Approval is subject to availability of the COR, type of work to be performed, and the specific hours requested. Contractors are reminded that patients are generally asleep after 9:00 PM. Approval to work beyond this time will also include an evaluation of the anticipated noise level generated by the contractor. Under no circumstances will the contractor proceed without express, written approval of the COR.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL BUILDING CONSTRUCTION: Work includes general construction, alterations, roads, walks, grading, surface slope, landscaping, necessary removal of existing structures and its disposal and construction and certain other items.
ITEM II, Electrical Work: Work includes all labor, material, equipment, and supervision to perform the required electrical construction work on this project including rough ins work to finishing works for both solar and standard AC power.
01 00 00 -4
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
3. The General Contractor prior to hiring subcontractors, GC shall have all subcontractor submitted to PM/COR to verification and approval by the VA.
Approved GC subcontractors shall furnish to the COR and Contracting Officer lists of employees that will be or may be on the construction site(s). The
List shall be on Company letter head that provides all the company contact information, shall provide the project number and title, locations of work, names of the employees, their titles, their job types, and personal contact numbers (i.e., cell phone). All sub-contractors, vendors and suppliers for the project shall furnish the same listing on their individual company letter heads to the GC who will provide the lists to the COR and Contracting
Officer. These lists shall be updated as necessary during the entire duration of the project. These lists may be used to provide a check list record of personnel on-site each day to be provided with the contractors
Daily Log reports. These lists may be used to provide a check list record of personnel on-site each day to be provided to the VA Police Department and their Dispatch Office where normal sign in and sign out occurs.
4. The General Contractor shall provide 2 ea Kaba Eplex E5731BWL-626-41, Electronic Pushbutton - Prox - Lock, IC “7 Pin O Bitted” BEST CORE. To be installed on the jobsite access doors. Locks are to be turned over to the COR upon completion of the project.
01 00 00 -5
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. (See hospital HPM 132-05) They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, the General Contractor shall provide a request for approval 21 calendar days prior to the requested date to the PM/COR so that security escort arrangements can be provided for the employees.
This notice is separate from any notices required for utility shutdown described later in this section.
3. No Phone photo allowed, or other photo devices of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. N/A
D. Key Control:
1. The General Contractor shall make available as requested keys and lock combinations to the Contracting officer’s representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the COR for permanent installation. See Section 08 71 00, DOOR
HARDWARE and coordinate.
3. Contractor may be issued keys for construction thru the COR.
4. All keys must be turned in at the end of the Contract.
5. Any key assigned to the contractor, which is lost or stolen will result in a replacement cost of $100.00 per key either lost or
01 00 00 -6 stolen. Any key either lost or stolen shall be reported to the COR;
it is the contractor’s responsibility to inform the VA Police and give a detailed report about the key loss. The contractor shall take a copy of the official police report and make payment to the
Agent Cashier before any additional replacement keys are made.
Final payment may be withheld and/or reduced until keys are returned or accounted for. A copy of the police report and receipt of payment shall be provided to the VA COR.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
01 00 00 -7
a. Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted at least 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies. Contractor and subcontractor parking is allowed in the Freedom lot only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or
01 00 00 -8 local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials location shall be as shown on the drawings as approved by the PM/COR. The contractor shall keep all work areas, storage areas, staging areas, access areas and routes clean and neat. The contractor shall provide sufficient trash containers so that there is no debris lying around. The containers shall be emptied at least daily, and trash disposed of by the contractor.
E. Workmen are subject to rules of Medical Center applicable to their conduct.
Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, always standing construction equipment and vehicles.
F. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation. All delivery shall be scheduled and received only during office hours. No nighttime delivery shall be accepted.
01 00 00 -9
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by PM/COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the COR with a schedule of phasing dates on which the Contractor intends to accomplish work in each specific area of site, grounds, or portion thereof. In addition, Contractor shall notify the PM/COR seven (7) calendar days in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
V A M & O and PM/COR and Contractor.
01 00 00 -10
The contractor shall have all submittals completed and turned in to the
Government for review no later than fourteen (14) calendar days from the date of the signed Notice to Proceed. The government will return submittals within seven (7) calendar days from acceptance/disapproval from the contractor. No work shall be started until all related submittals are approved. All materials shall be approved by the VA prior to delivery to the job site and start of work.
No work shall start until completion of VA approved plans and specs, and preconstruction survey and inspection are completed.
I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by PM/COR .
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall always maintain the campus ground clean, free from construction hazard and warning signs .
2. Contractor shall make sure lines buried at campus, such as existing fire protection and alarm equipment, landscape irrigation, electrical, and other hospital utility lines are protected and free from being damage during construction.
