This is a Sole Source Request and Determination Form submitted by the New Mexico Environment Department (NMED) for professional engineering and technical advisory services in support of drinking water system improvements for the City of Las Vegas, New Mexico. The contract is with Burns & McDonnell, with a primary contact of Mike Pindak, P.E. (720-227-8241). The scope of work encompasses comprehensive design management services for a water treatment plant reconstruction following the Hermits Peak/Calf Canyon Fire, including weekly engineering progress meetings, bi-monthly management meetings, quality control/quality assurance oversight, project scheduling, cost estimating, and preparation of detailed design documents at 60%, 90%, and 100% completion levels. Additional services include permitting and stakeholder coordination, water sampling and analysis support, and bidding phase services including bid document preparation, bid opening attendance, and issued-for-construction document preparation. The contract explicitly excludes construction services, general contracting, subcontractor bidding, equipment procurement, and construction management activities. The contract term is four years, with an estimated contract value of $6,024,004.00 before tax.
The sole source determination is based on Burns & McDonnell's unique qualifications stemming from its prior involvement in emergency engineering assessments and preliminary engineering documentation for the City of Las Vegas water system. The firm mobilized in early September 2025 and has maintained continuous on-site presence conducting performance evaluations, field investigations, and system-specific testing under post-fire conditions. NMED's due diligence process emphasized that transitioning to a different engineering firm would introduce an estimated 4-6 month delay, require duplication of completed analytical work, and necessitate re-establishment of regulatory coordination frameworks, thereby jeopardizing public health and water system reliability. Burns & McDonnell's established institutional knowledge, local presence with an Albuquerque office, proven design-build capability, and immediate readiness to advance accelerated design schedules position the firm as the only viable option to preserve project momentum and ensure timely delivery of safe drinking water to City of Las Vegas residents. The sole source request was posted for 30 days for public protest and requires written approval by the State Purchasing Agent before becoming effective.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2025 Sole Source Form
STATE OF NEW MEXICO
SOLE SOURCE REQUEST AND DETERMINATION FORM
A sole source determination is not effective until the sole source request for determination has been posted for thirty (30) calendar days without Protest, and subsequently approved in writing by the State Purchasing Agent of the General Services Department. The foregoing requirement is regardless of whether the sole source request for determination has been signed by the Agency.
I. Name of Agency: New Mexico Environment Department
Agency Chief Procurement Officer: Charlette Probst
Telephone Number: 505-500-9779
Agency Contact for this request: Andres Delgado
Email Address: andres.delgado@env.nm.gov
II. Name of prospective Contractor: Burns & McDonnell
SHARE Vendor Number (must be active): 0000178821
Address of prospective Contractor: 9191 S. Jamaica St., 324E, Englewood CO 80112
Contact Name, Telephone Number and Email Address: Mike Pindak, P.E. 720-227-8241
Amount of prospective contract before tax: $6,024,004.00
Estimated tax amount (tax is subject to change): Tax included
III. Term of prospective contract: 4 years
Note: Please refer to §13-1-150 for contract term limits.
If this is an amendment request to an existing contract, include current sole source posting number issued by SPD:
IV. Agency is required to provide the detailed scope of work (or amendment) for this sole source. Scope if work must match the scope included in the services determination and
Horizons declination.
Burns & McDonnell will provide professional engineering and technical advisory services to support long-term drinking water system improvements for the City of Las Vegas following impacts from the Hermits Peak/Calf Canyon Fire and subsequent watershed instability.
Design Management
Progress Meetings/Conference Calls
Engineer will conduct weekly engineering progress meetings and attend weekly coordination meetings conducted by others. These meetings will be held virtually via Microsoft Teams and will be attended by the Engineer’s design manager, process engineer, and discipline engineers as
Docusign Envelope ID: A5AA494B-0B26-4CCB-99C1-6195FDA6B5C7 mailto:andres.delgado@env.nm.gov needed. This task assumes a total of two (2) 1-hour meetings every week for the duration of design, for a total of one hundred and four (104) meetings.
Management Meetings
Engineer will conduct bi-monthly management meetings. These meetings will be held virtually via Microsoft Teams and will be attended by the Engineer’s design manager. This task assumes twelve (12) months of meetings. LVNM WTP SOW
Design Management
The Engineer’s design manager will review design status, review design schedule, review design deliverables, align design resources including sub-consultants, and provide oversite of the
Quality Control/Quality Assurance program.
