This is a Specifications/Requirements Confirmation Form for RFQ 2026-0039 issued by the Savannah Airport Commission in Georgia for the procurement of three (3) new, roll-off self-contained trash compactors. The compactors must be 35-yard capacity units with specifications that meet or exceed the RUDCO RP-3500SB model, including a 10 HP motor, 10.5 GPM pump, 33-second cycle time, and normal ram force of 39,900 pounds. The procurement seeks to maintain consistency with existing equipment currently operated by the Airport. Vendors must confirm compliance with all specified requirements on the form and note any exceptions on a designated Exceptions Sheet. The request includes comprehensive documentation requirements, including two copies of complete parts, shop repair, and operator manuals in paper or digital format, a factory-recommended preventative maintenance schedule, and a minimum of two sets of keys.
The manufacturer's factory warranty must provide a minimum of three years on structural components, two years on parts and major operating components, and one year on labor, with all warranty repairs including replacement parts, labor, service-call charges, and technician travel expenses at no cost to the owner. The Savannah Airport Commission will award the contract to the most responsible and responsive bidder at the lowest cost. No dealer advertising is permitted on any unit. Vendors must provide a complete copy of the manufacturer's warranty with their bid proposal, clearly identifying any exclusions, prorated coverage, deductibles, travel charges, maintenance requirements, or other warranty limitations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 2026-0039
Three (3) Self-Contained Compactors
SPECIFICATIONS/REQUIREMENTS CONFIRMATION FORM
SPECIFICATIONS: Vendors shall place a checkmark next to each requirement/specification that is applicable and inclusive with the compactors. For any requirement or specification that is not included, please leave the corresponding circle blank and clearly note the exception on the designated Exceptions Sheet.
Minimum Requirements:
The Commission will award the most responsible and responsive bidder at the lowest cost.
The specified roll-off, self-contained trash compactor has been identified based on the Savannah Airport Commission's current ownership and operation of similar equipment.
The intent is to maintain consistency with the existing compactors currently in use at the Airport. Unless otherwise stated, products equal to the identified brand name and model will be acceptable, provided they meet or exceed the minimum requirements for quality, workmanship, durability, economy of operation, and suitability for the intended purpose.
Model and Manufacturer known to meet these requirements:
o RUDCO RP-3500SB Self-Contained Compactor.
General Specifications
Minimal Requirements: must meet or exceed the following specifications for:
o Model: RP3500SB RUDCO Self-Contained Compactor (3 Each) o Size: 35 Yard o Motor: 10 HP Motor TEFC o Pump: 10.5 GPM o Oil level Site Gauge with Thermometer o Electrical: 3 Phase Electrical
Controls o UL Listed Relay Control Box o Push Button Start o Deadman/Hand Key Switch o Forward/Reverse Switch o Emergency Stop o 80% & 100% Container Full Lights (Standard and Manual Override) o PLC Operated Power Unit with 3 Multi-Cycle Setting Options o Cycle Time: 33 Seconds o Normal Ram Force: 39,900 o Maximum Ram Force: 44,000 o Packer Floor: ½" Plate o Packer Sides: ¼" Plate W/6" Channel o Ram Top: ¼" Plate o Ram Face: ½" Plate W/4"x3" Angle o Charge Box Cap.: MFG Rating 2.0 Cubic Yards o MSWMA Rating: 1.57 Cubic Yards o Charge Box Opening: 41"x60" o Two Grease Fittings Located Each Side of Charge Box for PM o Double End Pick-up o Ratings: ANSI Standards o Disconnects on Both Sides o Standard Factory Warranty
Detailed Specifications: Quality Assurance Products shall be Designed, Tested, Rated, and Certified in accordance with, and installed in compliance with all local, City, State and Federal Standards and Codes. All material and equipment shall meet or exceed existing material specifications. Material brand identified is used merely as a specification and not as a statement of a preference for the specific product identified. Unless otherwise stated, items equal to the identified brand name will be acceptable, considering quality, workmanship, economy of operation, and suitability for the purpose intended. Items must meet these minimum requirements.
o RUDCO RP-3S00SB SELF- CONTAINED COMPACTOR o CHARGE BOX CAP. - MFG. RATING 2.0 CUBIC YARDS o MSWMA RATING 1.57 CUBIC YARDS o CYCLE TIME 33 sec.
o NORMAL RAM FORCE 39,900 o MAXIMUM RAM FORCE 44,000 o NORMAL OPERATING PRESSURE 1750 o MAXIMUM OPERATING PRESSURE 2200 o CYLINDER (BORE x STROKE X ROD) (2) 4" x 30-88" x -2.5" o MOTOR 10 HP o PUMP SIZE 10.5 GPM o PACKER FLOOR 1/2" PLATE o PACKER SIDES 1/4" PLATE W/ 6" CHANNEL o RAM TOP 1/4" PLATE o RAM FACE 1/2" PLATE W/ 4" X 3" ANGLE o CHARGE BOX OPENING 41" X 60" o DIMENSION - A 104 - 1/2" o DIMENSION - B 282" o DIMENSION - C 204" o DIMENSION - D 67 - 3/4" o DIMENSION - E 41" o WEIGHT 11,331 lbs.
Additional Requirements:
o No dealer advertising is to be on any unit.
o All units delivered to the Savannah Airport Commission must be accompanied by two (2) copies of complete parts, shop repair, and operator's manuals through actual paper copies or digitally. The parts manuals must show all component parts including, but not limited to, component assemblies and their substitute components identified by manufacturers’ part number. Any component or sub-assembly not manufactured by the O.E.M. must be identified including the name of the manufacturer of said component and said manufacturer's part numbers and nomenclature. All parts information must be specific to the unit delivered to the Savannah Airport Commission.
All shop repair manuals will include but not be limited to the following:
o Complete disassembly instructions, adjustments and replacement procedures, wiring diagrams, hydraulic schematics {where applicable), hose routing, location and function of sensors, time standards where available, and trouble-shooting guide.
o All units must be accompanied by a factory recommended preventative maintenance schedule including procedures, time, hours, mileage intervals, pre-placement part numbers, and fluid specifications.
o All units must be accompanied with a minimum of 2 sets of keys.
o Factory Warranty: The self-contained compactors shall be provided with a manufacturer's factory warranty of not less than three (3) years on structural components, two (2) years on parts and major operating components, and one (1) year on labor, beginning on the date the equipment is placed into service and accepted by the owner.
The warranty shall cover defects in materials and workmanship under normal operation and shall include, at a minimum, the compactor structure and frame, ram, hydraulic power unit, hydraulic cylinders, pump, electric motor, electrical control panel, switches, sensors, and other factory-installed operating components.
During the applicable warranty period, warranty repairs shall include replacement parts, labor, service-call charges, and technician travel expenses associated with correcting a warrantable failure, at no additional cost to the owner.
The vendor shall provide a complete copy of the manufacturer's warranty with the bid. Any exclusions, prorated coverage, deductibles, travel charges, maintenance requirements, or other warranty limitations shall be clearly identified in the proposal.
| Minimum Requirements: |
| The Commission will award the most responsible and responsive bidder at the lowest cost. |
| The specified roll-off, self-contained trash compactor has been identified based on the Savannah Airport Commission's current ownership and operation of similar equipment. The intent is to maintain consistency with the existing compactors currently in... |
| Model and Manufacturer known to meet these requirements: |
| o RUDCO RP-3500SB Self-Contained Compactor. |
| General Specifications |
| Minimal Requirements: must meet or exceed the following specifications for: |
File details come from the government source that posted it. Updated .