K. Utilities Services: always Maintain existing utility services for
Medical Center. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
01 00 00 -11
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of // COR // [Chief Engineer]
[Chief of Facilities Management]. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 21 calendar days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption. Refer to Attachment 5A.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions (deemed by the COR) of any system must be requested, in writing, at least 30 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical. On the next business day, the contractor’s daily log report shall explain the circumstances causing the emergency and the corrective actions taken.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
01 00 00 -12
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped, or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces unless otherwise directed by the COR. Firestop as needed.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be always open to traffic with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
3. Interruptions to these areas must be requested, in writing, at least twenty-one (21) calendar days prior to the desired time and shall be performed as directed by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
O. Coordination of Construction with Medical center Director: The activities at the Medical Center shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Medical Center Director, through the COR, in arranging construction schedule to cause the least possible interference with
Medical Center activities. Construction noise during the interment services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period:
01 00 00 -13
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials, and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey of the JAHVH grounds and parking lots in which alterations occur and areas which are anticipated routes of access, and furnish a report to PM/COR. The survey shall include photographs with scale/measurement.
1. Existing site conditions shall be detailed in the report.
2. Existence and conditions in report such as crack, uneven surfaces and site condition of area needing repair or alteration shall be drawn in plan as part of the construction documents.
3. Shall note any discrepancies between drawings and existing conditions at site in construction documents.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR
// and/or Supply Representative //, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls
01 00 00 -14 and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
4. Once the contractor is notified by the VA of problems or damage to
VA property, the contractor shall take immediate corrective action to protect and restore said property. During normal duty hours, corrective action shall be initiated within two (2) hours. After normal duty hours, corrective actions shall be initiated within four
(4) hours. The daily log for that day shall explain the problem(s) and corrective action(s) taken.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows and/or in accordance with Section 01 74 19, CONSTRUCTION WASTE
MANAGEMENT and the contractor shall fill up VA Waste Management form to be submitted with billing as back up for approval.
01 00 00 -15
1. Reserved items which are to remain property of the Government are // identified by attached tags or noted on drawings or in specifications // as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. NOT USED
3. NOT USED
4. NOT USED
5. NOT USED
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer
Representative.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
01 00 00 -16
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils, and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
- Designating areas for equipment maintenance and repair.
- Providing waste receptacles at convenient locations and provide regular collection of wastes.
- Locating equipment wash down areas on site and provide appropriate control of wash-waters.
- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
- Providing adequately maintained sanitary facilities.
01 00 00 -17
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter, or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed because of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 NOT USED
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, 01 00 00 -18 templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer Representative. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer Representative until authorized to remove them. If such marks are destroyed by the
Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.
C. NOT USED
D. NOT USED
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
01 00 00 -19
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR [Chief
Engineer] [Chief of Facilities Management] within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed, and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.16 RESIDENT PM/ENGINEER'S FIELD OFFICE
A. The Contractor shall, within fifteen (15) days after receipt of Notice to Proceed, provide where shown on the drawings a temporary field office, furniture, and two-inch-deep gravel surfaced area for use of the Resident Engineer COR. Office and furniture shall be new.
B. The field office shall provide not less than 67 square meters (720 gross square feet)134 square meters (1440 gross square feet) of floor area in one unit. Installation of the office shall meet all local codes.
01 00 00 -20
C. Provide office with two, 900 mm (three foot) wide exterior doors, including hardware and OSHA approved platform and stairs leading to grade.
D. Enclose the entire perimeter of the office from the floor to the ground and finish to match exterior. Provide R7 insulation and seal tight to ground with a painted 19 mm (3/4 inch) exterior grade plywood skirt.
E. Exterior finishes shall be manufacturer's standards.
F. Provide floor, wall, and roof with not less than R5 insulation.
G. Interior finishes shall consist of resilient flooring, plywood paneling or painted wallboard on walls, and acoustical tile ceilings. Interior doors may be either painted or stained.
H. NOT USED
I. Provide 750 mm (2-1/2 feet) wide by 900 mm (3 feet) high operable windows; two in each room (none required in sample room), except provide only one 600 mm (2 foot) high window in toilet room(s). Window openings shall be fitted with security bars to prevent any forced entry. The doors of field office shall have a hasp and padlock and deadbolts keyed from both sides.
J. Provide sufficient fluorescent lighting in each room to deliver 750 lux
(70 foot-candles) of light at desk top height without the aid of daylight. Provide one light switch in each room.
K. Provide one duplex receptacle in each wall of each room. If a wall is
3.0 m (10 feet) long or more, provide two receptacles for each 3.0 m
(10 feet), or portion thereof, of wall. Provide two duplex receptacles in low partition at secretary's desk.
L. The Contractor shall provide the following:
1. Electricity, hot and cold water, and necessary utility services
(except telephone).
2. All necessary piping, power circuits network cabling, cat 5e or better cabling for phones and computers, electrical fixtures, lighting, and other items necessary to provide a habitable structure for the purpose intended. The number of network and electrical receptacles will be as per attached drawing of the field office.
01 00 00 -21
3. NOT USED
4. NOT USED
P. At the completion of all work, including the punch list, the Resident
Engineer's COR field office and facilities shall become the property of the Contractor and Contractor shall remove same, including utility connections, from the Medical Center. The site shall be restored to original condition and finished in accordance with contract requirements. All Government temporary utilities shall be left intact, including utility connections, for future use by Department of Veterans
Affairs.
Q. NOT USED
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e., transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical
1.18 NOT USED
01 00 00 -22
1.19 NOT USE
1.20 TEMPORARY TOILETS
A. Contractor to provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer storage and water tank; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
A*. Contractor may have for use of Contractor's workmen; such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. NOT USED
C. NOT USED
D. NOT USED
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices
01 00 00 -23 providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the
Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the
Contractor at Contractor's expense.
1.22 NOT USED
1.23 TESTS
A. All campus sidewalks, ramps, roads, and parking lots shall be tested for compaction to pass soil engineering specifications.
B. Prior to asphalt and / or concrete placement individual passing test result of all required areas, will only be accepted when submitted with the test results and report.
1.24 NOT USED
1.25 NOT USED
1.26 NOT USED
01 00 00 -24
1.27 STORAGE SPACE
A. The DB contractor shall be responsible in storing all their materials, equipment, and tools offsite the JAHVH campus.
B. The DB contractor shall request the COR to allow their materials, equipment, and tools to remain on site over night for next they early hour construction.
1.28 CONSTRUCTION SIGN
A. Provide 22”x28” aluminum frame for project information to be displayed next to main entrance to construction site. Show in plan sign location and layout of all construction safety signs.
B. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
C. Paint all surfaces of sign and posts two coats of white gloss paint.
Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
D. Maintain sign and remove it when directed by the COR.
E. Detail Drawing of construction sign showing required legend and other characteristics of sign is attached hereto and made a part of this specification and shown on the drawings.
SPEC WRITER NOTE: Specify safety sign for all projects when construction cost estimate is over $2,000,000, except where the work is such that a sign cannot be observed by the Contractor's personnel sometime during the working day.
01 00 00 -25
1.29 SAFETY SIGN
A. Provide a Safety Sign were directed by COR. Face of sign shall be 19 mm
(3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm
(four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with;
gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign showing required legend and other characteristics of sign is attached hereto and is made a part of this specification shown on the drawings.
E. Post the number of accident free days on a daily basis.
Estimated Cost No. of
Photographs
Up to $250,000 50 to 100
" " $500,000 100 to 150
" " $1,000,000 150 to 200
" " $2,000,000 200 to 250
" " $5,000,000 250 to 300
" " $10,000,000 300 to 400
More than
$10,000,000 400 to 500
1.30 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications. The commercial photographer or the subcontractor used for this work shall meet the following qualifications:
01 00 00 -26
1. Demonstrable minimum experience of three (3) years in operation providing documentation and advanced indexing/navigation systems including a representative portfolio of construction projects of similar type, size, duration and complexity as the Project.
2. Demonstrable ability to service projects throughout North America, which shall be demonstrated by a representative portfolio of active projects of similar type, size, duration, and complexity as the
Project.
B. Photographic documentation elements:
1. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing
200x250mm (8 x 10 inch) prints with a minimum of 2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.
2. Indexing and navigation system shall utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.
3. Documentation shall combine indexing and navigation system with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones.
Documentation shall be accessible on-line through use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, on-line.
4. Before construction, the building pad, adjacent streets, roadways, parkways, driveways, curbs, sidewalks, landscaping, adjacent utilities, and adjacent structures surrounding the building pad and site shall be documented. Overlapping photographic techniques shall be used to insure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings. If site work or pad preparation is extensive, this documentation may be required immediately before construction and at several pre-determined intervals before building work commences.
01 00 00 -27
5. Construction progress for all trades shall be tracked at pre-determined intervals, but not less than once every thirty (30) calendar days (“Progressions”). Progression documentation shall track both the exterior and interior construction of the building.
Exterior Progressions shall track 360 degrees around the site and each building.