6645-26 RFP -CSO 24 26 Storage and Springfield Lift Station SCADA Upgrade.pdf

PDF 450 KB Posted

Attached to
RFP CSO 24, 26 Storage and Springfield Lift Station SCADA Upgrade
Solicitation number
RFP 6645-26
Issued by
Spokane County, Tacoma City, Washington

About this file

This Request for Proposals (RFP #6645-26) is issued by the City of Spokane, Washington, through its Integrated Capital Management Department, seeking qualified firms to design, program, and implement a Supervisory Control and Data Acquisition (SCADA) system upgrade for CSO 24, CSO 26 storage facilities, and Springfield Lift Station. The project involves a second phase implementation of PlantPAx SCADA monitoring and control systems utilizing Rockwell Automation technologies, with services including system design, PLC programming, HMI development, network infrastructure, security implementation, testing, training, and comprehensive documentation. The RFP coordinator is Connie Wahl of the City of Spokane Purchasing Department. The deadline for submitting questions is Monday, November 23, 2026, at 11:00 a.m., and proposals are due electronically through the ProcureWare portal by Tuesday, December 29, 2026, at 11:00 a.m. Contract award is anticipated in January–February 2027, with work commencing March–April 2027. The contract period is for one year, renewable for an additional six-month period or longer upon mutual agreement, with performance-based payment phases contingent upon completion of defined project milestones and operational functionality verification.

Proposers must meet minimum qualifications including three years of experience in PlantPAx system design, construction, implementation, configuration, and programming, plus three years in wastewater management. Required certifications include Rockwell Silver Level System Integrator ranking, current PlantPAx badged integrator certification, Rockwell Automation Control capability badge for PLC panels, and Rockwell Automation Visualization capability badge for FactoryTalk ViewSE, along with valid UL 508 certification for panel fabrication. The cost proposal shall provide fully detailed budgets broken into specific categories: system review, design, component replacement, commissioning, PlantPAx programming, installation with testing, post-implementation modifications, training, travel, documentation, and final acceptance. Proposers must separately estimate costs for all new SCADA system components, software licenses, and annual subscriptions, as well as provide ongoing support rates and maintenance agreements. The proposal evaluation employs a 200-point scoring system: Technical Proposal (40 points), Management Proposal (40 points), Experience (60 points), and Cost Proposal (30 points). The City has made available partial documentation from the initial pilot phase, including design drawings, control narratives, equipment inventory, PLC programming files, and preliminary standards; proposers must sign a Non-Disclosure Agreement to access sensitive project information and configuration details. Rockwell Automation will assign one Global Process Technical Consultant to provide advisory support and design verification at no cost to the City during the five-phase implementation process (PSE selection, preliminary design, design verification, project verification, and system registration for a "System ID").

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP #6645-26

11/11/2026

REQUEST FOR PROPOSALS

RFP NUMBER: 6645-26

RFP TITLE: CSO 24, 26 Storage and Springfield Lift Station SCADA Upgrade

RFP COORDINATOR: Connie Wahl, City of Spokane Purchasing Department

QUESTION DEADLINE: MONDAY, NOVEMBER

23, 2026 TIME: 11:00 A.M.

PROPOSAL DUE DATE: TUESDAY, DECEMBER 29,

2026 TIME: 11:00 A.M.

PROPOSAL SUBMITTAL:

All Proposals shall be submitted electronically through the ProcureWare online procurement system portal:

https://spokane.procureware.com by the due date and time.

All questions shall be submitted through the ProcureWare ‘Clarifications’ tab.

TABLE OF CONTENTS

1. GENERAL INFORMATION

1.1 COMMUNICATION

1.2 BACKGROUND AND PURPOSE SUMMARY

1.3 MINIMUM QUALIFICATIONS

1.4 CONTRACT PERIOD

1.5 ADDENDA

1.6 TERMS AND CONDITIONS

1.7 ESTIMATED SCHEDULE OF PROCUREMENT ACTIVITIES

1.8 DEFINITIONS

2. SCOPE OF SERVICES

2.1 DESCRIPTION

2.2 SCOPE OF SERVICES SUMMARY

2.3 SI REQUIREMENTS

2.4 GENERAL AND ROCKWELL AUTOMATION PROJECT REQUIREMENTS

2.5 PROJECT MANAGEMENT

2.6 SCOPE OF WORK AND PHASING

3. PROPOSAL CONTENT

3.1 PREPARATION OF PROPOSAL

3.2 LETTER OF SUBMITTAL

3.3 TECHNICAL PROPOSAL

3.4 MANAGEMENT PROPOSAL

3.5 COST PROPOSAL

4. PROPOSAL SUBMISSION AND EVALUATION

4.1 SUBMISSION OF PROPOSALS

4.2 EVALUATION PROCEDURE

4.3 EVALUATION SCORING

4.4 AWARD/REJECTION OF PROPOSAL/CONTRACT

5. RFP ATTACHMENTS

CITY OF SPOKANE

PURCHASING &

CONTRACTS

915 N. Nelson St.

Spokane, Washington 99202

(509) 625-6400 https://spokane.procureware.com/

1. GENERAL INFORMATION

1.1 COMMUNICATION

For ProcureWare E-procurement system technical issues only and if the deadline for entering clarification questions has passed, contact Purchasing@SpokaneCity.org or call 509-6400. All other communication between the Proposer and the City of Spokane (hereinafter “City” or “COS”) shall be with the Request for Proposals Coordinator and submitted through the ‘Clarifications’ tab in the City’s online procurement system portal: https://spokane.procureware.com. Any communication directed to other parties is prohibited.

