6100049681_Architecture & Preservation Project Manager_General Requirements.pdf

PDF 113 KB Posted

Attached to
Architecture and Preservation Project Manager
Solicitation number
6100049681
Issued by
Beaver County, Dauphin County, Allentown City, Harveys Lake Borough, Pennsylvania

About this file

This document is a Statement of Work for an Architecture & Preservation Project Manager contract opportunity issued by the Pennsylvania Historical and Museum Commission (PHMC). The contract requires the selected contractor to plan and manage preservation projects at historic sites and museums, including developing restoration or rehabilitation plans, overseeing construction projects, and providing technical assistance. The contractor must have a bachelor's degree in a relevant field and at least two years of experience managing historic preservation construction work. Bids are due electronically by 2:00 PM on January 24, 2020, and the contract term is 24 months with options to renew for up to three additional one-year terms. The contractor is required to submit bi-weekly invoices and may adjust the hourly rate by up to 3% annually for any renewal periods. The contractor must also obtain a criminal background check prior to starting work and coordinate access, identification, and working hours with the PHMC Project Manager.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

GENERAL REQUIREMENTS

1.1 PROJECT INFORMATION

Name: Architecture & Preservation Project Manager

Agency: PA Historical and Museum Commission Division of Architecture and Preservation

Project Manager: Joe Lauver

Chief, Division of Architecture and Preservation

Work Location: Commonwealth Keystone Building

400 North St., Plaza Room N118 Harrisburg, PA 17120

Issuing Office: PA Historical and Museum Commission

State Museum of PA, Room 529 300 North Street Harrisburg, PA 17120 Attention: Patricia Frey Telephone: 717-772-8875 Email: pafrey@pa.gov

1.2 BID QUESTIONS/BID ADDENDUMS

Questions are due to the issuing office via email to pafrey@pa.gov by 2:00 PM on Thursday, January 9, 2020. Answers to all questions and/or addendums will be posted to www.emarketplace.state.pa.us (click on “Solicitations”, enter Solicitation Number 6100049681 and click on “Search”) by 4:00 PM on Wednesday, January 15, 2020. No other questions will be permitted after this date. All questions and answers will become an addendum to the IFB (Invitation for Bid). The issuing office shall not be bound to any verbal information nor shall be bound by any written information that is not either contained within the IFB or formally issued addendums by the issuing office.

An addendum may also be posted if the issuing office deems it necessary to revise any part of this bid, will be posted to www.emarketplace.state.pa.us. It is the potential bidder’s responsibility to periodically check the website for any new or revised bid information or addenda prior to the submission of the bid. If an addendum has been issued, the bidder must print a copy of it, sign it and attach it to the bid response.

mailto:pafrey@pa.gov mailto:pafrey@pa.gov http://www.emarketplace.state.pa.us/ http://www.emarketplace.state.pa.us/

1.3 BID SUBMISSION

The bid submission is to be electronically submitted by 2:00 PM on Friday, January 24, 2020. Bidders must go to the www.pasupplierportal.state.pa.us to submit a bid. Mailed, faxed, emailed and/or late bids will not be accepted.

1.4 BID RESULTS

Bidders will be notified of the bid results by email and will also be posted to the eMarketplace website under “Bid Tabulations”. The results are the apparent bidders and all bids will be under review until the final award of the purchase order.

1.5 INFORMATION REQUIRED FROM BIDDER

To be considered, bids must respond to all requirements of the bid package. Any other information thought to be relevant, but not applicable to the categories below, should be provided as a separate attachment to the required bid information.

• Submit a letter and resume that details all academic training and work experience that meet the minimum qualifications listed in Section 2.3 – Required Experience, Training, & Eligibility. The letter must demonstrate a clear understanding of the tasks performed in Section 2.1 Description of Work and Section 2.2 – Essential Functions.

• Submit three (3) references, including names, street addresses, email addresses, and phone numbers.

• Complete the IFB document electronically by providing an hourly rate which does not exceed $55.00 and attach the letter, resume, and references with the bid electronic response.

1.6 BACKGROUND CHECKS

The selected contractor will be responsible for obtaining a Criminal Background check, at their own expense, on an annual basis while working under this contract. The Pennsylvania State Police Criminal History Check may be obtained at https://epatch.state.ps.us/Home.jsp. The contractor must provide copies of a certified, clear report that contains the Commonwealth seal. This report must be submitted to the Project Manager prior to reporting to the Keystone Building facility.

