About this file

This is a Request for Proposal (RFP) issued by Dalton Utilities, a municipal utility in Dalton, Georgia, seeking engineering and architectural services for the design of a 60MW reciprocating internal combustion engine (R.I.C.E.) generation facility. The project involves designing a power generation facility with an initial capacity of 3x20MW generators and infrastructure to accommodate future expansion to 6x20MW generators. The facility will be located on Looper Bridge Road in Whitfield County, Georgia, and will include coordination of all infrastructure requirements, including a new onsite substation, building with administrative and operational spaces, parking, site survey, geotechnical studies, grading, stormwater drainage, sanitary systems, water supply, backup diesel storage, and natural gas pipeline interconnections. The scope encompasses Building Information Modeling (BIM) in Autodesk Construction Cloud format, design deliverables at 30%, 60%, and 90% completion stages with Rough Orders of Magnitude cost estimates, Factory Acceptance Testing, and all testing and commissioning services. Proposals must be submitted no later than 2:00 PM on Monday, February 2nd, 2026, to Mr. David Keaton, Director of Energy Services at Dalton Utilities. The proposed plant in-service date is January 1st, 2029.

Proposals are limited to 20 sheets and must include resumes of responsible Professional Engineers for each engineering discipline, a detailed estimate of hours, rate sheets, and a proposed schedule. Respondents must provide clarification requests in writing or via email to Mr. David Keaton at dkeaton@dutil.com, with all inquiries answered as addenda to the RFP. The project requires coordination with equipment manufacturers, utility interconnections, Factory Acceptance Testing for paralleling switchgear and ancillary systems, construction phase engineering support, and compliance with all local, state, and federal regulatory and environmental requirements. No specific pricing information, set-asides, incumbent contractor information, or funding sources are detailed in this RFP document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

60MW R.I.C.E. Generation Facility

October 28th, 2025

Request for Proposal:

Dalton Utilities is seeking engineering and architectural services to design a new power generation facility. The new facility will be designed and constructed to support full generation capacity of 6x20MW generators, whereas the initial capacity will be 3x20MW generators. The generators will be paralleled within an arc-resistant metal-clad switchgear lineup which will interconnect with a new substation for exporting. The new substation for export will be designed and constructed by Dalton Utilities, the prime engineer will coordinate the substation grading and drainage within the site development plans.

General Scope of Work:

The successful prime engineer will be required to:

1. Provide a Building Information Model (BIM) in industry standard format, for all systems being installed within the facility. This should include all electrical systems (to include conduits 0.75” and larger), piping, ductwork, and other systems required to be installed within the new building. The Model should be configured in a secure Autodesk Construction Cloud format for review during the design process by the Owner and/or Owner’s Representatives.

2. The project team should anticipate both remote and onsite team meetings for coordination purposes with Dalton Utilities.

3. Provide drawing packages, 30%, 60%, 90%, along with Technical Specifications.

Provide industry standard models, and files at each deliverable for Owner and/or

Owners Representatives review. In addition, providing Rough Orders of

Magnitude (ROM) cost breakdowns at all milestones as indicated.

4. Conduct all coordination with equipment manufacturer(s) for the specification of materials procured by the installing contractor, the Owner, or Others. Provide a matrix of equipment procurement and installation responsibilities during the design process for construction bidders.

5. Conduct all coordination for utility interconnections such as substation, ancillary power, sanitary sewer, water, natural gas, and pipeline requirements.

6. Design storage tanks for diesel fuel backup and assist with all required permitting for associated fuel supply.

7. Ensure the design meets all Local, State, and Federal regulatory and environmental requirements.

8. Provide all permitting assistance.

1200 V.D. Parrott Jr. Parkway * P.O. Box 869 * Dalton, GA 30722 * 706.278.1313 * 706.278.7230 Fax * www.dutil.com

9. Conduct all Factory Acceptance Testing (FAT) for paralleling switchgear, PLC, Generators, and Ancillary Systems required by the Owner.

10. Provide all testing and commissioning services during construction.

11. Provide project engineering construction support services.

Site Selection and Location:

Looper Bridge Road

Land Lot 14, 13th District, 3rd Section

Whitfield County, Georgia

Plant Configuration

The design team will be required to coordinate all infrastructure requirements for an initial (3) 20MW units with (3) 20MW future units within the facility. This should include building sizing, along with the infrastructure to support the future mechanical systems, electrical systems, controls, SCADA, fire protection, HVAC, and pipeline interconnections.

The site will be developed to accommodate a substation for transmission interconnect and building with parking sized for full capacity of the generation plant. This would include survey, coordination of all grading, storm drainage, sanitary, water, backup diesel storage, ancillary electrical, and ancillary natural gas. In addition, this would include coordination of all underground duct banks for full capacity of the generation plant to a substation located onsite, and pipeline interconnection.

Conduct all Geotechnical Engineering studies for structural designs.