Quality Control/Quality Assurance
The Engineer’s project team will follow Engineer’s QA/QC program. This task includes time to manage the internal review of the design by qualified staff.
Project Schedule
Engineer will develop a master project engineering schedule in critical path format that includes major design activities. The schedule will be updated monthly.
Project Costs & Weekly Reporting
Engineer will review engineering labor on a monthly basis during design to track estimated and actual costs. Engineer will provide a weekly progress report including general
Detailed Design
Design Documents
Drawings and specifications will be provided by Engineer at the 60% design level. The 60%
Documents will include the following:
Technical Specifications
Drawings included in the 30% design package brought to 60% completion
Additional detailed drawings needed for final design
The Owner and NMED will be given at least one (1) week to review the drawings and specifications prior to holding the 60% Design Review Meeting. PDF documents will be provided to the Owner and NMED for review.
Cost Estimating
Based on the 60% design documents, Engineer will prepare an updated engineer’s opinion of probable cost for the Project. This cost opinion will be submitted to NMED and Owner for review. The cost opinion will be based on recent bid tabulation information, historical cost data, and discussions with local suppliers and contractors. Costs developed at this stage are assumed to be in general conformance with AACE Class 3.
Estimates, schedules, forecasts, and projections prepared by Engineer relating to loads, interest rates and other financial analysis parameters, construction costs and schedules, operation and maintenance costs, equipment characteristics and performance, and operating results are opinions based on Engineer’s experience, qualifications, and judgment as a professional. Since
Engineer has no control over weather, cost and availability of labor, cost and availability of material and equipment, cost of fuel or other utilities, labor productivity, construction contractor’s procedures and methods, unavoidable delays, construction contractor’s methods of determining prices, economic conditions, government regulations and laws (including the interpretation thereof), competitive bidding or market conditions, and other factors affecting such estimates or projections, Engineer does not guarantee that actual rates, costs, quantities, LVNM WTP SOW performance, schedules, etc., will not vary significantly from estimates and projections prepared by Engineer.
Design Review Meeting
After the 60% design document review period, Engineer will conduct a 60% design review meeting at the Owner’s offices to be attended by the design manager and process engineer(s).
The purpose of this meeting is to provide the Owner and NMED an opportunity to clarify comments on the documents. Comments will be incorporated into the 90% design documents as appropriate.
Design
Design Documents
Drawings and specifications will be provided by Engineer at the 90% design level. The 90%
Documents will include the following:
Refined Technical Specifications
Drawings included in the 60% design package, brought to 90% completion
Additional detail drawings needed for final design or bidding
The Owner and NMED will be given at least one (1) week to review the drawings and specifications prior to holding the 90% Design Review Meeting. PDF documents of the drawings will be provided to the Owner and NMED for review.
Cost Estimating
Based on the 90% design documents, Engineer will prepare an updated engineer’s opinion of probable cost for the Project. This cost opinion will be submitted to NMED and Owner for review. The cost opinion will be based on recent bid tabulation information, historical cost data, and discussions with local suppliers and contractors. Costs developed at this stage are assumed to be in general conformance with AACE Class 3.
Estimates, schedules, forecasts, and projections prepared by Engineer relating to loads, interest rates and other financial analysis parameters, construction costs and schedules, operation and maintenance costs, equipment characteristics and performance, and operating results are opinions based on Engineer’s experience, qualifications, and judgment as a professional. Since
Engineer has no control over weather, cost and availability of labor, cost and availability of material and equipment, cost of fuel or other utilities, labor productivity, construction contractor’s procedures and methods, unavoidable delays, construction contractor’s methods of determining prices, economic conditions, government regulations and laws (including the interpretation thereof), competitive bidding or market conditions, and other factors affecting such estimates or projections, Engineer does not guarantee that actual rates, costs, quantities, performance, schedules, etc., will not vary significantly from estimates and projections prepared by Engineer.
Design Review Meeting
After the 90% design document review period, Engineer will conduct a 90% design review meeting at the Owner’s offices to be attended by the design manager and process engineer(s).
The purpose of this meeting is to provide the Owner and NMED an opportunity to clarify comments on the documents. Comments will be incorporated into the IFB design documents as appropriate.
