605B7600024 Project Manual.pdf
PDF 217 KB Posted
- Attached to
- Renovation of Entrance Road Sassafras NRMA
- Solicitation number
- BPM059369
- Issued by
- Kent County, Maryland
About this file
This project manual is issued by the State of Maryland Department of Natural Resources Engineering and Construction Division for the renovation of the entrance road at Sassafras NRMA located at 13521 Turner's Creek Road, Kennedyville, Maryland 21646, in Kent County. The project involves resurfacing an existing gravel roadway approximately three-quarters of a mile long by 20 feet wide through stabilization, surface preparation, proof rolling, grading, placement and compaction of aggregate, and construction of roadside drainage ditches. The scope of work includes vegetation and debris removal, proof rolling with a loaded tandem dump truck to identify areas requiring repair, scarification to one inch below the lowest point of any surface defects, grading to establish proper crown for water drainage, placement and compaction of four inches of SHA-approved CR-6 aggregate using a 5-ton vibratory roller, and installation of drainage ditches along both sides of the roadway with outlets to adjacent fields. The contractor must complete all work within sixty calendar days of receiving the Notice to Proceed, with work scheduled Monday through Friday from 7:00 a.m. to 5:00 p.m. and coordinated through the Project Manager and Facility Manager. All prospective bidders are encouraged to attend a pre-bid conference and conduct site visits by contacting the Park Manager, Debbie Cooper at Tuckahoe State Park, (410) 820-1668.
The contractor shall provide a unit price for CR-6 aggregate calculated as a cost per ton multiplied by an estimated 2,000 tons, incorporating all associated costs for transportation, fuel, equipment maintenance, labor, benefits, overhead, and profit. The unit price will be used to adjust the contract price based on actual quantities installed. The contractor must be licensed as a Maryland General Contractor with a minimum of three years of documented experience in gravel roadway grading and aggregate placement, possess a superintendent with prior experience supervising at least two similar projects, and maintain ownership or dedicated access to necessary equipment including a road grader, tandem dump trucks, and vibratory roller. All work must comply with Maryland Department of the Environment regulations, OSHA and MOSHA standards, and applicable building and safety codes. The contractor is required to guarantee all work for two years from the date of acceptance, with any defects corrected at no additional cost to the State. The project is subject to inspection and approval by the Facility/Park Manager, DNR Project Engineer, and DGS Inspector, and the contractor shall be responsible for temporary facilities, erosion control, site cleanup, and repair of any damage caused by construction operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 605B7600024 Bid Response Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
Renovation of Entrance Road
Sassafras NRMA 13521 Turner’s Creek Road, Kennedyville, MD 21646, Kent County
Project Number: EC26-09072-72
June 11, 2026
For The State of Maryland Department of Natural Resources
Engineering and Construction Division Josh Kurtz, Department Secretary
State of Maryland Board of Public Works Wes Moore, Governor
Brooke E. Lierman, Comptroller Dereck E. Davis, Treasurer
TABLE OF CONTENTS
I. Detailed Specifications
A. Scope B. Qualifications of the Contractor C. Site Visit D. Work Schedule E. Standards and Codes F. Materials and Supplies G. Method of Work H. Warranty and Guarantee I. General Requirements
II. Alternates, Unit Prices and Allowances
A. Alternates B. Unit Prices C. Allowances
III. Drawings
A. Vicinity Map & Details
IV. DETAILED SPECIFICATIONS
A. SCOPE:
1. This project shall consist of the Contractor providing all labor, materials, equipment, tools, insurance, etc., necessary to resurface existing gravel roadway at Sassafras NRMA Stabilization of existing road. 13521 Turner’s Creek Road, Kennedyville, MD 21646, Kent County, including surface preparation, proof rolling, grading, placement and compaction of aggregate, and construction of roadside drainage ditches.
