Limited Sources Justification Summary

This document is a Limited Sources justification filed by the Consumer Product Safety Commission (CPSC), Office of Procurement Services, for a sole-source contract award. CPSC awarded contract 61320627F0007 to EMCOR Government Services for specialized office renovations in the U.S. Government Accountability Office (GAO) building, with a total estimated value of $436,996.41. The justification cites FAR GSAR 538.7104-3(b)(1)(ii) and FAR 8.401(b) as the regulatory authorities for the sole-source procurement.

The contracting officer determined that only EMCOR is capable of providing the required renovations because EMCOR is the GSA contractor currently providing renovation services to the GAO building. Following competitive procedures would result in unacceptable delays. The pricing is deemed fair and reasonable under the Federal Supply Schedule Contract 47QSHA19D0044, with GSA having already determined these prices to be appropriate under FAR 8.404(d). The justification was signed by Ankur Patel, Contracting Officer, on November 12, 2026, and will be posted to SAM.gov within 14 days of award. The contracting officer certified the accuracy and completeness of the justification based on supporting data provided by technical personnel.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES

CONSUMER PRODUCT SAFETY COMMISSION

WASHINGTON DC, 20548

Limited Sources

FAR GSAR 538.7104-3(b)(1)(ii) (and FAR 8.401(b)

(i) This justification is for the Consumer Product Safety Commission (CPSC), Office of Procurement Services.

(ii) CPSC awarded 61320627F0007 to EMCOR Government Services, on a sole-source basis for specialized office renovations.

(iii) CPSC requires specialized office renovations in the U.S. Government Accountability

Office (GAO) building. The total estimated value of the award is $436,996.41 which includes the necessary renovations to prepare offices for employees.

(iv) Only one source is capable of providing the supplies or services required, following procedures would result in unacceptable delays. EMCOR is the GSA contractor that provides renovations to the GAO building. They are contracted to complete renovations.

(v) The contracting officer has determined that the order represents the best value consistent with 538.7104-3(b)(1)(ii). The price is deemed fair and reasonable based on Federal Supply Schedule Contract: 47QSHA19D0044 In accordance with FAR 8.404(d), the General Services Administration (GSA) has already determined the prices of supplies and fixed-price services under Federal Supply Schedule contracts to be fair and reasonable.

(vi) This justification will be posted to SAM.gov within 14 days of award.

(vii) The requirement cannot be modified to enhance competition, because the proposed contractor is the only one who can provide the renovations.

(viii) The contracting officer certifies that the justification is accurate and complete to the best of the contracting officer’s knowledge and belief.

(ix) Technical personnel who provided supporting data, which forms the basis for this justification have certified that the information is complete and accurate.

(x) The contracting officer has determined that the circumstances at FAR 538.7104- 3(b)(1)(ii) apply to this acquisition.

Ankur Patel Contracting Officer

2026-11-12T12:39:03-0500
ANKUR PATEL

File details come from the government source that posted it. Updated .