Permitting & Stakeholder Communication
Design Consultant Discussions LVNM WTP SOW
Engineer will support the Owner in project discussions between stakeholders and other engineering design consultants. This task includes virtual meetings with stakeholders and/or consultants who are directly involved in design and future phasing of associated infrastructure including reservoir and distribution system upgrades and installation of GAC at the existing
WTP. This task assumes one (1) meeting per week through 60% design and two (2) meetings per month for the remainder of design. Meetings will be attended by the design manager and process engineer.
NMED Permitting
Engineer will work with NMED for permitting and project approval requirements. Permit applications and necessary documents will be prepared and provided to the Owner for signature and submittal as required. Owner and/or Contractor will be responsible for all permitting fees.
General Permitting
Engineer will develop and maintain a permitting matrix identifying required approvals, submittal requirements, responsible parties, sequencing, and review durations. The matrix will be updated throughout design and will be utilized to identify, track, and support procurement of environmental clearances and regulatory approvals required for the design and construction of the new WTP.
Miscellaneous Support
Water Sampling
Engineer will work with Owner-contracted analytical laboratories to perform raw water sampling and testing to evaluate raw water quality characteristics that will impact treatment.
This task assumes that Engineer will provide two (2) staff members to sample from raw water sources and ship the collected water to Owner-contracted analytical laboratories. This task assumes that one (1) sampling event will occur every two weeks for an eight-week period for a total of four (4) sampling events to complete winter trend analysis, and that one (1) sampling event will occur every two weeks for a sixteen-week period for a total of (8) sampling events to establish summer trend analysis. Engineer has assumed that the cost for all lab equipment, consumables and outside water quality laboratory work would be paid by the Owner.
Engineer will use the results of the sampling and testing in the design basis document. This design basis will be used to size the technology and other scope items to support the overall design.
Issued for Bid Documents and Bid Phase Services
Issue for Bid Design Documents
Engineer will prepare and submit Issue for Bid drawings and specifications to the Owner and
NMED for bidding purposes. The drawings and specifications will incorporate final Owner and
NMED comments prior to bidding, as appropriate.
Furnish one (1) electronic copy of the Issue for Bid documents to Owner and NMED
Bidding or Negotiating Phase
Engineer will assist NMED in advertising for and obtaining bids or proposals for the Work, assist NMED in issuing assembled design, contract, and bidding-related documents (or requests for proposals or other construction procurement documents) to prospective contractors, and, where applicable, maintain a record LVNM WTP SOW of prospective contractors to which documents have been issued, attend pre-bid conference, if any, and receive and process contractor deposits or charges for the issued documents.
Engineer will prepare and issue addenda as appropriate to clarify, correct, or change the issued documents. This task assumes three (3) addenda.
Engineer will attend the Bid Opening at the location established by NMED and develop a Bid
Tabulation summary identifying the bid price provided by each bidder and confirming that the bidder submitted required documentation with their respective bids.
Consult with NMED as to the qualifications of prospective contractors and contractor’s proposed subcontractors, suppliers, and other individuals and entities, for those portions of the Work as to which review of qualifications is required by the issued documents. Provide information or assistance needed by NMED during review of proposals or negotiations with prospective contractors.
If the issued documents require, the Engineer will evaluate and determine the acceptability of
"or equals" and substitute materials and equipment proposed by prospective contractors, provided that such proposals are allowed by the bidding-related documents (or requests for proposals or other construction procurement documents) prior to award of contracts for the
Work.
If NMED engages in negotiations with bidders or proposers, assist NMED with respect to technical and engineering issues that arise during the negotiations.
The inclusion of any contractor or subcontractor on the list of bidders does not constitute any endorsement or warranty by the Engineer, and NMED will exercise its own due diligence in reviewing the qualifications and experience, and check the references of, any prospective contractor or subcontractor, and in making a final selection of the qualified contractor and subcontractors for this Project.
Issued for Construction (IFC) Documents
Furnish one (1) electronic PDF of the issued for construction drawings and specifications to
Owner and NMED
Engineer will prepare and submit issued for construction drawings and specifications. The drawings and specifications will incorporate bidding addenda prior to submitting.
This contract does not authorize Burns & McDonnell to perform construction services, act as a general contractor, conduct subcontractor bidding, procure equipment or materials on behalf of the State, or manage construction contractors.