1.2 BACKGROUND AND PURPOSE SUMMARY

The City, through its Integrated Capital Management Department is initiating this Request for Proposals (hereinafter “RFP”) to solicit Proposals from Firms to provide CSO 24, 26 Storage and Springfield Lift Station SCADA Upgrade Services for a fully executable and operational SCADA system. The City is implementing a second phase of SCADA monitoring and future control Master Plan for the City’s CSO and lift station facilities. The SCADA functions include data acquisition, data historization, alarming, and security. A future SCADA project will include control function. The current SCADA system uses ethernet cables, fiber optic, and wireless network (WAN). Currently the remote sites in the pilot project are using CAT 5 cable or DSL with cellular backup. Fiber Optic communication exists between the Sewer Maintenance office and the CSO 26 Site. The goal is to utilize fiber as it becomes available near each site.

1.3 MINIMUM QUALIFICATIONS

The Firm and System Integrator (hereinafter “SI”)must have three (3) years of experience in each PlantPAx system design, construction, implementation, configuration, programing, to ensure a fully executable and operational SCADA system. SI must have a minimum of 3 years of experience in the Wastewater Management Industry. Documentation of items requested below shall be included in Proposal submittal. Reference Part 3 “Proposal Content”.

• The Firm and SI will have achieved, before Proposal submittal, a minimum Rockwell Silver Level System Integrator ranking and a current PlantPAx badged integrator certification or, per Rockwell Automation’s approval, be in the process of attaining a PlantPAx badge. Documentation shall be submitted with Proposal to support Integrators’ certifications or certification process milestones with Allen Bradley/Rockwell Automation and clearly identify key staff members with the above certifications and milestones that will be working on this project with the specific certifications and dates of when those certifications and milestones were completed.

• Provide documented proof of member status as a Rockwell Automation System Integrator Partner that will be permanently assigned to this project.

• Provide up-to-date training certificates for completed assessment associated with Partner Program badge capability (i.e. Control capability training, Visualization capability training, PlantPAx capability training) for staff to be assigned to the project.

• Hold a valid UL 508 certification for panel fabrication, modification and/or utilizes a subconsultant with UL 508 certification for panel builds.

• Have a current Rockwell Automation Control capability badge for PLC Panel mailto:Purchasing@SpokaneCity.org

• Have a current Rockwell Automation Visualization capability badge for Factory Talk ViewSE. This also includes FactoryTalk Security, FactoryTalk Policy Manager, FactoryTalk Historian, and FactoryTalk Asset Centre.

The City may consider non or below Rockwell Silver Level System Integrator Certification’s Proposal if the Proposer is in the process of attaining a PlantPAx badge, Rockwell Automation Control capability badge for PLC Panel, and Rockwell Automation Visualization capability badge for Factory Talk ViewSE.

If Proposal demonstrates that the Firm is willing to get the certification(s) through the development and completion of this project and with sufficient evidence provided to show a significant attempted badge obtainment and shown experience with successful PlantPax full control system installation and implementation. Reference Part 3 “Proposal Content” for documentation required to include to demonstrate sufficient evidence.

Note: In order to enter into a contract, the Firm must be licensed to do business in the State of Washington.

1.4 CONTRACT PERIOD

Any contract resulting from this RFP will be for a period of one (1) year. Contract is renewable for an additional six (6) month period or additional time if necessary and upon mutual agreement.

1.5 ADDENDA

It is the responsibility of Proposers to check the City’s online procurement system https://spokane.procureware.com for Addenda or other additional information that may be posted regarding this RFP.

1.6 TERMS AND CONDITIONS

Terms and Conditions applicable to this RFP and potential contract are included herein by reference and attached to this RFP as Attachment 1.

1.7 ESTIMATED SCHEDULE OF PROCUREMENT ACTIVITIES

Deadline for Questions 11/23/2026 – 11:00 a.m.

Proposals Due 12/29/2026 – 11:00 a.m.

Evaluation, Negotiation and Contract Award January - February 2027 Begin Contract Work March - April 2027

The City reserves the right to revise the above schedule.

1.8 DEFINITIONS

Definitions for the purposes of this RFP include:

AB – Allen Bradley Air Gap – Fully disconnected from other networks and without the ability to remote-in for licensing, monitoring, troubleshooting or configuring or be able to connect to the SCADA system through any other type of connection.

ANSI – American National Standards Institute City o r COS – The City of Spokane, a Washington State municipal corporation and the agency issuing this RFP.

https://my.spokanecity.org/administrative/purchasing/current-projects/

CIP Security – Common Industrial Protocol Security CPwE – Converged Plantwide Ethernet COOP – Continuity of Operations CSF – Cybersecurity Framework DCS – Distributed Control System DLR – Device Level Ring network topology used to allow ethernet devices to connect directly to neighboring nodes through dual network ports.

DMZ – Demilitarized Zone which is logical network segment that manages flow of information and defends against unauthorized access within internal and external networks. This is used specifically for interposing network between SCADA and WWW DR – Disaster Recovery DSL – Digital Subscriber Line EOL – End of Life dates EPA – Environmental Protection Agency FAT – Final Acceptance Testing or Factory Acceptance Testing FDS – Functional Design Specification Firm – Consultant, Joint Venture, Team, or Company including Sub-consultants.

FW – Firewall GNA – Grande, Novac & Associates Incorporated as usually referred to the wastewater flow control system GPTC – Rockwell Automation Global Process Technical Consultant Historian – database system that accumulates time stamped data and events and can be queried, exportable and used to populate graphic trends and reports into alternative software such as excel.

