6025-004_WHIS_AML_Rems_Phase_1.pdf
PDF 3 MB Posted
- Solicitation number
- 0000037664
- Issued by
- Shasta County, California
About this file
This is a Public Works Invitation for Bid (IFB) issued by the California Department of Conservation (DOC) in coordination with the National Park Service (NPS) for abandoned mine land remediation services at Whiskeytown National Recreation Area in Shasta County. The solicitation seeks fabrication and installation of nine abandoned mine remediations across seven mine sites, including polyurethane foam plugs with backfill, bat gates, and rebar air grates with barriers. A mandatory full-day pre-bid walkthrough is required on January 21, 2026, at 7:00 AM at the Whiskeytown NRA Visitor Center, involving site visits over steep terrain requiring four-wheel drive vehicles and moderate hiking. Written questions must be submitted by January 28, 2026, at 5:00 PM, with responses provided by January 30, 2026, at 3:00 PM. Bids are due by February 6, 2026, at 2:00 PM, with bid opening on February 9, 2026, at 2:15 PM and proposed award on February 10, 2026. The contract performance period runs from March 2026 through September 30, 2027, with work commencing no later than 30 days after final approval and Work Authorization issuance.
Bidders must be registered California Department of Industrial Relations public works contractors with current General Contractor licenses, possess MSHA Form 5000-23 certification for the onsite job foreman, provide Acord Certificates of Insurance with specified coverages (General Liability of $1,000,000 per occurrence/$2,000,000 aggregate, Business Automobile Liability of $1,000,000 combined single limit, Workers' Compensation with $1,000,000 Employers Liability limits, and Aircraft Liability of $5,000,000 if helicopter support is used), and submit three references demonstrating relevant abandoned mine remediation experience. The solicitation includes prevailing wage requirements under California Labor Code sections 1720 et seq., with applicable classifications including Laborer and Iron Worker categories. A Performance Bond of 100 percent of the total contract amount is required for awards exceeding $25,000. The Department will evaluate bids based on responsiveness to administrative criteria and award to the lowest responsive responsible bidder after application of eligible preferences, including five percent small business preferences for certified public works small businesses and disabled veteran business enterprise incentives up to five percent. No budget amount is specified in the solicitation; bidders must propose costs for each of the nine tasks individually, with federal funding provided through the Cooperative Agreement between NPS and DOC.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Gavin Newsom, Governor
Jennifer Lucchesi, Director
PUBLIC WORKS INVITATION FOR BID
Notice to Prospective Bidders
January 6, 2026
SOLICITATION NO.: 6025-004
SOLICITATION TITLE: NPS WHIS Phase 1 Abandoned Mine Remediations
Pursuant to direction from the U.S. Department of the Interior National Park Service (NPS) as federal landowner, and pursuant to Cooperative Agreement # P25AM00263 (January 20, 2025) and Task Agreement # P25AC00594 (July 30, 2025) between NPS and the California Department of Conservation (Department or DOC), the Department requires abandoned mine remediation services on NPS lands at Whiskeytown National Recreation Area (WHIS) in Shasta County. You are invited to review and respond to this Invitation for Bid (IFB), entitled 6025-004: NPS WHIS Phase 1 Abandoned Mine Remediations. This is a Public Works IFB and all contractors and subcontractors included in a bid must be registered Public Works contractors with the California Department of Industrial Relations at the time of bid submission.
Contractors wishing to bid on this solicitation are required to attend a mandatory pre-bid walkthrough starting on Wednesday, January 21, at 7:00 AM. Please note: This pre-bid walkthrough will be one full-day long – all tasks will be visited in the field.
Access to the mine sites and features is over sometimes-steep terrain that requires a four-wheel drive vehicle and some moderate hiking on trails and cross-country. A full tank of gas and food and water sufficient for a long day are recommended for this pre-bid walkthrough.
Note that all agreements entered into with the State of California will include by reference General Terms and Conditions for Non-IT Services (GTC, effective 02/2025) and Contractor Certification Clauses (effective 4/4/2017). If you do not have internet access, hard copies can be provided by contacting Samantha Brooks at email address below.
In the opinion of the Department, this Public Works IFB is complete and without the need for explanation. However, the Department may release, in a timely manner and upon approval by NPS, an Addendum to this IFB solicitation. Potential bidders may submit questions regarding intent, expectations, or other topics pertaining to the actual bid solicitation by contacting Samantha Brooks via email at email address below.
Questions must be received by Wednesday, January 28 at 5:00 PM. All questions received by the Department will be answered by Friday, January 30 at 3:00 PM. The Department must receive bids by Friday, February 6 at 2:00 PM.
Please note that no verbal information given will be binding upon the State unless such information is issued in writing as an official Addendum.