1.7 CONTRACTOR USE OF PREMISES/ACCESS/WORKING HOURS

The selected contractor must coordinate access to the site, identification badge, and working hours with the Project Manager. Work is to be completed during business hours, Monday through Friday. Alterations to the work schedule must have prior approval of the Project Manager.

1.8 PROJECT GUIDANCE

The selected contractor will work with the Chief of the Division of Architecture and Preservation. All aspects of the management of the projects will be coordinated with the Division Chief. The Division Chief will review and evaluate the contractor’s work on an on-going basis.

http://www.pasupplierportal.state.pa.us/ https://epatch.state.ps.us/Home.jsp

1.9 TERM OF THE PURCHASE ORDER

The term of the purchase order will commence on the Effective date indicated on the purchase order and will terminate 24 months from that execution date. The contractor shall not start the performance of any work prior to the Effective Date of the purchase order and the Commonwealth shall not be liable to pay the selected contractor for any service or work performed or expenses incurred before the Effective Date of the purchase order. Further, the Commonwealth has the option to renew this contract for up to three (3) additional consecutive one (1) year terms if both parties are agreeable. The same terms and conditions set forth in the initial contract will remain in full effect for all renewal periods. If the renewal option is exercised, the contractor may adjust the hourly rate each renewal period provided the rate is not increased by more than 3% annually.

1.10 CONTRACT INVOICING

• The contractor is to submit bi-weekly invoices for the hours worked the previous two week period.

• The invoice must include the contractor’s name, address, purchase order number, line item number, invoice date, days and hours worked, travel costs incurred during that time period with supporting documentation, and the total amount of the invoice.

• Invoices can be sent by mail to the address in the “Bill To” section on the purchase order or by email to 69180@pa.gov.

Electronic bid responses are due by 2:00PM on Friday, January 24, 2020.

mailto:69180@pa.gov

SECTION 2

PROJECT SPECIFICATIONS

2.1 DESCRIPTION OF WORK

Plan projects and submits to Chief of the Division of Architecture and Preservation. Apply a high level of professional expertise in evaluating the condition and integrity of historic structures and related features, and in developing restoration or rehabilitation plans, including drawings and specifications, for them in conjunction with the Site Administrator, other staff, consultants and the Chief of the Division of Architecture and Preservation.

Manage projects designed by DGS or outside architects and engineers serving as a representative for the agency throughout the design and construction phases.

Plan and manage assigned projects at historic sites and museums. Coordinate with site staff to minimize adverse impacts on the operation of the site.

Observe construction projects in progress to ensure conformance and compliance with the contract documents and with the Secretary of the Interior's Standards for the Treatment of Historic Properties (when applicable.) Conduct and attend job conferences and submit reports as needed for each project.

Coordinate with the Chief of the Division of Architecture and Preservation. Direct contractors to correct deficient work.

Provide technical assistance to site maintenance staff.

Incumbent is responsible to be familiar with PHMC general safety rules and safety rules specific to this position; for working in a safe manner and following all PHMC safety rules; immediately report all workplace injuries or incidents to their supervisor; and to immediately correct any safety hazards in the work area or report same to supervisor.

This work may require overnight travel.

2.2 ESSENTIAL FUNCTIONS

1. Prepare forms, memos, letters, and reports

2. Manage, organize, and file project records

3. Survey preservation construction needs

4. Formulate project work scopes

5. Communicate orally and in writing

6. Observe construction project in process

7. Travel for extended periods

8. Use computer and software normally used in the practice of Architecture (including CADD)

9. Utilize equipment, ladders, scaffolding and mechanical lifts to access roofs and other building areas for inspection

2.3 REQUIRED EXPERIENCE, TRAINING & ELIGIBILITY

A bachelor's degree in Architectural History, American History, Historic Preservation, or a similar field;

and two years of experience managing historic preservation construction work; or

Two years of post-secondary education and training in the above designated fields of study and four years of experience in historic preservation and construction which includes directly overseeing construction work; or

Any equivalent combination of experience and training that includes two years of experience in historic preservation and construction management.

STATEMENT OF WORK GENERAL REQUIREMENTS
1.2 BID QUESTIONS/BID ADDENDUMS
1.3 BID SUBMISSION
1.4 BID RESULTS
1.5 INFORMATION REQUIRED FROM BIDDER
1.6 BACKGROUND CHECKS
1.7 CONTRACTOR USE OF PREMISES/ACCESS/WORKING HOURS
1.8 PROJECT GUIDANCE
1.9 TERM OF THE PURCHASE ORDER
1.10 CONTRACT INVOICING