This Statement of Work outlines requirements for replacing an existing highline dock at Joint Base McGuire-Dix Lakehurst in New Jersey. The contractor must procure and install a new galvanized steel dock that is 48-50 feet in length with a minimum capacity of six pallets and total load weight of 80,000 pounds. The dock must have a roller deck, handrail, and be weather resistant. The contractor shall provide a dedicated project manager and complete delivery, installation, and demolition within 10 weeks of award. All work must be performed Monday through Friday between 7:30 am and 4:00 pm, excluding federal holidays and weekends, unless approved. The related solicitation was issued by the Department of the Air Force Air Mobility Command for this highline dock replacement at Joint Base McGuire-Dix Lakehurst.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions.docx | DOCX document | |
| Solicitation - FA448423Q0035.pdf | ||
| SFS Appendix - CONTRACTOR APPENDIX SEP 21.pdf | ||
| Medical Statement.docx | DOCX document | |
| JB MDL AT Awareness Guide for Contractors 1FEB22.pdf | ||
| JB MDL Antiterrorism Awareness for Contractors Trifold.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
621ST CRS
HIGHLINE DOCK INSTALLATION
JOINT BASE MCGUIRE-DIX LAKEHURST
1. General:
This Statement of Work (SOW) outlines the requirements and specifications for the procurement, installation, and warranty of a High Line Dock for the 621st CRS at JBDML, New Jersey. The purpose of this project is to replace the existing high line dock with an updated model that meets safety standards and enhances operational efficiency.
2. Scope of work:
The vendor will procure the highline dock and provide all necessary hardware, personnel, and equipment for the demolition of the old dock as well as installation of the new dock as well as being held responsible for the proper disposal of all packaging/crating materials and/or other waste generated in the unloading/installation of the new system and removal process of the old system.
3. Requirements:
A. The contractor shall provide a dedicated project manager who will oversee all aspects of the project, including procurement, installation, safety compliance, testing, and commissioning. The project manager will serve as the primary point of contact for communication and issue resolution.
B. Highline Dock Specifications:
a. Dock is required to be 48 – 50 feet in length
b. Capacity:
i. At minimum six (6) pallets
ii. Total load weight- 80,000 pounds
iii. Roller Deck
c. Handrail
d. Galvanized Steel with reinforced structure
Statement of Work (SOW)
e. Weather Resistant
C. 1 Year warranty on parts
D. 1 Year warranty on labor
4. Deliverables:
A. Completion of delivery, install, and demolition is expected within 10 weeks after award
B. All work must be performed Monday through Friday between the hours of 7:30 am and
4:00 pm. No work will be performed on weekends, federal holidays, JB MDL family days or before/after the hours specified on weekdays unless prior approval is granted