2. The proposed project shall include, but is not limited to the following:
a. Using a road grader, scrape off any vegetation and/or debris from the road surface; remove material from State property.
b. Proof roll the entire length of roadway to test for insufficient base material, using a loaded tandem dump. Approximately 3,960’ x 20’.
c. Make repairs to areas determined by the proof roll process.
d. Scarify the entire length of the roadway to a depth of 1 inch below the lowest point of any trenches or potholes. Approximately three quarters of a mile by 20 feet. (3,960’ x 20’).
e. Using the road grader, grade the entire roadway, creating the proper crown as specified to assure maximum water flow off the roadway and shoulders.
Approximately three quarters of a mile by 20 feet. (3,960’ x 20’)
f. Spread and grade 4inches of SHA approved CR-6 on top of the crowned road surface. Use Unit Price #1
g. Roll/compact CR-6 using a 5-ton vibratory roller, ensuring all material is locked into place.
h. Provide drainage ditches down each side of the roadway, diverting all water ways from the road surface, out to adjacent fields.
NOTE: All quantities and sizes listed are approximate. The Contractor shall be responsible to obtain his/her measurements for the project and bidding purposes.
B. CONTRATOR QUALIFICATIONS:
1. The Contractor shall be licensed in the State of Maryland as a General Contractor and in accordance with COMAR regulations to perform work associated with this contract.
2. The Contractor shall have a minimum of three (3) years of documented experience performing gravel roadway grading, aggregate placement, and drainage improvements of similar scope and complexity.
3. The Contractor’s superintendent shall have prior experience supervising at least two projects involving roadway regrading and aggregate surfacing using motor graders and vibratory rollers.
4. The Contractor shall maintain ownership or dedicated access to a road grader, tandem dump trucks, vibratory roller, and other equipment necessary to perform the Work within the specified schedule.
5. All equipment operators shall be qualified and experienced in operating grading and compaction equipment on roadway projects and shall hold applicable licenses or certifications where required by law,
6. Upon request, the Contractor shall supply a list of similar projects which have been successfully completed by the Contractor to the DGS Procurement Officer for review.
C. SITE VISIT:
1. All prospective bidders are encouraged to attend the pre-bid conference and familiarize themselves with all requirements for the project. Failure to attend the pre-bid conference will not relieve the successful bidder from complying with the requirements of these specifications at no additional cost to the State.
2. The Contractor shall verify field dimensions, limits of Work, and existing utilities or obstructions affecting construction and shall not rely solely on verbal descriptions.
3. Commencement of Work shall constitute acceptance of existing site conditions as suitable for performing the Work, except for concealed conditions not reasonably observable during the site visit.
4. Please notify the Park Manager, Debbie Cooper of Tuckahoe State Park (410) 820-
1668 prior to any site visits other than the pre-bid meeting to arrange access to the site.
D. WORK SCHEDULE:
1. Work shall be scheduled through and approved by the Project Manager and Facility Manager. The Contractor shall perform all work Monday through Friday during the normal working hours of 7:00am TO 5:00pm unless approved by the Project Manager in writing.
2. The Contractor shall notify the Project Manager seven (7) days prior to his start of work. They shall coordinate with the Project Manager and the Facility Manager the dates of Work Initiation Conferences, the work, and any closures required.
3. Use of the premises by the Contractor is to be limited to specified work areas and approved storage areas. Verify these locations with the Park Manager.
4. The Contractor shall submit a proposed schedule showing sequencing of vegetation removal, proof rolling, repairs, scarification, grading, aggregate placement, compaction, and ditch construction.
5. Perform operations in a logical sequence to maintain access and limit exposure of unprotected subgrade to weather, completing proof rolling and associated repairs prior to final grading and aggregate placement.
6. Schedule Work to avoid prolonged open excavations or un-compacted surfaces that may be damaged by traffic or precipitation and coordinate traffic control with DNY as required.
7. Work shall be performed and completed by the Contractor within sixty (60) calendar days of Notice to Proceed.
E. STANDARDS AND CODES:
1. All work shall be performed in a first-class workmanship manner in accordance with standards of the trade.
2. All work shall be performed in accordance with the Maryland Department of the Environment Regulations.
3. The Contractor shall comply with OSHA and MOSHA regulations regarding construction safety and health standards throughout the duration of this project.