Samantha Brooks Department Contracts Analyst ServiceContracts@conservation.ca.gov https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language mailto:ServiceContracts@conservation.ca.gov
California Department of Conservation Solicitation Number 6025-004
NPS WHIS Phase 1 Abandoned Mine Remediations
Table of Contents
I. DESCRIPTION OF SERVICES
A. Overview
B. Period of Performance
C. Work to Be Performed
i. Task-Specific Details
ii. Construction Drawings and Required Variations
D. Construction Schedule and Stipulations
E. Additional Stipulations
F. Worker Site Hazards Mitigation
II. BUDGET DETAIL AND PAYMENT PROVISIONS
A. Invoicing and Payment
B. Budget Contingency Clause
C. Prompt Payment Act
D. Federal Funding
III. BIDDER MINIMUM QUALIFICATIONS
IV. INSURANCE REQUIREMENTS
V. PUBLIC WORKS REQUIREMENTS AND INFORMATION
VI. BOND REQUIREMENTS (only required for the Bidder awarded the contract)
VII. BID REQUIREMENTS AND INFORMATION
A. Key Action Dates and Times
B. Mandatory Pre-Bid Walkthrough
C. Questions and Answers
D. References
E. Cost Detail Format and Requirements
F. Submission of Bid
G. Evaluation and Selection
H. Award and Protest
I. Disposition of Bids
J. Payee Data Record
K. Contractor Certification Clauses (CCC 04/2017)
L. Tax Delinquent Status Verification
M. Preference Programs
N. Commercially Useful Function (CUF)
O. GenAI Disclosure Notification
P. Executive Order N-6-22 Russia Sanction
VIII. REQUIRED ATTACHMENTS
Attachment 1: Required Attachment Checklist
Attachment 2: Bid Sheet and Response
Attachment 3: Bid/Bidder Certification Sheet
Attachment 4: Bid/Bidder Declaration
Attachment 5: Bidder References
Attachment 6: Darfur Act Certification
Attachment 7: California Civil Rights Laws Certification
Attachment 8: Disabled Veteran Business Enterprise Declarations (STD 843)
Attachment 9: Bidder’s Acknowledgement of Prevailing Wage Requirement
Attachment 10: Nondiscrimination Compliance Statement (STD 19)
Attachment 11: Contractor Certification Clauses
Attachment 12: Non-Collusion Declaration
Table of Figures
Figure 1. Map of task locations and bidwalk meeting location
Figure 2. Adit PUF Closure with Backfill – Tasks 1, 2
Figure 3. Shaft PUF Closure with Backfill – Tasks 3, 5, 6, 8, 9
Figure 4. Angle Iron Bat Gate – Task 4
Figure 5. Shaft Rebar Air Grate – Task 7
Figure 6. Rebar Barrier – Task 7 (continued)
Figure 7. Pre-bid walkthrough meeting location
I. DESCRIPTION OF SERVICES
A. Overview The California Department of Conservation (Department or DOC) requires the services of a business with the resources, experience, and abilities to remediate physical safety hazards associated with abandoned mine lands (AML) features. The Department intends to award one (1) service contract for this Invitation for Bid (IFB).
1. The work consists of the fabrication and installation, as specified, directed, and approved by the National Park Service (NPS), of nine (9) abandoned mine remediations at seven (7) mine sites.
2. These features are located on NPS lands at Whiskeytown National Recreation Area (WHIS) in Shasta County (see Figure 1).
Figure 1. Map of task locations (red diamonds) and bidwalk meeting location (arrow)
B. Period of Performance The Agreement's performance schedule shall be from March 2026, or upon approval by the Department and the Department of General Services (DGS), through September 30, 2027. The Contractor agrees to start work no later than thirty (30) days after final approval and Department authorization to proceed via Work Authorization, or at a mutually agreed-upon time specified in the Work Authorization.
Alternative start dates may be granted under special circumstances with written approval via email from the Department.
Upon mutual consent, the Department and the Contractor may execute Amendments to the executed Agreement for time due to schedule conflicts, inclement weather, or other special circumstances. No verbal understanding or agreement not incorporated into the Agreement is binding on either party.
Work shall not commence until:
1. The Department and DGS have awarded, executed, and approved the contract; and
2. The Department has issued the Contractor a Work Authorization, including a date upon which work may commence; and
3. The Contractor possesses any necessary licenses, certifications, and/or permits required for the work.
Note: The Department reserves the right to cancel remediation at any task if proper permits or authorizations cannot be obtained or direction to do so is received from
NPS.
C. Work to Be Performed Work performed under this contract shall be as directed by NPS. The AML feature remediations and specifications included in this bid solicitation were approved by NPS. The Department prepared the bid solicitation, will conduct the solicitation per state contracting rules, and will manage the contract and project during installation according to NPS direction, as contained in this solicitation and the subsequently awarded contract.
Unless directed by NPS through the Department, remediation installations shall be performed in conformance with the Construction Drawings, associated Required Variations, and Task-Specific Details herein. Construction Drawings are the specifications required to complete the remediation in accordance with NPS requirements. Required Variations are corrections and modifications of the generic Construction Drawings necessary to address errors and/or provide additional information specific to the remediation type (see Section I.C.ii and Figures 2 through 6). Task-Specific Details include information particular to the task or specific conditions necessary for the installation (e.g., dimensions, see Section I.C.i).
Additional site-specific modifications or clarifications will be identified during the pre-bid walkthrough (see Section VI.B). If approved by NPS, these will be detailed shortly after the pre-bid walkthrough in an official Addendum from the Department and provided to all bidders to inform their bid submission. It is the bidder's responsibility to submit design questions or modification requests to the Department for clarification and approval prior to submitting their bid.
The Contractor agrees to provide to the Department all services summarized in Table 1 as described herein, including in Task Specific Details, Construction Drawings and their Required Variations approved by NPS (see Section I.C.ii), and the Cultural and Biological Stipulations for this work (see Section I.E).
Table 1. Summary of tasks for NPS WHIS Phase 1 Abandoned Mine Remediations
DOC
Task #
Mine Site Name
DOC
Feature
ID
NPS Feature Name Remediation
Type 1 Figure
Number
Remediation Category and
Timing 2
Task #1 El Dorado 77014 El Dorado Adit 1 Adit PUF 2 DCAT
Task #2 El Dorado 2059 El Dorado Adit 3 Adit PUF 2 DCWS
Task #3 Ganim 1606 Ganim Inclined Shaft Shaft PUF 3 DCWS
Task #4 “Near Ganim” 77013 Near Ganim Adit Angle-Iron Bat Gate 4 BCAT
Task #5 Gladys 77011 Gladys Excavation Shaft PUF 3 DCAT
Task #6 Gladys 12289 Gladys Shaft Shaft PUF 3 DCWS
Task #7 Mt. Shasta 60578 Mt. Shasta Shaft Shaft Rebar Grate with
Rebar Barrier
5, 6 BCAT
Task #8 “South Boundary” 12279 South Boundary
Shaft Shaft PUF 3 DCWS
Task #9 “Dog Gulch” (Monarch Mtn.) 77012 Dog Gulch Shaft Shaft PUF 3 DCAT
1 Remediation types may change after the bidwalk if WHIS determines a more-preferred option. Any and all changes will be detailed in an official addendum released shortly after the pre-bid walkthrough.