HMI – Human Machine Interface IEC – International Electrotechnical Commission IAB – Integrated Architecture Builder software which houses the PSE tool.

IEC – International Electrotechnical Commission Integrator or System Integrator (SI) – a person or company that is an expert in designing, installing, provide ease of operation and maintaining SCADA systems and their integrations with the existing and new control systems. The SI professional(s) ensure that the SCADA system works effectively and efficiently through optimized control system integrations with all its other control systems, whether it involves industrial automation, safety systems, or remote monitoring tools.

I0 – Input/Outputs communications within the modules ISA – International Society of Automation NAT – Network Address Translation NDA – Non-Disclosure Agreement NIST – National Institute Standards and Technology NPDES – National Pollutant Discharge Elimination System. The NPDES permit program addresses water pollution by regulating point sources that discharge pollutants to waters of the United States. Created in 1972 by the Clean Water Act, the NPDES permit program is authorized to state governments by EPA to perform many permitting, administrative, and enforcement aspects of the program.

OIT – Operator Interface Terminal O&M Manuals – Operation and Maintenance Manuals OTDR – Optical Time Domain Reflectometer for fiber optic testing PASS – Process Automation System Server (PASS) is a pre-installed PlantPAx Virtual Image Template that provides centralized administration, name resolution and HMI/Alarm/etc.

PLC – Programmable Logic Controller

Proposal – A formal offer submitted in response to this solicitation.

Proposer – Individual or Firm submitting a Proposal in order to attain a contract with the City.

PSE Tool – Rockwell Automation Process System Estimator Tool Request for Proposals (RFP) – Formal procurement document in which a service or need is identified but no specific method to achieve it has been chosen. The purpose of an RFP is to permit the consultant community to suggest various approaches to meet the City’s needs at a given price or negotiated price.

RPWRF – Riverfront Park Wastewater Reclamation Facility SAT – Site Acceptance Testing SCADA – Supervisory Control and Data Acquisition SOE – Sequence Of Events SI – Integrator or System Integrator VFD – Variable Frequency Drive for pump motors VLAN – Virtual Local Area Networks WWC – Wastewater Collection WWM – Wastewater Management

2. SCOPE OF SERVICES

2.1 DESCRIPTION

The City of Spokane has completed a Wastewater and Stormwater Collection System SCADA Master Plan (Jacobs May 17, 2019). The SCADA system will be designed and implemented in phases; the portion of the project consists of a pilot phase which includes two CSO facilities, two or more flow monitoring locations, and one lift station. The ultimate goals for the Wastewater and Stormwater System are:

• To provide an isolated and air-gapped SCADA computer system and control center, operated from the City’s Wastewater Collection facility,

• Provide secure communications network, using the best industry network and cyber security practices,

• Implement monitoring site locations along the City’s main sewer interceptor and within the sewer facilities,

• Real-Time monitoring at the City’s major CSO facilities,

• Real-Time monitoring of the City’s major sewer and stormwater lift station facilities,

• Provide conditions for control through the SCADA system in the future, and

• Providing facilities the ability to maintain limited functionality with graceful degradation even if there is a SCADA system failure or the loss of SCADA control.

o An example for fiber optic backup communication for the fiber section that is located at City Hall if City Hall loses power; two alternative fiber optic routes could include RPWRF or CSO 26 for a disaster recovery site with limited servers.

The first phase of the CSO 24-1, 26, and Springfield lift station pilot SCADA project has been completed but there is still a significant amount of work remaining for these facilities to become operationally controlled by SCADA and staff.

General items and documentation that can be provided (although it may be partially complete record) once a Non-Disclosure Agreement (NDA) is signed with the COS (The NDA is included in Attachment 3). The COS has made its best efforts to ensure accuracy with limited resources of these documents, and it is not guaranteed of the accuracy or completeness of the resources. Validation is required initially and through the continuation of the project. The configuration files, IP addresses and passwords will be provided after the contract is awarded.

• Design or record drawings of the three facilities when the CSO and Lift Station facilities were constructed

• Construction design drawings for the first phase of the pilot project with markups

• The process control narrative for CSO 24-1 and CSO 26 Facilities o Control adjustments made to control flow between CSO 24-1 and CSO 26.

• CSO 24-1 and 26 Grande, Novac & Associates Incorporated Flow Control Devices (GNA) O&M and the Pump Operation and Maintenance (O&M) manuals

• Partial O&M Manuals from the first pilot project

• Draft inventory hardware from multiple manufactures, chasey modules, PLCs, CIP Security, DLR

Rings, Modbus systems, gas detection systems and flow monitoring systems, network switches, programing and major electronics.

• List of data required to be collected within the historian and the list of required alarming trigger points within each specific location

• Network map of fiber optic communications through Spokane

• Availability, routes, and locations of fiber optic within the Spokane Area available for the project

• PLC programing files for CSO 24-1, CSO 26 and Springfield LS

• OIT Programing for CSO 26 and Springfield LS (not available for CSO 24-1)

• WWC Preliminary PLC Programing Standards

• WWC Preliminary HMI Application Standards

• WWC Preliminary Tagging Standards

• WWC SCADA security policies

• WWC System SCADA Master Plan (Jacobs 2019)

• Draft Spokane RPWRF SCADA Reference Task 4.1 FactoryTalk Memo (HDR 2021)

Assume no configuration and no programing for each of the components listed below was completed unless otherwise specified. The work completed in the first phase of the pilot project includes the following:

• CSO 26 Control Facility o Installation of PLC Aggregator panel cabinet with OIT screen and interior components which include two redundant PLCs with Historian modules, 2 Ethernet network switches, DLR Ring, and uninterruptable power supply.

o Installation of fiber optic communication and ethernet cable within the Facility o Replacement of Ethernet switch in Control Cabinet o Installation of Modbus Gateway for the flow monitor with the installation of the protocol converter (Universal Gateway ProSoft Equipment).

