662-23-111 Const SOW_DRAFT.pdf
PDF 114 KB Posted
- Solicitation number
- 36C26126Q0458
About this file
This is a Statement of Work for Project 662-23-111 at the San Francisco VA Medical Center. The project requires a qualified General Contractor to repair and weatherize the single elevator in Parking Structure 211 and construct a vestibule to prevent future deterioration. The work scope is fully defined in attached construction documents, which include a combined drawing set, project specifications, and original construction documents for Parking Structure 211. The exterior construction work is located entirely within the footprint of Parking Structure 211.
The contract performance period is 180 calendar days. The contractor must use construction management software—either the government-provided Submittal Exchange platform or an alternative acceptable platform established by the awardee—and the government will grant access to all parties associated with the General Contractor as requested. The contractor is required to generate a Master Project Schedule that complies with VAAR 852.232-71, demonstrating critical path analysis, float identification, and costs organized by definable feature of work to enable timely and accurate progress payments.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26126Q0458.docx | DOCX document | |
| 662-23-111 Specifications_DRAFT.pdf | ||
| 662-23-111 Drawings_DRAFT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
San Francisco VA Medical Center
4150 Clement St
San Francisco, CA 94121
Project: 662-23-111, Repair and Weatherize Parking Structure 211 Elevator
Statement of Work
The San Francisco VA Medical Center requires the services of a qualified General Contractor to construct Project 662-23-111, Repair and Weatherize Parking Structure 211 Elevator.
The general scope of this requirement is to refurbish the single elevator from effects of weather and to construct a vestibule to limit further future deterioration. The nature and requirements of this construction are fully exhibited in the attached Construction Documents which include the following:
Bid Documents - Combined Drawing Set – This comprises the full drawing set as a single file.
Bid Documents - Specifications – This contains the entire project specification
Parking Structure 211 - Original Construction Documents
The exterior area of construction is located entirely within the footprint of Parking Structure 211.
Construction Management software is to be used in the completion of this requirement and will be provided by the government absent an established and acceptable platform utilized by the awardee. The software currently in use is Submittal Exchange. The government will grant access to all parties associated with the General Contractor as requested by the GC project manager.
The period of performance for this action is 180 calendar days. The contractor generated Master
Project Schedule shall meet the requirements of VAAR 852.232-71 to demonstrate critical path, identify float, and indicate costs by definable feature of work to facilitate timely and accurate progress payments.
File details come from the government source that posted it. Updated .