2 Category of remediation and required timing based on biological resources (see Sec. 1.D)
DCAT = Destructive Closure, Any Time DCWS = Destructive Closure, Warm Season (from May 1 to October 15) BCAT = Bat-Compatible, Any Time
i. Task-Specific Details The following Task-Specific Details shall be used in conjunction with the Construction Drawings and Required Variations (see Section I.C.ii) to perform the remediation installations. Each of the 9 individual tasks below include a mine site name, task number, NPS and DOC feature IDs, the remediation type to be installed, a description of the mine feature, information on access to the site, and other necessary details on the installation. Additional details will be determined on the pre-bid walkthrough and provided in an Addendum(s) after the walkthrough.
El Dorado Mine
Task #1: El Dorado Adit 1 (77014) – ADIT PUF PLUG WITH BACKFILL El Dorado Adit 1 is an adit with an eroded portal about 2 feet wide by 2 feet tall. The feature includes an existing barrier of T-posts and construction netting. The adit is about 40 feet upslope from an old roadbed.
An adit polyurethane-foam (PUF) plug with backfill shall be installed in conformance with Figure 2, and the associated Required Variations, along with the following:
• The existing barrier of T-posts and construction netting shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility.
Task #2: El Dorado Adit 3 (2059) – ADIT PUF PLUG WITH BACKFILL El Dorado Adit 3 is an adit with an eroded portal about 5 feet wide by 2 feet tall; the passage inside is about 5 feet wide by 6 feet tall. There is an existing barrier of T-posts and construction netting at the end of the run-in. The adit is about 30 feet upslope from an old roadbed.
An adit PUF plug with backfill shall be installed in conformance with Figure 2 and the associated Required Variations, along with the following:
• Due to the potential for bat habitat, construction work on this feature shall ONLY occur in the warm season between May 1 and October 15.
• A wildlife exclusion shall be performed immediately prior to initiating construction at the feature for a minimum of three nights (see Section I.D). The exclusion does not need to be observed or monitored while it is in place.
• The existing barrier of T-posts and construction netting shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility.
Ganim Mine
Task #3: Ganim Inclined Shaft (1606) – SHAFT PUF PLUG WITH BACKFILL Ganim Inclined Shaft is an inclined shaft with an eroded collar about 14 feet by 17 feet; the passage narrows as it runs down on a 45-degree angle. There is a chain-link fence around the shaft collar. Access to the feature is by an old road grade and then cross-country hiking. This task may require helicopter support due to location and access.
A shaft PUF plug with backfill shall be installed in conformance with Figure 3 and the associated Required Variations, along with the following:
• Due to potential for bat habitat, construction work on this feature shall ONLY occur in the warm season between May 1 and October 15.
• A wildlife exclusion shall be performed immediately prior to initiating construction at the feature for a minimum of three nights (see Section I.D). The exclusion does not need to be observed or monitored while it is in place.
• The existing fence shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility. The posts are set in concrete bases and shall be cut off as close to grade as possible; the concrete may be left in place.
• The PUF plug shall be poured onto a false bottom.
• The PUF plug shall be installed as far down the incline as reasonable to minimize the size of the plug.
“Near Ganim” Mine
Task #4: Near Ganim Adit (77013) – BAT GATE Near Ganim Adit is an adit with some erosion in the portal area; the adit passage opens to about 6 feet wide by 6 feet tall inside. Access to the feature is by an old road and then cross-country hiking. This task may require helicopter support due to location and access.
An angle-iron bat gate shall be installed in conformance with Figure 4 and the associated Required Variations, along with the following:
• Rubble in the portal area may be excavated as necessary for access into the adit.
• The bat gate shall NOT have a removable bar.
• The bat gate may require angled bracing behind the gate down to floor for support if sufficient anchor pins are not possible due to rock competency.
3-inch angle iron is suitable material for angled bracing.
• The installation date of the bat gate shall be welded or inscribed onto the portal side of the bat gate in the format Month Day Year (e.g., “JULY 20, 2026”), so as to be easily visible and permanently legible.
Gladys Mine
Task #5: Gladys Excavation (77011) – SHAFT PUF PLUG WITH BACKFILL Gladys Excavation is a prospect with a collar about 10 feet by 16 feet at grade, narrowing to 8 feet by 10 feet at bottom. The excavation contains some loose tree branches. The shaft is surrounded by a low fence of T-posts and chain-link fencing.
Access to the feature is either by fire road and then trail hiking, or by trail hiking from a main open road. This task may require helicopter support due to location and access.
A shaft PUF plug with backfill shall be installed in conformance with Figure 3 and the associated Required Variations, along with the following:
• The existing fence shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility.
• Loose tree branches shall be removed from the excavation prior to PUF installation.
• The PUF plug shall be poured from the bottom of the feature up.
• After 2+ feet of fill cover is installed over plug, the lowest side of the shaft collar shall be no more than 5 feet above the top of the fill (i.e., a person shall be able to self-extract from the resulting pit).