4. All work shall be performed in accordance with applicable code requirements and standards as defined by the Maryland Building Performance Standards (MBPS) and the latest editions of the:
a. International Building Code (IBC)
b. International Residential Code (IRC)
c. International Plumbing Code (IPC)
d. International Mechanical Code (IMC)
e. National Electrical Code (NEC)
f. International Energy Conservation Code (IECC)
g. Maryland Accessibility Code (MAC)
h. National Fire Protection Association 101 Life Safety Code (NFPA 101)
i. NFPA 70 – National Electrical Code
j. Maryland Department of Transportation – State Highway Administration’s (SHA)
“Standards Specifications for Construction and Materials” and any local amendments or modifications to the standards made by the authority having jurisdiction which may be applicable to the work.
F. MATERIALS AND SUPPLIES:
1. General:
a. All materials shall be as specified or approved equal by the DNR Project
Engineer.
b. The Contractor shall be responsible for the coordination, off-loading and proper storage of all materials and supplies and assume full responsibility for protection and safekeeping up until the time of the final inspection.
c. Where applicable, materials shall be delivered in their original unopened containers with labels intact and legible.
d. All materials and supplies shall be stored up from the ground surface and protected from weather with a waterproof covering.
e. Materials shall be stored in a safe area, out of the way of traffic. Storage site location shall be approved by the Facility Manager prior to the storage of any materials on site.
f. The Contractor shall provide and install soil erosion blanket as specified to protect all newly seeded areas, roadside slopes, and drainage ditches, and to prevent sediment deposition outside the limits of Work.
g. Any materials not specifically mentioned but are necessary for the safe, professional and satisfactory completion of the project shall be provided by the Contractor as if specified herein.
2. Specifics:
a. Surface Gravel shall be SHA approved graded aggregate sub-base CR-6.
b. Soil Erosion Blanket shall be a certified seed free, biodegradable straw blanket with a lifespan of 6 to 12 months. Erosion control blankets should contain no plastic mesh. Loose straw will not be accepted as a substitute.
i Install soil erosion blanket immediately after seeding in accordance with the manufacturer’s recommendations and MDE erosion and sediment control standards. Anchor blankets with biodegradable staples or stakes at spacing recommended by the manufacturer, with additional anchorage at overlaps, edges, and all slope breaks, ditch inlets, and outlets. Overlap adjacent blankets a minimum of 6 inches in the direction of water flow.
c. Provide water, as necessary, for moisture conditioning of subgrade and aggregate during compaction to achieve required density and surface stability.
d. Seed shall be MDE Seed Mix #1, #3, or #5 as per Table B-6 on page 35 of MDE Sediment and Storm Water Management Standard 2009.
e. Furnish all incidental materials, including stakes, markers, and temporary measures required to shape the crown, delineate limits of Work, and protect completed sections from damage.
G. METHOD OF WORK
1. General:
a. All work shall be performed as called for in these written specifications.
b. The Contractor shall coordinate all work with the various trades and suppliers in order to complete the project expeditiously within the time limits of the contract.
The sequence of events shall be left up to the Contractor.
c. All work shall be performed in accordance with applicable local and national code requirements.
d. All work shall be performed in the best and most professional manner by mechanics skilled in their respective trades.
e. The Contractor shall maintain the job site in a safe, neat and orderly manner throughout the entire project and take steps to prevent accumulation of debris at the job site.
f. Upon completion of the project, the Contractor shall legally dispose of all excess materials and other debris.
g. Any work which has not been specifically mentioned but is reasonably implied and is necessary for the safe, professional and satisfactory completion of the project, shall be performed by the Contractor as if specified herein.