The building will require the following spaces:

1. Offices

2. Open Offices

3. Server Room with raised floor

4. I.T. Room

5. Control Room with raised floor

6. Conference Room

7. Electrical Room

8. Mechanical Room

9. Laundry Room

10. Storage Room

11. Lavatories

12. Locker Rooms

13. Break Room

14. Warehouse Space

15. Maintenance Shop

16. Powerhouse

Process Description

1. Gas Supply

Pipeline interconnection by Dalton Utilities

Compressor and/or Regulator Station(s) requirements to be determined by

Design Engineer and implemented into the Construction Documents

Gas Interconnect to Generator(s) to be designed by the Engineer and implemented into the construction documents

Natural gas piping design to accommodate (3) 20MW future generators such that there is no interruption to the generation plant.

2. Power Generation

MAN V51/60G Gas Engine

3x20MW reciprocating internal combustion engine lineups

13.2kV output voltage

Generators to be paralleled on an arc-resistant metal-clad paralleling switchgear lineup for grid interconnection. Switchgear design and specification to be constructed such that it can be maintainable while under load.

Neutral grounding resistors

All ancillary systems, medium voltage connections, low voltage connections, Instrumentation & Controls, and SCADA systems.

3. Power output target:

Initial (3) 20MW units for a total of 60MW

Full capacity total of (6) 20MW units for a total of 120MW

4. Waste Management & Emissions Control

Emission reduction technologies (SCR, electrostatic precipitators).

Waste heat recovery systems.

5. Major Equipment Specification

Reciprocating internal combustion engine generator package to include all mechanical and electrical auxiliary systems

Fuel gas system

Exhaust systems including all ductwork and structural systems

Lube Oil Systems

Natural gas compressor and/or regulator stations

Cooling systems (air or water-cooled condensers)

Charge Air System

Oily Water System

NOx and CO Control Systems

Compressed Air Systems

Fire Protection Systems

Lightning Protection Systems

SCADA Systems

PLC, HMI, Instrumentation & Controls, and Remote Panels

Fiber Optic Cabling

Low Voltage Structured Cabling Systems

Medium Voltage Systems

Low Voltage Systems

DC/UPS Systems

Networking Equipment

Standby Black Start Generator and Automatic Transfer Switch

Server Room, I.T. Room, and Control Room Cooling Systems

Plant Electrification and Grounding

Cathodic Protection Systems

Sound dampening acoustics within generation plant

Fire Alarm Mass Notification System

Security Camera Systems

Access Control Systems

6. Civil & Mechanical Infrastructure

Site Survey

Geotechnical Engineering

Site development to accommodate a new substation, building, and parking lot

Foundations and structural design

Fuel and water storage tanks

Access for pipeline interconnections

Utility interconnections for sanitary, water, natural gas, and electrical

Stormwater

Gas interconnections to generators

HVAC systems design

Fire Protection System Design

7. Control & Instrumentation

Distributed Control System (DCS)

SCADA integration

Safety and alarm systems

8. Electrical Systems

Building power and lighting systems design and specifications

Ancillary power systems for generation equipment

Emergency Power Systems (Life Safety and Optional Standby)

Power Evacuation System

Generator Protection Relay Specification

Paralleling Switchgear Design and Specification

Power Systems Modeling and Studies in SKM Power Suites during the design phase such as:

o Short-Circuit Analysis o Protective Device Coordination o Neher-McGrath heat calculations for all underground ducts o Cable Pulling

Fire Alarm and Mass Notification Systems

Voice / Data Network Systems Designs

Lightning Protection Systems Design and Specification

Grounding Systems Design and Specification

Security Camera Systems

Access Control Systems

9. Environmental & Safety Considerations

Compliance with local environmental standards

Safety protocols and emergency shutdown procedures

10. Project Schedule & Cost Estimation

30% Construction Documents with ROM of +30%

60% Construction Documents with ROM of +20%

90% Construction Documents with Technical Specifications, and ROM of

+10%

Issued For Bid Documents

Issued For Construction Documents

A. Detailed Engineering Services

Detail Engineering includes completion of all Engineering related documents including preparation of detailed scaled drawings of the project stamped by a

Licensed Professional Engineer registered in the State of Georgia, preparation of project Specifications, preparation of any required permits, proposed budget estimate and schedule to act as a project baseline during bidding and construction execution, and a list of completed deliverables upon project completion.

Dalton Utilities will be heavily involved in the design decisions for the facility.

The Engineer should plan on several meetings with the Dalton Utilities

Operations and Engineering group to discuss progress and ensure the preliminary design is proceeding in accordance with Dalton Utilities’ expectations.

Please limit proposal to 20 sheets and include resumes of responsible Professional

Engineers for each engineering discipline described in the General Scope listed above.

Provide estimate of hours and a detailed rate sheet to perform the activities listed in the

General Scope. Also provide proposed schedule assuming the plant in service date is

January 1st, 2029.

Any clarifications on the project scope listed above must be submitted in writing or via email to:

Mr. David Keaton

Director of Energy Services

Dalton Utilities

1200 VD Parrott Jr Parkway / PO Box 869

Dalton, GA 30721 dkeaton@dutil.com

All inquiries will be answered as an addendum to the RFP.

Please submit responses to the RFP no later than 2:00 PM Monday, February 2nd, 2026 to:

Mr. David Keaton

Director of Energy Services

Dalton Utilities

1200 VD Parrott Jr Parkway / PO BOX 869

Dalton, GA 30721 dkeaton@dutil.com mailto:dkeaton@dutil.com mailto:dkeaton@dutil.com

File details come from the government source that posted it. Updated .