Task #6: Gladys Shaft (12289) – SHAFT PUF PLUG WITH BACKFILL Gladys Shaft is a vertical shaft with a collar about 20 feet by 20 feet at grade, narrowing to 8 feet by 8 feet about 15 feet down from collar. The shaft is surrounded by a low fence of T-posts and chain-link fencing. Access to the feature is either by fire road and then trail hiking, or trail hiking from the main open road. This task may require helicopter support due to location and access.
A shaft PUF plug with backfill shall be installed in conformance with Figure 3, and the associated Required Variations provided on the page subsequent the Construction Drawing, along with the following:
• The existing fence shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility.
• Due to potential for bat habitat, construction work on this feature shall ONLY occur in the warm season between May 1 and October 15.
• A wildlife exclusion shall be performed immediately prior to initiating construction at the feature for a minimum of three nights (see Section I.D). The exclusion does not need to be observed or monitored while it is in place.
• The PUF plug shall be poured onto a false bottom.
• After 2+ feet of fill cover is installed over plug, the lowest side of the shaft collar shall be no more than 5 feet above the top of the fill (i.e., a person shall be able to self-extract from the resulting pit).
Mt. Shasta Mine
Task #7: Mt. Shasta Shaft (60578) – SHAFT REBAR GRATE with REBAR
BARRIER
Mt. Shasta Shaft is a shaft with an eroded collar about 10 feet by 15 feet. Below the collar, the shaft narrows to about 5 feet by 6 feet in area, and contains permanently standing water about 6 to 8 feet down from the collar. There is a chain-link fence around the collar. Access to the feature is via trail hiking from the main open road.
This task may require helicopter support due to location and access.
A shaft rebar grate shall be installed in conformance with Figure 5 and the associated Required Variations, along with the following:
• The existing fence shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility. If the posts are set in concrete bases, they shall be cut off as close to grade as possible; the concrete may be left in place.
• Minimal vegetation clearing required for installation of the shaft rebar grate is permitted.
• Care shall be taken to avoid impacts to cultural resources around shaft collar (e.g. embedded brick) to the maximum extent practicable.
• The installation date of the shaft rebar grate shall be welded or inscribed onto the structure in the format Month Day Year (e.g., “JULY 20, 2026”), so as to be easily visible and permanently legible.
A rebar barrier shall be installed around the shaft collar in conformance with Figure 6 and the associated Required Variations, along with the following:
• Minimal vegetation clearing required for installation of the rebar barrier is permitted.
• The rebar barrier shall be set back from the shaft collar edge by a minimum of 5 feet.
• Care shall be taken to avoid impacts to cultural resources around shaft collar to the maximum extent practicable.
“South Boundary” Mine
Task #8: South Boundary Shaft (12279) – SHAFT PUF PLUG WITH BACKFILL South Boundary Shaft is a vertical shaft with a collar about 12 feet by 15 feet at grade, and approximately 12 feet by 13 feet to the bottom of the shaft. The shaft collar is surrounded by a chain-link fence. Access to the feature is by an old, overgrown, ascending roadbed for about 250 feet from an open route.
A shaft PUF plug shall be installed in conformance with Figure 3, and the associated Required Variations, along with the following:
• Due to the potential for bat habitat, construction work on this feature shall ONLY occur in the warm season between May 1 and October 15.
• A wildlife exclusion shall be performed immediately prior to initiating construction at the feature for a minimum of three nights (see Section I.D). The exclusion does not need to be observed or monitored while it is in place.
• The existing fence shall be removed and properly reused, recycled, and/or disposed of at a permitted offsite facility. The posts are set in concrete bases and shall be cut off as close to grade as possible; the concrete may be left in place.
• The PUF plug shall be poured onto a false bottom.
• After 2+ feet of fill cover is installed over plug, the lowest side of the shaft collar shall be no more than 5 feet above the top of the fill (i.e., a person shall be able to self-extract from the resulting pit).
“Dog Gulch” Mine (Monarch Mountain)
Task #9: Dog Gulch Shaft – SHAFT PUF CLOSURE WITH BACKFILL Dog Gulch Shaft is a shaft with a collar approximately 8 feet by 9 feet, and irregularly shaped sidewalls at approximately 6 feet by 7 feet, to the bottom of the shaft 20 feet down from collar. There is significant vegetation around and over the shaft collar. The shaft is about 20 feet downslope from a road.
A shaft PUF plug with backfill shall be installed in conformance with Figure 3, and the associated Required Variations, along with the following:
• Minimal vegetation clearing required for installation of the PUF plug is permitted.
• The PUF plug shall be poured onto a false bottom.
After 2+ feet of fill cover is installed over plug, the lowest side of the shaft collar shall be no more than 5 feet above the top of the fill (i.e., a person shall be able to self-extract from the resulting pit).
ii. Construction Drawings and Required Variations The following Construction Drawings and Required Variations shall be used in conjunction with the Task-Specific Details (see Section I.C.i) to perform the remediation installations:
Figure 2. Adit PUF Closure with Backfill – Tasks 1, 2 (see associated Required Variations next page)
Figure 2 (continued): Adit PUF Closure with Backfill – Required Variations The bulleted items below represent modifications for installation from the standard adit PUF closure with backfill drawing in Figure 2 required by NPS. They consist of clarifications to, and changes from, the drawing. To properly install each adit PUF closure with backfill, the Task-Specific Details (see Section I.C.i), the above drawing (Figure 2), and these Required Variations must be applied jointly:
• PUF plugs may be installed in horizontal adits (as shown in Figure 2) and in other types and inclinations of openings.
• PUF plug shall be covered with a minimum of 24 inches of random fill from adjacent area.
• Optional pipe (see Figure 2 and Note 3) and “trench armoring” below pipe outlet shall NOT be installed.