2. Specifics – Road Repairs:
a. Strip vegetation and debris from the roadway and shoulders with a road grader or suitable equipment and promptly remove and legally dispose of material from State property.
b. Conduct proof rolling over the full roadway width using a loaded tandem dump truck, observing and marking areas of deflection, rutting, or pumping for subsequent repair.
c. Excavate unstable areas to firm material, then place, grade, and compact suitable aggregate base in lifts to restore uniform support prior to scarifying and final grading.
d. Scarify the existing road surface to a depth of one inch below the lowest point of the road. This includes one inch below the deepest pothole or trench to break up hardpan and blend existing materials. Approximately three thousand nine hundred sixty feet by twenty feet (3960’ x 20’).
e. Supply, place, and compact CR-6 aggregate using Unit Price 1. Compact the aggregate using a 5-ton vibratory roller, making multiple passes until a dense, tightly locked surface free of visible movement or excessive rutting under construction traffic is obtained.
f. Excavate and shape drainage ditches along both sides of the roadway to prevent water accumulation; provide outlets to adjacent fields at regular intervals to ensure proper drainage away from the roadway.
g. Stabilize and clean-up site, to include, but not be limited to excess road materials.
These materials shall be removed from the park property.
h. Erosion Control and Stabilization:
i After final grading is completed, stabilize all disturbed roadside shoulders, side slopes, and drainage ditch banks by seeding with the specified MDE seed mix and installing soil erosion blanket as described in Section F.2.b. Install soil erosion blanket on all seeded slopes steeper than 3H:IV, on all drainage ditch banks and bottoms, and on any other disturbed areas identified by DNR Project Manager to minimize erosion and sediment transport.
H. WARRANTY AND GUARANTEE
1. The Contractor shall guarantee his/her work for a period of two (2) years from the date of acceptance. Any defects found within the warranty period shall be repaired or replaced by the Contractor at no additional cost to the State.
2. During the warranty period, the Contractor shall, at no additional cost to the Owner, correct defects resulting from non-conforming Work, including regarding, recompaction, and replacement of CR-6 aggregate as necessary.
I. GENERAL REQUIREMENTS:
1. The Maryland Department of General Services “Instructions to Bidders for
Construction Projects and General Conditions of Contract Between Owners and Contractors”, dated March 2007, are hereby made part of these specifications.
2. All work shall be coordinated with the Facility / Park Manager, DNR Project Engineer and DGS Inspector during the work initiation meeting.
3. Protect adjacent fields, property, and existing improvements from damage during construction, including prevention of sediment deposition outside the limits of Work.
4. Maintain the roadway in a reasonably trafficable condition for authorized vehicles during construction, coordinating lane closures or restricted access with DNR.
5. Keep the Work area in a neat and orderly condition, removing excess materials, debris, and waste from State property at regular intervals and at completion of the Work.
6. Repair, at the Contractor’s expense, damage to existing improvements, utilities, or property caused by construction operations associated with the Work.
7. Throughout the duration of the project, the Contractor shall be responsible for providing temporary toilet facilities and protection of work as required at no additional cost to the State.
8. The completed project is subject to the inspection and approval of the Facility / Park Manager, DNR Project Engineer and DGS Inspector.
V. ALTERNATES, UNIT PRICES AND ALLOWANCES
A. ALTERNATES
1. None, unless otherwise indicated on the Bid Form.
B. UNIT PRICES
1. The Contractor shall insert a cost per ton X an estimated 2,000 tons to apply new CR- 6 with fines as directed by the DNR Project Manager; to include purchasing, grading, and compaction in accordance with the specifications.
NOTE: The Contractor shall incorporate all costs associated with transportation, fuel, maintenance of equipment, employee salary, benefits, overhead, profit, etc., in the Unit Price. Unit Prices will be used to increase/decrease the contract price based on actual quantities installed, in accordance with Instruction to Bidders for Construction Project (3.B.3).
C. ALLOWANCES
1. None
VI. DRAWINGS
A. The following drawings are included and shall be considered parts of these specifications:
1. V.1 Vicinity Map
2. L.1 Location Map