All construction procurement, contractor selection, and material purchasing will be conducted separately by the State of New Mexico in accordance with the New Mexico Procurement Code.
The State of New Mexico retains sole responsibility for compliance with IGA Intergovernmental
Agreement No. 25-667-4000-0001 (IGA). The IGA is separate from and not incorporated into this
Contract Agreement.
V. Provide a detailed explanation of the criteria developed and specified by the agency as necessary to perform and/or fulfill the contract and upon which the state agency reviewed available sources. (Do not use “technical jargon;” use plain English. Do not tailor the criteria simply to exclude other contractors if it is not rationally related to the purpose of the contract.)
Following the Hermits Peak/Calf Canyon Fire and recurring post-fire flooding, the City of
Las Vegas’ water treatment system has experienced significant operational instability due to elevated turbidity, sediment loading, and debris flows originating from the burn scar.
These conditions pose continuing risks to public health and water reliability.
The State entered into an Intergovernmental Agreement with the City to support stabilization and long-term engineering planning. In furtherance of this effort, Burns &
McDonnell was engaged to conduct engineering assessments, evaluate treatment performance, perform field investigations, and develop preliminary engineering documentation.
The criteria developed for contractor evaluation included:
• Demonstrated expertise in municipal drinking water treatment engineering
• Experience addressing post-wildfire watershed impacts on treatment systems
• Ability to provide immediate and continuous engineering support
• Familiarity with site-specific system deficiencies and watershed behavior
• Experience coordinating with state and federal regulatory entities
• Capacity to advance preliminary engineering documentation without duplication of prior work
The Burns & McDonnell team mobilized in early September 2025, and has remained continuously on the ground, actively planning, testing, evaluating an emergency procurement, and investigating system performance in close coordination with City staff, contractors, regulators, and technical consultants. Within the first 30 days, the team fully integrated with all project stakeholders, established governance and execution frameworks, and deployed qualified personnel who are actively delivering services today.
With the formal decision now made to fully rebuild the water treatment facility, Burns &
McDonnell is uniquely positioned to engineer this reconstruction on the most accelerated and least risky timeline possible through planning and design services. Given its existing presence, deep institutional knowledge of site conditions, established coordination mechanisms, and firsthand understanding of the exigent operational environment, Burns &
McDonnell offers the most seamless path to execution and the lowest risk of delay in delivering permanent water treatment solutions.
Any transition to a new vendor at this stage would introduce substantial delays measured in weeks or months at a time when continued system failure poses an ongoing threat to public health and safety. In light of the urgent need, the complexity of post-fire watershed conditions, and the critical reliance of the City of Las Vegas on a reliable drinking water supply, Burns & McDonnell is the only entity capable of delivering the required speed, integration, and technical expertise necessary to implement permanent water treatment infrastructure without jeopardizing schedule or public safety.
VI. Provide a detailed, sufficient explanation of the reasons, qualifications, proprietary rights or unique capabilities of the prospective contractor that makes their company the only source capable of providing the required professional service, general service, construction or item(s) of tangible personal property. (Please do not state the source is the “best” source or the “least costly” source. Those factors do not justify a “sole source.”)
Burns & McDonnell is uniquely qualified to provide the required professional engineering services due to its direct and ongoing involvement in evaluating and developing engineering solutions for the City of Las Vegas water treatment system.
The firm has:
• Conducted field investigations and performance evaluations under active post fire conditions
• Developed preliminary engineering documents currently relied upon by the State
• Coordinated with regulators regarding treatment requirements
• Established engineering baselines specific to watershed driven water quality variability
This firsthand technical knowledge cannot be replicated without significant reanalysis and delay.
The services required under this contract are professional engineering services only. The sole source determination is based on continuity of engineering work, preservation of technical assumptions, and avoidance of duplicative analysis not on construction execution.
Replacing Burns & McDonnell at this stage would introduce delays measured in months and require re-establishment of analytical frameworks, thereby increasing schedule risk and prolonging system instability.
VII. Provide a detailed, sufficient explanation of how the professional service, general service, construction or item(s) of tangible personal property is/are unique and how this uniqueness is substantially related to the intended purpose of the contract.
The uniqueness of the services lies in Burns & McDonnell’s established institutional knowledge and prior engineering work specific to the City’s post-wildfire water treatment challenges.