• CSO 24-1 Control Facility o Installation of Ethernet cable within facility for communication between the north and south PLC panels, between South Electrical Room PLC Control Cabinet and flow control panel, and between Service Room PLC Control Cabinet and hazardous gas detection panel o Ethernet network switch, DSL Modem, OIT screen, and uninterruptable power supply were installed in the South Electrical Room PLC Control Cabinet o Ethernet network switch installed in the north PLC Control panels o Installation of Modbus Gateway for the flow monitor with the installation of the protocol converter in South Electrical Room

• Springfield Lift Station o Partial OIT screen programing o Installation of the Ethernet switch, programing of the PLC module, and installation of the DLR and CIP Security Proxy modules for the VFDs.

o Replaced Motor Control panels with ones that have VFDs.

• Interceptor Monitoring Site o Spokane Falls Blvd and Post Street

Installation of control enclosure with breakout boards in flow monitoring cabinet.

Conduit installed for flow monitoring sensors to I06 Interceptor (manhole 0600142CD) (Future capital project planned for 2028.)

Site as flow monitoring capabilities which the data is sent via cellular.

Modbus gateway with cellular security appliance installed o Chestnut and Bridge Installation of Control Enclosure with break-out boards.

Conduit from power and control enclosure to I02 Interceptor (manhole

0204072CD)

Site as flow monitoring capabilities which the data is sent via cellular.

Current Plan: Modbus gateway with cellular security appliance to be installed by

City.

• Wastewater Management/Collection/Sprague Office o Servers and switches are installed o Connection of WWC Office to remote sites

Security appliance with modem and cellular backup o Fiber from CSO 26 is connected to the Ethernet switch at WWC Office.

• City Hall SCADA Cabinets o Fiber optic communication was installed as a pass through and not with a breakout board.

2.2 SCOPE OF SERVICES SUMMARY

The scope of services to be performed by the Firm and described in the RFP in general and specifically in this Part 2 “Scope of Services” includes , but is not limited to, the following paragraphs.

2.3 SI REQUIREMENTS

The SI will have knowledge and understanding of the key tools and documentation that are part of PlantPAx system design, construction, implementation, configuration, programing, and exhibit the knowledge to ensure a fully executable and operational SCADA system. The SI will be the same SI until completion of the project unless replaced with an SI with a documentable equal or higher skill level.

The SI and supporting staff shall have the following qualifications:

• SI shall have the minimum qualifications to complete the standard processes and procedures for developing a PlantPAx project within the current release of the software.

• The control system project delivery integrator shall be regularly engaged in the design and installation of the whole system and subsystems.

• If updates occur, provide updated training certificates for completed assessment associated with Partner Program badge capability (i.e. Control capability training, Visualization capability training, PlantPAx capability training) for staff to be assigned to the project.

• Must understand, provide and explain/train on maintenance requirements for the network, equipment and PlantPax.

• The SI shall have the ability to use the PlantPAx Process System Estimator (PSE) tool within the Integrated Architecture Builder (IAB) software.

• Preferably other relevant Rockwell Automation badges in addition to list in Paragraph 1.3 “Minimum Qualifications” including, but not limited to, Low Voltage Drives, etc.

• Must understand the interconnectivity of the Rockwell suite of products and how to tailor those products within the City’s wastewater environment. This also applies to cyber security standards and to include a minimum of Environmental Protection Agency (EPA) designation security first level. The SI must have a fundamental understanding of, able to practically apply the following standards, and experience in implementing the following technologies and how these technologies, standards, security systems, networks, etc. affect each other within the network.

o International Standards of Automation (ISA)/ International Electrotechnical Commission (IEC) ISA/IEC 62443 Standards.

Specifically, the 7 fundamental requirements to apply to and benefit the City’s

SCADA environment.

o The SI must understand Internet Protocol Security (IPSec) and Media Access Control

Security (MACSec).

o Understanding of EPA Guidance on Improving Cybersecurity at Drinking Water and

Wastewater Systems.

o It is crucial to maintain compliance within the City’s National Pollutant Discharge

Elimination System (NPDES) permit regulations. Specifically, to ensure compliance by not triggering a combined sewer overflow on land or to the river during this project.

o The SI must have familiarity with National Institute Standards and Technology (NIST) Cybersecurity Framework (CSF) (2.0 is the most current as of the writing of this RFP) and make efforts to comply with these standards as much as possible.

o Even though SCADA / Purdue Model/ Converged Plantwide Ethernet (CPwE) is not a typical deployment, it will be important to understand the basics of how these systems/models work o The SI must have familiarity with the following:

Device Level Ring (DLR) Common Industrial Protocol (CIP) Security / FactoryTalk Policy Manager Device hardening best practices Virtual Local Area Networks (VLANs) / Network Segmentation Network Address Translation (NAT)

At the conclusion of the project, COS will seek to ensure Rockwell Automation’s PlantPAx proper system design and deployment requirements are met by:

1. Completion of the PlantPAx Verification Tool found in the PlantPAx DCS (Distribution Control System) Configuration and Implementation User Manual and create a system that passes verification.