Figure 3. Shaft PUF Closure with Backfill – Tasks 3, 5, 6, 8, 9 (see associated Required Variations next page)
Figure 3 (continued): Shaft PUF Closure with Backfill – Required Variations adit PUF closure with backfill drawing in Figure 3 required by NPS. They consist of clarifications to, and changes from, the drawing. To properly install each adit PUF closure with backfill, the Task-Specific Details (see Section I.C.i), the above drawing (Figure 3), and these Required Variations must be applied jointly:
• The formula to determine minimum required PUF plug thickness shall be:
o Minimum PUF plug thickness = 0.7a (2.0+0.5(b/a-1)) a = bottom of plug short length b = bottom of plug long length NOTE: The formula in Figure 3, Note 5 (and on diagram) shall
NOT be used.
• PUF plug shall be covered with a minimum of 24 inches of random fill from adjacent area.
• The fill cover shall NOT be mounded over the shaft collar (to allow for settling as shown in Figure 3) unless the top of finished PUF plug is less than 2 feet from top of shaft collar. In this case, above-grade fill (a mound) would be required to achieve 24+ inches of fill cover over the top of the PUF plug.
• Optional vent pipe (see Figure 3, diagram and Notes 1-3) shall not be installed.
Figure 4. Angle Iron Bat Gate – Task 4 (see associated Required Variations second following page)
Figure 4 (continued): Angle Iron Bat Gate – Required Variations bat gate drawing in Figure 4, as required by NPS. They consist of clarifications to, and changes from, the Construction Drawing. The Task-Specific Details (see Section I.C.i), the above drawing (Figure 4), and these Required Variations must be applied jointly to properly install each bat gate:
• The uprights shall be on the portal side of the bat gate, with horizontal bars on the interior side of the bat gate, unless specified in the Task-Specific Details.
• The sill plate shall be 6-inch angle iron or C-channel. The top of the sill plate must be flat and flush to grade of the adit floor to allow clear ingress/egress of small animals.
• The uprights shall stand atop the sill plate, as shown in Detail 2 on Figure 4.
• The bat gate shall have 8 anchoring pins, unless specified in the Task-Specific Details: one pin driven up at the top of each upright, one pin driven down at the bottom of each upright, and four horizontal pins attached to the nearest bars at approximately 1/3 and 2/3 of the height of the gate (see Detail 2 on Figure 4).
• If a bat gate requires angled bracing down to the floor, 3-inch angle iron is an acceptable material. The angled bracing shall run from the back side of the gate to the adit sill and be securely pinned.
• The bat gate shall NOT have a removable bar. All horizontal bars shall be permanently welded onto the hangers.
• Other than as identified in the Task-Specific Details, no permanent writing shall remain on any structure at the completion of installation.
Figure 5. Shaft Rebar Air Grate – Task 7 (see associated Required Variations next page)
Figure 5 (continued): Shaft Rebar Air Grate – Required Variations shaft rebar air grate drawing in Figure 5, as required by NPS. They consist of clarifications to, and changes from, the Construction Drawing. The Task Specific Details (see Section I.C.i), the above drawings (Figure 5), and these Required Variations must be applied jointly to properly install each shaft rebar air grate:
• Other than as identified in the Task-Specific Details, no permanent writing shall remain on any structure at the completion of installation.
Figure 6. Rebar Barrier – Task 7 continued (see associated Required Variations next page)
Figure 6 (continued): Rebar Barrier – Required Variations The bulleted items below represent modifications for installation from the rebar barrier drawing in Figure 6, as required by NPS. They consist of clarifications to, and changes from, the Construction Drawing. The Task-Specific Details (see Section I.C.i), the above drawings (Figure 6), and these Required Variations must be applied jointly to properly install each rebar barrier:
• For installation of posts:
o In soil or unconsolidated rock (waste rock), no concrete, bends, or soil plates are required.
o In competent rock, the Contractor shall determine if epoxy is required for secure anchoring.
• No wire barrier fabric is to be attached.
• Relevant details from “Spec Section 0250”:
o Rebar shall be Grade 60 #8 minimum, meeting the ASTM A706 standard.
o Epoxy resin grout, if used, shall conform to the requirements of ASTM
C881, Type IV, Grade 3, such as Simpon ET Epoxy-Tie, Hilti HY 200 epoxy, or approved equivalent.
D. Construction Schedule and Stipulations
• Construction will begin once the contract is fully executed and a Work
Authorization has been issued by the Department. It is anticipated that construction shall begin in April 2026 at the earliest and be completed as soon as feasible unless otherwise directed by the Department in coordination with NPS. The Contractor shall notify NPS and the Department prior to their start of construction to allow relevant staff to be present if desired.
• Four tasks are designated as “Destructive Closure, Warm Season” (DCWS;
see Table 1), specifically:
o Task 2 - El Dorado Adit 3 o Task 3 - Ganim Inclined Shaft o Task 6 - Gladys Shaft o Task 8 - South Boundary Shaft
On these four features, construction work shall ONLY occur in the warm season between May 1 and October 15.
Immediately prior to construction start on any of these features, a wildlife exclusion3 shall be performed by the Contractor at the feature for a minimum of three nights. A wildlife exclusion shall consist of completely covering the adit portal or shaft collar with 1-inch chicken wire, anchored around the perimeter, while leaving a small, low awning (window) open. This allows any bats inside to exit the feature under the awning, but this opening will not be apparent when bats attempt to approach it from the outside. The exclusion does not need to be observed or monitored by the Contractor while it is in place.
• In addition to the above wildlife exclusion work, the Contractor shall thoroughly inspect the general area around the installation location at all features for wildlife immediately before installation begins. If any bats or nesting birds are observed, the Contractor shall exit the feature and contact NPS and the Department, and no work on that task shall proceed until authorized by NPS through the Department.