The firm has already:
• Developed engineering documentation tailored to burn-scar hydrology
• Conducted system-specific testing and data collection
• Established design parameters responsive to highly variable turbidity conditions
• Coordinated with stakeholders regarding regulatory compliance requirements
Continuity of engineering services ensures consistency in technical assumptions, methodology, and regulatory coordination. Engaging a different engineering firm would necessitate duplication of data analysis, redesign of treatment approaches, and repetition of regulatory consultation.
This sole source request is limited to professional engineering services and does not include construction, construction management, or procurement authority.
VIII. Provide a narrative description of the agency’s due diligence in determining the basis for the procurement, including procedures used by the agency to conduct a review of available sources such as researching trade publications, industry newsletters and the internet;;
contacting similar service providers; and reviewing the State Purchasing Divisions’
Statewide Price Agreements. Include a list of businesses contacted (do not state that no other businesses were contacted), date of contact, method of contact (telephone, mail, e-mail, other), and documentation demonstrating an explanation of why those businesses could not or would not, under any circumstances, perform the contract; or an explanation of why the agency has determined that no businesses other than the prospective contractor can perform the contract.
NMED conducted a rigorous and structured due-diligence process to identify the most qualified design-build firm for the City of Las Vegas Water Treatment Plant, consistent with industry best practices for emergency situation procurements. The evaluation emphasized transparency, fairness, and alignment with the project’s urgent public-health objectives. Firms were assessed against comprehensive criteria, including demonstrated water treatment plant experience, true in-house design-build capability, eligibility for government contracting schedules, experience delivering projects in New Mexico, availability of local personnel, and the capacity to meet an aggressive schedule. Outreach and market research showed that many firms lacked integrated design-build capabilities, would require joint ventures that could introduce delays, or were unable to mobilize quickly enough to meet project timelines.
Using a structured, weighted evaluation and risk assessment approach, NMED prioritized firms with proven capacity, local presence, and readiness to perform under emergency conditions. Through this process, Burns & McDonnell clearly emerged as the only firm that met all criteria. Burns & McDonnell demonstrated true design-build capability, a strong New Mexico presence with an established Albuquerque office and local staff, extensive statewide experience, and the ability to immediately mobilize and maintain the required schedule. Given that Burns & McDonnell is already advancing preliminary engineering and procurement planning, restarting the selection process would result in significant delays and jeopardize timely delivery of safe drinking water. Based on this best practice driven evaluation.
The New Mexico Environment Department is seeking a sole source for professional services with Burns & McDonnell for the City of Las Vegas, New Mexico Water Treatment
Plant based on urgent public-health needs and clear schedule and continuity advantages.
Burns & McDonnell is already advancing preliminary engineering, procurement planning, and early design activities, and shifting to a competitive procurement at this stage would result in an estimated 4–6-month delay. Such a delay would require duplicating completed work, disrupt current momentum, and significantly jeopardize the timely delivery of safe drinking water to Las Vegas residents.
Burns & McDonnell offers a unique combination of immediate readiness, technical strength, and local expertise that cannot be replicated without substantial risk. The firm has established an accelerated design-build schedule that incorporates early procurement and early site mobilization, saving months compared to a traditional design-bid-build approach.
With a strong New Mexico presence, extensive statewide experience, a large bench of licensed professionals, and proven safety and risk-management practices, Burns &
McDonnell is uniquely positioned to deliver this project under emergency conditions.
Awarding this sole source contract is necessary to preserve schedule, protect public health, and ensure uninterrupted progress toward a reliable water supply for the City of Las Vegas.
At this stage, replacing Burns & McDonnell is not a viable option without causing significant and unacceptable risk to public health. Any transition to another contractor would require restarting design and procurement activities, resulting in a minimum 4–6-month delay, loss of critical momentum, and jeopardizing the timely delivery of safe and reliable drinking water to the City of Las Vegas. Therefore, Burns & McDonnell is the only viable option and reason on why NMED is seeking a sole source procurement.
We are not including other firms contacted as we have already engaged with Burns &
McDonnell and are requesting a transition to sole source.
Certified by: Date:____________________
Agency Chief Procurement Officer
Agency Approval by: Date: ____________________
Cabinet Secretary/Agency or Entity Head or Designee
APPROVED: Date:____________________
State Purchasing Agent
If this sole source is being submitted by a governmental agency or governmental entity not under the final authority of the State Purchasing Agent, the State Purchasing Agent’s signature is not required. The signature line may be removed from this form or marked as N/A. Hard Copy
Documentation for Courtesy Postings do not need to be submitted to SPD for approval.