2. Register the PlantPAx system with Rockwell Automation by obtaining a PlantPAx “System ID.”

2.4 GENERAL AND ROCKWELL AUTOMATION PROJECT REQUIREMENTS

The selected SI will be tasked with replacing an existing air-gapped Factory Talk HMI system, software, servers, PLCs, etc. with a new Allen Bradley/Rockwell PlantPAx system. These specifications describe the implementations and the expectations of the new system.

• The SCADA system shall be designed, programmed, and made operable with the most current version of Rockwell Automation PlantPAx Distributed Control System programing for this project.

• The SI shall engage Rockwell Automation for advisory support on the use of the PlantPAx Process System Estimator (PSE) tool as necessary within the Integrated Architecture Builder (IAB) software. Rockwell Automation will provide one Global Process Technical Consultant (hereinafter “GPTC”) to review the SI’s Process System Estimator (PSE) tool application for validation. The GPTC will also be required to sign a Non-Disclosure Agreement before working on this project. The SI is responsible for developing and documenting the system verification and design plan to be provided to the COS. The SI will complete the application and architecture completed and available for review at the meeting with COS. After sign-off from the COS, the SI will provide all information required to the GPTC for verification. COS and GPTC verification are required completed prior to software and hardware acquisition as discussed below.

• The Rockwell Automation distributor and the GPTC will advise the SI on use of the tool estimator tool upon request. The GPTC will review and validate the architecture drawings for compliance with the Converged Plant Wide Ethernet standards (CPwE), PlantPAx Reference Manual, Selection Guide, Application Configuration User Manual, and Quick Start Guides.

o The SI will review the verification checklist with the GPTC the Project Validation phase.

This phase shall be completed prior to software and hardware acquisition. This verification checklist will be submitted during the final phase as project verification in order to document the design and configuration is done to standard.

o The SI, under the advisement of Rockwell Automation and the use of the PlantPAx PSE tool, shall provide the COS with design specifications in alignment with PlantPAx System deployment guidelines, each within the specific phases and include the PSE tool file. The SI shall consult with Rockwell Automation in developing the points below; Note: See Attachment 2: “City of Spokane (COS) Phase I, II, III and IV PlantPAx design and Rockwell Automation verification process with further document processing details.”

Phase 1 - PSE Selected System Elements and Sizing Guidelines Phase 2 - Confirm and Modify Preliminary Software/Hardware Design Phase 3 - Design Verification Phase 4 - Project Verification and Project Function Phase 5 – Submittals and “System ID”

• At the conclusion of the project, the SI shall submit all required documentation and files to COS and Rockwell Automation. COS will leverage these materials in-turn by asking for them to be reviewed by Rockwell Automation for the purpose of confirming alignment with PlantPAx system guidelines, but this review by Rockwell Automation does not constitute approval of the design. Formal verification and approval must be obtained from the COS.

• This project must receive a Rockwell Automation “System ID” in which Rockwell Automation will provide after review completion and approval.

2.5 PROJECT MANAGEMENT

• The project team (outside of the COS) shall treat system details as confidential and will be required to sign the NDA confidential agreement as shown in the attachment for the supporting RFP documentation but also for all future work as it is generally described within this document and within the future contract.

• The COS technicians shall not be locked out of any application implemented. COS technicians must be able to modify operations (at a minimum allowing “faceplates” on top of original controls to modify the control).

• The SCADA control plan must function in the field as intended by COS staff and as described within associated documents that describe the full functionality of the system to include but not limited to network communication, fail safe measures, security measures, automated, manual and offline control functions, alarming systems, and data collection, reporting and storing systems.

• Remote sites should be able to maintain local control and functionality including data logging if there is a loss of external network connections such as to the Aggregator PLC or servers at Sewer Maintenance.

• The existing control system must not be interrupted without COS staff oversite and only done for short durations to ensure that no wastewater flow will overflow to the river as a result of adjustments or implementation of the SCADA system.

• Identify and implement fiber or other backup and failover systems for network communication, continued control and real-time monitoring to supplement AutoDialer systems.

• Network design foundation and expansion of design and associated programming will be based on the ability to expand to other CSO facilities or Lift Stations into the future efforts.

Additionally, design foundation, functionality and programing will consider future facility operational control at the WWC Office HMI site design and programing considerations will be considered within the project with the ability to provide real-time data review.

• In initial phases of the project, a review of existing physical system and documentation of the existing entire SCADA system and functionality to confirm accuracy of existing documentation and provide necessary corrections or completely new data files.

• Provide design, networking and operational modifications as a result of field discoveries to ensure a fully functioning SCADA system.

• Any public works construction required will be performed by the City or done as a separate solicitation process and contract. Firm will provide oversight of any construction done to ensure it is done properly.

• Provide exhaustive system testing and debugging services as required prior to and after any of the phases of work have been completed, and before and after approval of work have been completed. A phased testing and debugging review process system shall be generated to confirm each progressive step was successful.

• Provide recommended system and historical data backup, restoring capabilities and procedures and provide actions required for a completely restorative system as the project progresses.

• Implementation of security upgrades with device hardening, network segmentation, CIP security, IPSEC, MACSEC, device hardening and other recommendations with penetration testing. Implementation of EPA’s Level 1 security measures and doc recommendations to implement EPA’s Level 2 security measures.