• Avoid disturbance near active bald eagle nests during nesting season (January 1 to August 15). The bald eagle is a State Listed Endangered Species and is federally protected by the Bald and Golden Eagle Protection Act (16 U.S.C. 668-668d). Restrict activities producing above-ambient noise (above 92 decibels) or visual disturbance within 0.25 mile (no line-of-sight) or
0.50 mile (line-of-sight) of an eagle nesting site during the nesting season. The Contractor shall consult with WHIS via DOC on the distribution of active eagle nests before any work is conducted during the eagle nesting season.
3 For more information, see “Step 4.3.3 Exclusions for Destructive Closures” (pages 85, 88) in Managing Abandoned Mines For Bats for more details: pacwestbats.org/_files/ugd/943ff7_303b8c449b2346cca350682ca3b6b359.pdf
• When work is to occur during raptor and other birds' nesting season (February 1 to August 1), the Contractor is required to consult with WHIS via DOC to ensure that a pre-work nesting bird survey is conducted in work areas and overland vehicular travel routes prior to commencing work. If an active nest is found during pre-work surveys, the nest information shall be shared by WHIS with DOC prior to work commencement. Information will include species, location, and recommended protective measures to be implemented. If an active bird nest is encountered during work, work shall cease within the area of the nest and the Contractor shall contact WHIS via DOC for further guidance. Nesting birds are protected by the Migratory Bird Treaty Act (16 U.S.C. §§ 703-712).
• For fire prevention:
a) WHIS typically experiences higher fire danger between June and
November, although annual weather conditions vary considerably.
b) Due to the year-round high risk of fire at WHIS, an NPS-approved Fire
Prevention Plan (FPP) is required for all Contractors operating in the park. The FPP shall be submitted to DOC and WHIS within 30 days of contract award for review and approval.
c) Standard best management practices in the FPP shall include the following:
i. All motorized vehicles and equipment in each active construction area will carry a copy of the approved FPP, one round-point shovel with an overall length of not less than 46 inches, one fire extinguisher rated 5 A:B:C or greater or two fire extinguishers rated 2 A:B:C or greater, a first aid kit, a method of communication (see d. below), one gallon of bottled water, and an emergency evacuation action plan.
ii. During conditions of extreme fire danger, the USFS system and the localized CalFire Rating System may limit or suspend operations in specific areas or require additional measures.
iii. WHIS also retains the authority to suspend or stop all work activities during red flag warnings, fire weather watch, and/or during an ongoing emergency in the Park.
1. Red Flag Warnings are posted on the National Weather Service (NWS) website:
http://www.wrh.noaa.gov/firewx/main.php.
2. Fire Weather Watches are issued by NWS to alert land managers and the public that upcoming weather conditions could result in extensive wildfire occurrence or extreme fire behavior. A Fire Weather Watch means https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.law.cornell.edu%2Fuscode%2Ftext%2F16%2F703&data=05%7C02%7CDavid.Tibor%40conservation.ca.gov%7C2b6442436ecf46227c3708de33930774%7C4c5988ae5a0040e8b065a017f9c99494%7C0%7C0%7C639004903774593410%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=gDLOAmhGnR54l7S5Y16%2Fsgc%2BO1InyMcskjDbH%2FAb2FU%3D&reserved=0 http://www.wrh.noaa.gov/firewx/main.php critical fire weather conditions are possible but not imminent or occurring.
iv. All fires will be reported via 9-1-1 and/or agency dispatch ASAP.
In the event that project construction results in a wildfire or other unplanned ignition, on-site staff will immediately call 9-1-1 and take all reasonable steps to safely attempt to extinguish the fire.
d) WHIS has limited cellular capabilities in various areas of the park, with Verizon the primary accessible cellular network provider. Limited service may be available for T-Mobile, AT&T, or other cellular providers.
Due to poor cell phone coverage in certain areas of the park, each work site shall possess a satellite phone and/or Verizon-network cellular phone for emergency use.
• For “hot work”:
a) All hot work (e.g., welding, cutting, brazing/soldering, grinding) must conform to industry best practices and safety standards.
b) To minimize the potential for accidental ignition from welding, the use of protective welding blankets, wetting down of vegetation or flammable cultural resources (e.g. collar timbering), and/or work in a non-vegetated area may be required.
c) Hot work performed within the Park shall adhere to the stipulations of the approved Fire Prevention Plan, including the following:
i. Hot work is allowed on all dates, except during Red Flag Warnings, Fire Weather Watches, and/or during an ongoing emergency in the Park.
ii. Removal of shrubby vegetation immediately surrounding a mine feature to facilitate safe work distances is authorized. All vegetation must be cut flush to the ground and dispersed at least 25 feet from the mine feature. No vegetation piling is authorized.
iii. If tree felling is required to facilitate a safe work zone, please notify DOC and WHIS for assistance. The Contractor is not authorized to fell trees within WHIS.
E. Additional Stipulations The following additional stipulations are provided by NPS and shall be followed by the Contractor. Any deviations shall be discussed and agreed upon with NPS and the Department.
• Primary access to the project sites is limited to existing roads. Off-road equipment travel and use are prohibited.
• To reduce the risk of introducing invasive plant species, all equipment, tools, and materials shall be washed, free of mud, and inspected by the Contractor prior to transport to each mine site.
• To prevent the introduction or spread of invasive weed species, WHIS requires off-site inspections for large equipment (e.g. toter/track-barrow, ATV, skid steer) before entering the park. Additional large equipment inspections are required before transporting equipment between work sites within the park.
WHIS will provide these inspection services in coordination with the Contractor upon work mobilization.