Docusign Envelope ID: A5AA494B-0B26-4CCB-99C1-6195FDA6B5C7
3/6/2026
3/6/2026
Certificate Of Completion Envelope Id: A5AA494B-0B26-4CCB-99C1-6195FDA6B5C7 Status: Completed
Subject: Complete with Docusign: Burns sole-source-determination-form-v2025-dmm-1025 3.6 cp.docx
Source Envelope:
Document Pages: 10 Signatures: 2 Envelope Originator:
Certificate Pages: 5 Initials: 0 Charlette Probst
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC-07:00) Mountain Time (US & Canada)
1100 S Saint Francis Dr
Santa Fe, NM 87502 charlette.probst@gsd.nm.gov
IP Address: 174.238.227.6
Record Tracking Status: Original
3/6/2026 4:28:22 PM
Holder: Charlette Probst charlette.probst@gsd.nm.gov
Location: DocuSign
Security Appliance Status: Connected Pool: StateLocal
Storage Appliance Status: Connected Pool: General Services Department Location: Docusign
Signer Events Signature Timestamp Charlette Probst charlette.probst@gsd.nm.gov
State Purchasing Division CPO
Security Level: Email, Account Authentication (None) Signature Adoption: Pre-selected Style
Using IP Address: 174.238.227.6
Sent: 3/6/2026 4:31:39 PM
Viewed: 3/6/2026 4:31:50 PM
Signed: 3/6/2026 4:32:00 PM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
John Rhoderick
John.Rhoderick@env.nm.gov
Deputy Cabinet Secretary of Administration
ENV
Signing Group: 66700 - Cabinet Secretary
Security Level: Email, Account Authentication (None)
Signature Adoption: Pre-selected Style
Using IP Address: 73.26.161.167
Sent: 3/6/2026 4:32:01 PM
Viewed: 3/6/2026 6:02:36 PM
Signed: 3/6/2026 6:02:48 PM
Electronic Record and Signature Disclosure:
Accepted: 10/25/2024 8:18:11 AM ID: 680e865f-1c7d-4e6e-ab3d-f3572a97bc57
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Summary Events Status Timestamps Envelope Sent Hashed/Encrypted 3/6/2026 4:31:39 PM
Certified Delivered Security Checked 3/6/2026 6:02:36 PM
Signing Complete Security Checked 3/6/2026 6:02:48 PM
Completed Security Checked 3/6/2026 6:02:48 PM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
A. ELECTRONIC RECORD AND SIGNATURE DISCLOSURE (ERSD)
From time to time, New Mexico General Services Department (GSD), on behalf of the State of
New Mexico (SONM), may be required by law to provide you with certain written notices or disclosures. Stated below are the terms and conditions for GSD's providing you such notices and disclosures electronically through the DocuSign system. Please read this information carefully. If you are able to access this information electronically and agree to this Electronic Record and
Signature Disclosure (ERSD), please confirm your agreement by selecting the check-box next to “I agree to use electronic records and signatures” before clicking “CONTINUE” within the
DocuSign system.
B. Obtaining paper copies
At any time up to twenty (20) calendar days following your use of DocuSign to electronically sign a document, you may request a paper copy of any record provided or made available electronically to you by GSD. You will have the ability to download and print documents SONM sends you through the DocuSign system during and immediately after the signing session and, if you elect to create a DocuSign account, you may access the documents for a twenty (20) calendar day period after such documents are first sent to you. Following the twenty (20) day period, if you want GSD to send you paper copies of any such documents from GSD's office, you will be charged a $1.00 per-page fee plus postage. You may request delivery of such paper copies from GSD by following the procedure stated in Section H, below.
C. Withdrawing your consent
If you decide to receive notices and disclosures from GSD electronically, you may at any time change your mind and inform GSD you want to receive required notices and disclosures only in paper format. The procedure concerning how you may inform GSD of your decision to receive future notices and disclosures in paper format as well as withdraw your consent to receive notices and disclosures electronically is stated in Section D, immediately below.
D. Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the speed with which GSD will be able to complete certain steps in specific transactions and deliver paper copies to you. GSD will need: (1) to send the required notices or disclosures to you in paper format; and (2) wait until GSD receives your acknowledgment of your receipt of such paper notices or disclosures. Further, you will no longer be able to use the DocuSign system to receive required notices and consents electronically from SONM or to electronically sign documents generated and sent to you from SONM.
Electronic Record and Signature Disclosure created on: 4/14/2020 1:18:28 PM Parties agreed to: John Rhoderick
E. All notices and disclosures will be sent to you electronically
Unless you inform GSD otherwise according to these procedures, GSD will electronically provide you through the DocuSign system all required notices, disclosures, authorizations, acknowledgements and other documents that are required to be provided or made available to you during the course of your electronic signature relationship with SONM. To reduce the possibility of inadvertent non-receipt, GSD prefers to provide all required notices and disclosures by the same method and to the same email or physical address that you furnish to GSD. Thus, you may receive the disclosures and notices electronically or in paper form. If you do not agree with this procedure, please inform GSD according to the procedures stated in Section I, below.
Please also refer to Section D, immediately above, which states the consequences resulting from your declination of electronic delivery of notices and disclosures.
F. How to contact GSD:
You may inform General Services Department (GSD) of any changes you select regarding State
Purchasing Division’s (SPD) electronic communications with you, to request paper copies of certain information from SPD, and to withdraw your prior consent to receive notices and disclosures electronically by emailing your request(s) to SPD at: GSD.SPDinfo@state.nm.us
G. To advise SPD of your new email address
To inform SPD of a change in the email address to which SPD sends you notices and disclosures electronically, you must send an email to SPD at GSD.SPDinfo@state.nm.us and in the body of such request you must include your previous and new email addresses.
H. To request paper copies from SPD
To request delivery of paper copies of electronic notices and disclosures that DocuSign and/or
SPD have previously provided to you, you must send an email to SPD at
GSD.SPDinfo@state.nm.us and in the body of your email request state your email address, full name, mailing address, and telephone number. SPD will charge you a $1.00 per page copy fee plus postage.
I. To withdraw your consent with SPD
To inform SPD that you no longer wish to receive notices and disclosures in electronic format you may:
(1) Decline to sign a document from within a signing session, and on the subsequent page, select the check-box indicating you wish to withdraw your consent, or you may:
(2) Send SPD an email to GSD.SPDinfo@state.nm.us and in the body of your request state your email address, full name, mailing address, and telephone number.
J. Required hardware and software
The minimum system requirements for using the DocuSign system may change over time. The current DocuSign system requirements may be found at:
https://support.docusign.com/guides/signer-guide-signing-system-requirements
K. Acknowledging your access and consent to receive and sign documents electronically
To confirm that you are able to electronically access the information contained in this Electronic
Record and Signature Disclosure (ERSD), please confirm that you have: (1) read this ERSD, and either: (2) you are able to print on paper or electronically save this ERSD for your future reference and access; or (3) you are able to email this ERSD to an email address where you will be able to print this ERSD on paper and/or save this ERSD for your future reference and access.
Further, if you consent to receiving notices and disclosures from DocuSign and/or SPD exclusively in electronic format, then select the check-box next to “I agree to use electronic records and signatures,” before you click “CONTINUE” within the DocuSign system.
By selecting the check-box next to “I agree to use electronic records and signatures,” you confirm that:
You have read this Electronic Record and Signature Disclosure (ERSD); and
You can print this ERSD on paper, or you can save and/ or send this ERSD to a location where you can print this ERSD, for your future reference and access; and
Until or unless you notify SPD as stated in this ERSD, you consent to exclusively receive through electronic means all notices, disclosures, authorizations, acknowledgements, and other documents that are required to be provided or made available to you by SPD during the course of your electronic signature relationship with SPD.
https://support.docusign.com/guides/signer-guide-signing-system-requirements
| I. Name of Agency: New Mexico Environment Department |
| B. Obtaining paper copies |
| C. Withdrawing your consent |
| D. Consequences of changing your mind |
| E. All notices and disclosures will be sent to you electronically |
| F. How to contact GSD: |
| G. To advise SPD of your new email address |
| H. To request paper copies from SPD |
| I. To withdraw your consent with SPD |
| J. Required hardware and software |
| K. Acknowledging your access and consent to receive and sign documents electronically |
| 2026-03-08T07:45:40-0700 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .