6080-Q__A_Addendum_(002).pdf

PDF 61 KB Posted

Attached to
Drill Machine, Off Road, Rubber Tire, 4 WD
Solicitation number
32-12-6080
Issued by
California

About this file

This is an Invitation for Bid Addendum #1 from the California Department of Transportation - Division of Equipment for solicitation number 32-12-6080, with a bid due date of May 19, 2016, and bid opening at 2:15 PM. The addendum contains four questions and answers relating to technical specifications for what appears to be equipment involving a water tank system. The questions clarify requirements for: a spark arrestor on the engine muffler (required), an air gap anti-siphon fill pipe for the on-board water tank (required), fire hose connections for filling the water tank (required), and a spindle tachometer (required).

The addendum must be included with the submitted solicitation, and failure to return the form may result in bid rejection. The document references a technical specification document that contains at least 10 pages, though the full specifications are not included in this addendum. No pricing terms, funding requirements, or other financial details are included in this addendum.

View the file

Other files

File Type Posted
IFB-6080_.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of California

California Department of Transportation - Division of Equipment

INVITATION FOR BID ADDENDUM

BID DUE DATE: 05/19/2016 SOLICITATION NO. REV DATE PURCHASE ESTIMATE NO.

BID OPENING: 2:15 PM 32-12-6080 1 05/12/2016 32-12-6080

THIS BID ADDENDUM MUST BE INCLUDED WITH SUBMITTED SOLICITATION

FAILURE TO RETURN THIS FORM MAY BE CAUSE FOR BID REJECTION

ADDENDUM # 1 QUESTION AND ANSWERS

1. Question: Is a spark arrestor required on the engine muffler?

Answer: This answer refers to Page 6 of 10 of the technical specification, #35. ENGINE:

Yes

2. Question: Fill pipe for on-board water tank. Is an air gap, anti-siphon fill pipe required?

Answer: This answer refers to Page 4 of 10 of the technical specification #23. VALVES AND FITTING: Yes

3. Question: Fire hose and connections for filling water tank?

Answer: A fire hose connection is required

4. Question: Is a spindle tachometer required?

Answer: This answer refers to Page 3 of 10 of the technical specification #11. SPINDLE:

Yes

BID DUE DATE: 05/19/2016
BID OPENING: 2:15 PM

File details come from the government source that posted it. Updated .