• Limit vegetation removal and other surface disturbance to the minimum required for project implementation.
• Feeding of wildlife, leaving of food or trash as an attractive nuisance to wildlife, collection of native plants, or harassment of wildlife is prohibited.
• Collection of any natural or historical materials (e.g., plants, seeds, rocks, artifacts) is strictly prohibited.
• All persons involved with the project must follow the most recent version of the National White-Nose Syndrome (WNS) Decontamination Protocol4:
o Before entering WHIS:
All tools, equipment, and clothing will be properly decontaminated (see below).
If the Contractor has previously worked at a WNS-positive site, any clothing or tools used at that site will not be used on this project.
o Before moving between mine sites or demobilizing from a mine site:
Remove dirt/mud from equipment at site.
Change into clean clothing and footwear prior to entering a vehicle.
Contain work clothing in a garbage bag or other container for treatment away from the location.
Spray work boots and hard wearable items (e.g., hard hat, welding helmet) with 50-70% Isopropyl alcohol and let dry for at least 20 seconds.
Wash work clothing with hot water of at least 131 degrees Fahrenheit (55 degrees Celsius) for at least five continuous minutes.
4 National White-Nose Syndrome (WNS) Decontamination Protocol, last updated March 2024.
https://www.fs.usda.gov/Internet/FSE_DOCUMENTS/fseprd1173245.pdf https://www.fs.usda.gov/Internet/FSE_DOCUMENTS/fseprd1173245.pdf
• All motorized project equipment shall be equipped with spark arrestors and mufflers.
• Within WHIS boundary, smoking only is allowed in designated areas (e.g., Visitor Center picnic area, marinas, parking lots) or within a personal vehicle.
• To protect cultural resources, if changes or modifications to the approved hazard mitigation methods become necessary due to unforeseen circumstances during project implementation, all work on that feature shall be stopped, and NPS shall be consulted prior to any deviation from the approved plan.
• All timbers, cribbing, or other features that retain the integrity and are associated with mine adits, shafts, or prospects proposed for remediation by this project shall be left in place and intact unless otherwise directly specified in the task descriptions. If loose artifacts (e.g., individual timbers on the floor inside an adit) must be moved to allow for access and construction, they shall be photographed and returned as closely to their original positions as possible.
• Pets must be kept on a leash no longer than six feet at all times. Pets may never be left unattended. Pet excrement must be collected and disposed of in garbage receptables.
• Any existing fences around mine features shall be removed only immediately prior to remediation work. If construction work is not completed in a single day, protective measures (e.g., reinstalling removed section of fencing, adding temporary construction fencing) to restrict wildlife and human access shall be installed while the job site is unattended, and removed when the work is completed.
• Standard practices, such as the use of containment areas and spill cleaning kits, will be onsite to prevent toxic chemicals, hazardous materials, and other fluids from entering vegetation type streams, washes, and tributary networks through water runoff, erosion, or sediment transport. Contact NPS immediately if any spill occurs.
• All materials, debris, and trash must be removed from site after completion of the installation.
• Project areas and adjacent staging areas shall be returned to approximate original site conditions upon completion of work.
F. Worker Site Hazards Mitigation The Contractor must provide at the site such equipment and medical facilities as are necessary to supply first aid service to anyone who may be injured in connection with the work. The Contractor will be responsible for accident prevention and safety in the performance of all work and will be governed by the requirements of this article in all operations at the work site. The Contractor shall ensure all personnel have appropriate Cal/OSHA trainings and certificates related to the work being performed.
The Contractor must comply with all applicable safety regulations and orders of the State of California, Department of Industrial Relations, Division of Occupational Safety and Health and all applicable provisions of the California Health and Safety Code and will take or cause to be taken such additional measures as may be necessary for the prevention of accidents. The Contractor must impose the foregoing requirements on all subcontractors and enforce compliance therewith.
II. BUDGET DETAIL AND PAYMENT PROVISIONS
A. Invoicing and Payment Payment for services performed under the Agreement will be made upon receipt of an acceptable invoice and approval by NPS of the completed task based on conformance with the Task-Specific Details, Construction Drawings, Required Variations, any NPS-approved changes to design specifications, and information documented by the Contractor and/or the Department. The Contractor shall invoice the Department upon successful completion of services rendered. The State agrees to compensate the Contractor upon completion of a line item as specified in the Budget Detail. Invoices shall be submitted via email (email address to be provided upon award of contract) or via regular mail to:
Department of Conservation 715 P Street, MS-1905 Sacramento, CA 95814
ATTN: TBD (will be provided upon award of contract)
An acceptable invoice must include:
• Date(s) of task performance.
• Contractor's name and address.
• Department's name and address.
• Department agreement number.
• Appropriate itemization that matches the Budget Detail.
• Deliverables stipulated in the Work Authorization.
The Department will verify and approve or disapprove the invoice item(s). If the Department does not approve the invoice item(s), the Department will dispute the invoice per Prompt Payment Act and provide opportunity to the Contractor to resolve the dispute.
Please note that invoices not submitted to one of the above listed addresses run the risk of not being received by the appropriate unit for processing or the appropriate unit not being aware that an invoice has been submitted. To ensure an invoice is received for processing and to start the Prompt Payment process it must be delivered to one of the addresses listed above.
B. Budget Contingency Clause It is mutually agreed that if the State Budget Act of the current year and/or any subsequent years covered under the Agreement does not appropriate sufficient funds for the program, the Agreement shall be of no further force and effect. In this event, the State shall have no liability to pay any funds whatsoever to the Contractor or to furnish any other considerations under the Agreement and the Contractor shall not be obligated to perform any provisions of the Agreement.