• Identifying procurement of additional equipment, software, specialists’ support and licensing required for the project including design, development, configuration, operation, and maintenance of the system. Provide a detailed list for the City to manage and purchase these items. Additionally, advise the City on specific software and programing licenses in which the City should acquire to review and manage this project’s systems.

o The City Staff to be responsible for purchasing equipment, software and licensing based on identified procurement list.

o The Firm is responsible for installation, setup, and configuration of equipment and software to meet requirements and functionality of system.

o The Firm to be responsible for purchasing equipment and all others as backup to the City when the City is unable to purchase but still requires the approval of the purchase by the City before the purchase.

o If Firm mis-recommends or miss-identifies equipment/software/other for purchase, then they shall be responsible for those costs accrued if the items are unable to be returned at fully accrued costs.

• Provide all installation, configuration, networking creation, adjustments, administration and functionality of the SCADA system with PlantPAx.

• Provide CAT 5/6 testing and fiber optic OTDR testing as required to ensure a complete and uninterruptible network connection and document results.

• Continuously update and track design and field changes and associated records throughout the project.

• Identify roles and responsibilities for all parties at each stage and phase of the project.

• Coordinate and manage bi-monthly meetings to ensure continued and effective progression of the project.

• Identify any assumptions made within the response to the RFP.

• Provide all exhaustive documentation as described throughout the RFP.

• Turnkey delivery with a fully operational SCADA system that is trackable, modifiable, with all hardware operable, and fully recoverable with the latest firmware within the hardware as of the date of commissioning.

• Firm and SI including subconsultants shall follow COS and WWC SCADA policies related to security. City IT Departments will be involved in several stages of this project.

2.6 SCOPE OF WORK AND PHASING

The next phase of the pilot project scope of PlantPAx programming SCADA system implementation includes:

PREPARATION FOR PROJECT PROGRAMMING

• Review the current design, construction, complete a comparison of record drawings and partially complete list of the equipment, PLC, rack, modules, drives, switches, overloads, etc., including configuration, Network, logic and loop descriptions, programming, and networking “blueprints” to actual field conditions and update all types of records as required and confirm status.

o Compare and update existing and partially complete record drawings, inventory lists and other documentation as required by the project.

o Review of proposed historian data lists and alarm list vs current physical and control systems to confirm ability to implementation of listed alarms.

o SI shall review existing network and programming to find shortfalls

• SI shall review, with the COS, the control system functionality for the entire pilot study project to fully identify how the overall system and each individual system will operate within several fail-safe scenarios within the development of the project with incremental project phased goals. This is where the SI will familiarize themselves with wants and demands of the project and the COS staff, how the facilities will operate, and how the COS will expect to operate the facilities into the future. The control system functionality, historian data collection, and alarming system documentation will be updated at this stage and receive concurrence before the next phases of the project are initiated.

• SI shall review existing network, security, PLC programming and compare to the control system functionality to develop updated baseline functionality for new programming. New programming shall include improvements to:

o Cyber-security/CIP protection/data encryption o Automatic failover and system data collection o Networking connectivity improvements o Command/response priority levels o Increased scan rate and/or multi-scan options o Increased system data transmission

• SI shall conduct final onsite testing, field investigations and prepare findings reports.

o Confirm any additional hardware requirements as part of this project.

o If SI finds that a component of existing system is functionally incompatible with the upgrade, the SI shall make recommendations for replacement and notify the City Staff for the additional purchases required.

o Connect or ensure connection of pump controls, GNA controls, hazardous gas and flow monitoring data to the PLC and Historian

• Discuss preliminary software and hardware design o Review any requests from the COS or SI that may affect the performance, stability and supportability of a PlantPAx system.

o Discuss development steps, work plan(s) and what needs to be completed.

o Identify PlantPAx engineering workflow and the documentation that will be developed to be used to configure each device during software development.

o Identify key responsible parties from COS, selected Firm, Rockwell Automation and

Distributor resources for required support throughout the project. Anything that is not within the PlantPAx documentation or is not clear should be discussed with the various identified resources during cadence calls with COS.

o Review and identify best management project and infield implementation practices for design, networking, implementation, operation and security.

o System design shall be based primarily on standardized PlantPAx templates whenever possible. Custom templates (or face plates) are permitted only when standard templates are unavailable. Custom templates shall allow the ability to make changes to the template, which will then be able to propagate throughout all instances where that template is used. No customization shall be made to the Library of Process Objects faceplates or global objects. If required, customization to objects or faceplates will be made to copies, and not the original objects. Identifiers must be placed on faceplates to identify which are customized when future upgrades occur.

o System must utilize the Rockwell Automation library of process objects for a characterized system, utilize ISA 18.2 and 101 standards for alarm and grayscale HMI. Also, the alarming program design must follow Rockwell Automation suggested methodologies and the project organization follows the process organization and not the technology segmentation.

o Discuss and select the basis for HMI/OIT visualizations, operator interface, and the basic adherence, as close as possible, to a common or shared template between sites and their screens; system functionality, programming, data management, and control of equipment with City Staff.

o PlantPAx programing standards should also follow WWC’s standards for options obtained from the PlantPAx symbol libraries for objects and screen options to maintain coherency throughout the Wastewater Operations.

o Discuss and finalize the Historian data that will be captured.

o New system must be configured and have the ability to display, save and print custom trend charts with multiple variables and as described in the Report Section.

o Discuss and select solutions for how SCADA alarms and notifications will be sent to staff (email, text, voice).

• Allow for Rockwell GPTC review to verify that the project at Rockwell Automation’s required incremental phases as identified by Rockwell and within Attachment 2.

• Provide field and functional testing for the first phase of the pilot project and continuing phases of the next phase of the pilot project and as described in the Testing Section below.

o Provide offline testing prior to field and in the field online testing.

• Provide site refinement, additional installation of equipment, design, recoding, networking refinement and programing as needed to fully complete the pilot project o Design/Implement backup communication for the section of fiber between Sewer Maintenance and CSO 26.

Plan for two alternative locations, include RPWRF or CSO 26 for a disaster recovery site and system with servers if the communication at Sewer Maintenance is lost or its equipment goes down.

o Engage with Rockwell Automation to jointly provide COS a plan to document system characterization and design of the system before acquisition of additional control system software and hardware and throughout the project as required. Engage with Rockwell Automation for advisory support and review of design-related decisions throughout the project. The SI shall consult with Rockwell Automation when developing a documented plan for system characterization and design prior to the acquisition of additional control system software and hardware. Provide municipal COS with manufacturer compliance validation, factory acceptance testing (or field functionality testing confirmed by Firm) and specification documentation at the conclusion of the project, with all submitted files required for manufacturer validation.

o The new SCADA system control and programing systems shall meet the following design specifications:

The SCADA system shall be the basis for HMI visualizations, operator interface, and the basic current standard of the screens; system functionality, programming, data management, and control of equipment.

Modifications should be implemented as they become the new “basic standard” SCADA system implementation shall provide successful data and tag conversion from the existing system. Tags should follow the current WWC SCADA Standard tagging documents.

New system must be configured and have the ability to display, save and print custom trend charts with multiple variables and as described in the Report Section.

o List of recommended spare parts including manufacturer, model, and quantity.

o Update inventory lists per location

Include type of equipment, date of purchase, life cycle expectance, field location, manufacture, model and serial numbers, firmware version, network configuration (including existing and new IP addresses, subnets, gateway, VLANs, and NAT), usernames and passwords, etc. for each site o Develop individual checklists for each of the following and at each site as needed that: verifies components at each location, o verifies configuration for each server and workstation, o verifies the network connectivity, o verifies the applications hosted on controllers and completed for each controller, o verifies operational functionality, and o verifies documentation of efforts, equipment mapping, and operational and controlling logic, etc.

• Initiate efforts to collect, modify, create, update and provide all-inclusive documentation and as described in the Documentation Section below but not limited to.

PROJECT PROGRAMING AND COMMISSIONING

• The SI shall provide on premises Active Directory services for SCADA user access and permissions. WWC IT/OT SCADA manager, SCADA administrators, and instrument technicians shall have full access to specify permissions for all users. The SI shall provide on premises Active Directory services for SCADA user access and permissions.

• The SI shall confirm that the City has their own software access with City owned licensing for all software and tools used in the development of programing, reviewing, commissioning, testing, and beyond after project completion.

• The SI shall review the existing SCADA system and develop a strategy for migrating data, tags, HMI layout/visualizations, communication protocols, and data transfer limitations, into the new SCADA system control.

• The SI shall configure all necessary components required for the project completion in preparation of the PlantPAx SCADA Control programing.

• The SI shall develop a new SCADA system control, integrating: data, tags, HMI layout/visualizations, communication protocols, and PLC data transfer, from the existing SCADA system while incorporating input from City Staff. The SI will:

o Review pre-bid system details for additional specifications.

o Update/Replace all Input/Output channel tags to follow WWC SCADA and PlantPAx

Standards The selected transmitting communication is “tags for producing and tags for consuming” o The SI shall work with City Staff to implement new HMI functionality and visualizations.

The SI is expected to do most of the work off site before delivering a mostly configured system. Functional reviews will take place periodically as stated in the implementation plan, and at key milestones in the project such as agreed upon with the Firm and the COS. When the system is ready for deployment the SI shall be onsite for a minimum of three days (24hrs) per week to review progress and incorporate any changes necessary in programming if the travel, room and board expenses are greater than $500.

• The SI shall complete the remaining PlantPAx programing for the installed systems; HMI, OITs, PLCs, switches, historian, Modbus gateways for flow monitors, hazardous gas detectors, control systems, alarming systems, etc. and install programing o The SI shall be responsible for developing new programming, downloading into PLCs, performing bench tests, and preparation for deployment.

New programming for these PLCs will be unlocked and fully available for City

Staff.

SI and/or the Firm will use AssetCentre to check in and manage new versions of programming or configuration files before being downloaded or deployed to equipment.

o Programing to incorporate the wastewater mechanical GNA components and functionality, odor control, hazardous gas monitoring, pump and motor status, generator status, HVAC status, ISCO flow monitoring system on and off site, telemetry status, power status, door/hatch status, network status, and loss of communications status.

PLCs must retain ability to provide localized zone management for relevant site physical system controls for the CSO and lift station facilities and all their control combinations

Program shall provide for enhanced cyber-security/CIP security Program shall provide for increased data throughput, confirm scan cycles, enhanced data points o Recommend and help the City select, replacement and migrate existing servers.

o Recommend and plan for DR backup site and equipment o Review configuration and coding and update as needed for all methods of alarm annunciation and communication of alarming or notifications. (HMI, Texts, Voice Calls, and/or Email) o Review configuration and update configuration for Historian modules for all sites and ensure communication from the aggregator PLC collects and displays information to the WWC HMI location.

o Identify where coding and programing resides for each component such as in the local PLCs or the aggregator PLC or within the servers of at the WWC office location.

• The SI shall complete the network so that it is in a fully functioning state where all sites are securely connected through the network and that the network can support the needs of new SCADA system. This will include installation, configuration, and/or replacement of components, cables, and equipment needed to get function networking within and between each site. The network shall have the ability for the City to control which devices can connect through the network to devices at other sites. This control should be through software configuration of the network equipment. Only designated City owned SCADA devices should be allowed to connect to the SCADA network. For security reasons the SCADA network should not allow any outside connections to the SCADA network.

• The SI shall retain the current ability to function solely in an "Air Gapped" or "Dark Site" environment. The new SCADA system shall not require an outside connection for design, development, operation, maintenance (including updates), administration, configuration, or repair either during or after the implementation.

o SI shall acknowledge that the availability of the SI to be onsite for downtime or repairs is critical for safety and security of the City of Spokane’s infrastructure and is expected by the COS.

• The SI shall include a testing environment or “sandbox” to design new screens/features in and the ability to test them before publishing them into the live system.

• Allow Rockwell GPTC to review and verify that the project:

o Distributor and the Rockwell GPTC resources will be available within a reasonable schedule request to advise the SI on the PlantPAx design standards upon request (10-15 working days).

• Plan for future fiber connections as the City continues to develop the fiber optic network system.

• Update all existing OIT screens to meet HMI/Tagging standards and add additional functionality as needed.

• Site specific tasks required during the second phase of this project for each site:

o CSO 26 Control Facility

Update the SCADA PLC, Aggregator PLC, hazardous gas, sensors, GNA systems, MCCs, flow monitoring and Telemetry cabinets components for compatibility

Update with compatible Ethernet modules with the CIP security and DLR Configure CSO 26 SCADA PLC Stratix 5700 and Aggregator PLC Stratix Switch

5400, NAT, VLAN, IP address, modbus gateway, and username with passwords

Update SCADA PLC with alarming, data logging, produce tags for Agg PLC, and additional functionality.

Add ability for SCADA PLC to log and store historian data for up to a week when communication to Aggregator PLC or SCADA servers are lost. Data should be automatically uploaded to Aggregator PLC and SCADA server after communication is restored.

Program Agg PLC to consume tags and provide alarming and tags to SCADA servers along with other required functionalities.

Complete programing the OIT screens on the Aggregator Panel, SCADA Control Panel and Telemetry Pannel including modifying existing screens to meet standards and to add new screens as needed.

Plan for fiber communications between PLC cabinets to flow monitoring system cabinet at Spokane Falls & Post.

o CSO 24-1 Control Facility Complete programing the HMI screens on both the north and south SCADA

Control Panel, GNA cabinet panel, flow monitoring panels and hazardous gas detection panels. This work was not started or completed originally with the construction of the tank structure.

Update the SCADA PLCs, hazardous gas, GNA systems, sensors, MCCs, and flow monitoring cabinets components for compatibility.

Update with compatible Ethernet modules with the CIP security and DLR for both the north and south locations

Configure CSO 24-1 South SCADA PLC Stratix 5700 for NAT, VLAN, IP address, modbus gateway, and username with passwords

Update SCADA PLC with alarming, data logging, produce tags for Agg PLC, and additional functionality.

Add ability for SCADA PLC to log and store historian data for up to a week when communication to Aggregator PLC or SCADA servers are lost. Data should be automatically uploaded to Aggregator PLC and SCADA server after communication is restored.

Complete programing the HMI screens on both the north and south SCADA Control Panel, GNA cabinet panel, flow monitoring panels and hazardous gas detection panels. This work was not started or completed originally with the construction of the tank structure.

o Springfield Lift Station

Update the SCADA PLCs, hazardous gas, GNA, MCCs, and flow monitoring cabinets components for compatibility.

Switch to be enabled/configured for DLR, VLAN, IP address, Modbus gateway and username with passwords.

Confirm the completion of programing requirements through the HMI.

Confirm telemetry communication capacity to the appropriate locations.

Update SCADA PLC with alarming, data logging, produce tags for Agg PLC, and additional functionality.

Add ability for SCADA PLC to log and store historian data for up to a week when communication to Aggregator PLC or SCADA servers are lost. Data should be automatically uploaded to Aggregator PLC and SCADA server after communication is restored.

Enable and configure CIP security modules for VFDs o Wastewater Collections Management Office (WWC) Confirm and complete the physical setup of the HMI location as needed.

Update, setup and configure Rockwell software and VMs including

FactoryTalk View, FactoryTalk Historian, FactoryTalk Asset Centre, FactoryTalk Security, FactoryTalk Policy Manager, OWS App-Server, EWS App-Server, and other software that is identified by the SI or Firm for the project or for the operation, administration, or maintenance of the SCADA system.

Setup and configure version control in FactoryTalk AssetCentre for storing development and configuration files. SI and Firm should use AssetCentre for checking in/out file version for development and configuration throughout the project.

Programing all of the HMI screens for FactoryTalk View servers. The HMI screen interface will be used to review activities at each site in real-time as well as receive, acknowledge and shelve alarms. HMI screens should use standardized PlantPAx faceplates where possible.

Setup and configure SCADA system security including FactoryTalk Security, FactoryTalk Policy Manager, and other security software identified by the SI or Firm for the project.

Setup FactoryTalk Historian to record historical data as reviewed and accepted by COS and SI. FactoryTalk Historian should be able to automatically fill in gaps from historical data log and stored at remote sites after communication loss and/or SCADA system downtime once communication has been restored and/or SCADA system is functioning again.

Setup system for sending staff alerts/notifications (text, email, voice) based on rules for various SCADA alarms, alerts, or other types of notifications.

Programing for trend reporting of the historian data review as described in the Reporting section…