If funding for any fiscal year is reduced or deleted by the Budget Act for purposes of this program, the State shall have the option to either cancel the Agreement with no liability occurring to the State or offer an Agreement amendment to the Contractor to reflect the reduced amount.
C. Prompt Payment Act Payment will be made in accordance with and within the time specified in the California Government Code Chapter 4.5, commencing with Section 927.
D. Federal Funding It is mutually understood between the Contractor and the Department that the Agreement may have been written for the mutual benefit of both parties before ascertaining the availability of congressional appropriation of funds to avoid program and fiscal delays that would occur if the contract were executed after that determination was made.
The Agreement is valid and enforceable only if sufficient funds are made available to the State by the United States Government for the purpose of this project. In addition, the Agreement is subject to any additional restrictions, limitations, or conditions enacted by the Congress or to any statute enacted by the Congress that may affect the provisions, terms, or funding of the contract in any manner.
The Contractor and the Department mutually agree that if the Congress does not appropriate sufficient funds for the program, the contract shall be amended to reflect any reduction in funds.
The Department has the option to invalidate the Agreement under the 30-day cancellation clause or to amend the Agreement to reflect any reduction in funds.
III. BIDDER MINIMUM QUALIFICATIONS
In order for bids to be considered responsive, the bidding Contractor shall:
1. Be registered with the California Department of Industrial Relations as described below (as well as any subcontractors listed in the bid).
2. Possess a current and active California General Contractor License.
3. Possess a current, signed Mine Safety and Health Administration (MSHA) Form
5000-23 for the onsite job foreman5 for completion of 40 hours of health and safety training.
4. Possess an Acord Certificate of Insurance and capability to meet all requirements as specifically outlined in Section IV.
5. Submit at least three (3) references with descriptions and photos of relevant abandoned mine remediation work performed (e.g., bat gates, culvert gates, cupolas, wire nets; see Attachment 5: Bidder References).
6. Participate in a mandatory pre-bid walkthrough at the job sites.
7. Submit all items detailed in Section VII in their bid package.
The winning bidder only must submit a copy of their Acord Certificate of Insurance with required endorsements. The Department will request these items after the contract award date.
IV. INSURANCE REQUIREMENTS
The following are general provisions which apply to all policies:
1. Coverage Term: Coverage needs to be in force for the complete term of the contract. If insurance expires during the term of the contract, a new certificate must be received by the State at least thirty (30) days prior to the expiration of this insurance. Any new insurance must comply with the original contract terms.
2. Policy Cancellation or Termination & Notice of Non-Renewal: Insurance policies shall contain a provision stating coverage will not be cancelled without thirty (30) days prior written notice to the State. New certificates of insurance are subject to the approval of the Department of General Services (DGS) and the Contractor agrees no work or services will be performed prior to obtaining such approval. In the event the Contractor fails to keep in effect at all times the specified insurance coverage, the State may, in addition to any other remedies it may have, terminate this contract upon the occurrence of such event, subject to the provisions of this contract.
3. Premiums, Assessments and Deductibles: The Contractor is responsible for any premiums, policy assessments, deductibles or self-insured retentions contained within their insurance program.
5 Only the onsite job foreman requires this certificate; additional workers onsite do not.
4. Primary Clause: Any required insurance contained in this contract shall be primary, and not excess or contributory, to any other insurance carried by the State.
5. Insurance Carrier Required Rating: All insurance companies must carry an AM Best rating and financial category rating acceptable to the Office of Risk and Insurance management. If the Contractor is self-insured for a portion or all its insurance, review of financial information including a letter of credit may be required.
6. Endorsements: Any required endorsements requested by the State must be physically attached to all requested certificates of insurance and not substituted by referring to such coverage on the certificate of insurance.
7. Inadequate Insurance: Inadequate or lack of insurance does not negate the Contractor's obligations under the contract.
8. Use of Subcontractors: The Contractor's insurance must state that there is blanket coverage while work is being performed under the contract. The Contractor shall include all Subcontractor's insurance equal to policies, coverages, and limits required of the Contractor.
The following are contract-specific insurance requirements. Bidder shall display evidence of the following on an Acord certificate of insurance evidencing the following coverages:
1. Commercial General Liability: The Contractor shall maintain general liability on an occurrence form with limits not less than $1,000,000 per occurrence for bodily injury and property damage liability combined with a $2,000,000 annual policy aggregate. A "per project aggregate" endorsement is required. The policy shall include coverage for liabilities arising out of premises, operations, independent contractors, products, completed operations, personal & advertising injury, and liability assumed under an insured contract. The policy must name The Department of Conservation, Division of Mine Reclamation, The State of California, its officers, agents, employees and servants as additional insureds, but only with respect to work performed under the contract. A Primary and Noncontributory endorsement must be included.
2. Business Automobile Liability: The Contractor shall maintain business automobile liability insurance for limits not less than $1,000,000 combined single limit. Such insurance shall cover liability arising out of a motor vehicle including owned, hired and non-owned motor vehicles.
3. Worker's Compensation and Employers Liability: The Contractor shall maintain statutory worker's compensation and employer's liability coverage for all its employees who will be engaged in the performance of the contract. A waiver of subrogation is required to be attached to the workers' compensation certificate of insurance. In addition, employer's liability limits of $1,000,000 are required. The
Waiver of Subrogation should waive any right of subrogation against “The State of California, Dept of Conservation” as insured.
4. If a helicopter is used, the Contractor shall supply evidence of Aircraft Liability or Subcontractor's evidence of Aircraft Liability. The Contractor shall maintain Aircraft Liability limits not less than $5,000,000 including passenger and third-party coverage. The policy must name The Department of Conservation, Division of Mine Reclamation, The State of California, its officers, agents, employees and servants as additional insureds, but only with respect to work performed under the contract.